Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberBLD12-00246
StatusFinaled
Name BRUCE POE
Site Address 6455 S EISENMAN RD
Project NameTK Bar
Customer Number 
ePlanReviewNo
Description
(TK BAR – Interior Demo / Early Start TI) This permit is to perform interior non-structural demo work and Early Start permit work as outlined within this scope of work only. Scope of work: includes removal of non-bearing interior partition walls, removal of interior finishes, removal of all existing outlets and wiring back to the box or properly terminated above ceiling line, removal of some existing light fixtures, construction to the framing stage including rough-in electrical, plumbing, and mechanical while the plans for the space are being reviewed (Major TI is submitted under BLD12-00197). Any construction not meeting code must be removed prior to framing inspection approval and any further construction being endorsed. This building is fully Fire Sprinklered with an approved Fire Alarm system. Any alterations or modifications to the buildings Fire Sprinkler or Fire Alarm system WILL REQUIRE A SEPARATE PERMIT and shall be installed per NFPA 13 & NFPA 72 as regulated by the Boise Fire Department. Do not remove ceiling unless sprinkler coverage is able to be maintained in accordance with the Boise City Fire Dept. **TLW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Third Notice 7/20/20127/24/2012 DONE
received 7-23
Third Notice 6/12/20127/6/2012 DONE
mailed to Bruce Poe
Second Notice 5/31/20126/7/2012 DONE
DetailsChristina Prado
faxed 6-7-12
First Notice4/3/20124/3/20125/17/2012 DONE
DetailsJim Storey
e-mailed to Bruce Poe
BLD-Final4/3/20124/3/20124/3/2012PDONE
DetailsJim Storey
DOC - Permit Finaled4/3/20124/3/20124/3/2012PPASS
DetailsJim Storey
BLD-Final3/27/20123/30/20123/30/2012ADEFR
DetailsJim Storey
Bruce Poe Phone #: ###-####
Application received  2/8/2012 DONE
Application submitted via PDS Online on Feb 8 2012 2:44PM
Plans ACCEPTED BY PLAN CHECK  2/8/2012 DONE
DetailsTim L. Woodard
Plan assigned to (TLW)2/8/2012 2/8/2012 DONE
DetailsTim L. Woodard
Routing - PLAN CHECK2/8/2012 2/8/2012 PASS
DetailsTim L. Woodard
1st review completed  2/8/2012 DONE
DetailsTim L. Woodard
PLANS/APPL TAKEN TO FRONT DESK  2/8/2012 DONE
DetailsTim L. Woodard
Case Summary (BLD)  2/8/2012 DONE
DetailsTim L. Woodard
Permit Ready to Issue  2/8/2012 DONE
DetailsChristina Prado
Inspection Record Card- Bld  2/8/2012 DONE
DetailsChristina Prado
Issue PAID IN FULL permit  2/8/2012 DONE
DetailsChristina Prado