Permit NumberBLD12-00336
StatusFinaled
Name SLETTEN CONSTRUCTION
Site Address 6001 W CASSIA ST
Project NameBorah High School Main Bldg
Customer Number 
ePlanReviewYes
Description
(BORAH HIGH SCHOOL - SEISMIC ENHANCEMENT - CLASSROOM WINGS A, B, AND C) To add full depth vertical truss blocks at 12 feet on center maximum spacing around the perimeter of the roofs of Classroom Wings A, B, and C to connect the existing overbuilt trusses installed in 1998 to the exterior bearing walls of the original building constructed in the 1950s. The truss blocks will have a 2x4 frame with a structural panel nailed to the frame. The structural panels will be about 2 feet wide by about 4 feet tall. The truss blocks are shear panels intended to tie the existing overbuild trusses to the original structure at the exterior of the building, thereby, improving the ability of the building to respond appropriately to seismic loads. The work is required to comply with the approved drawings, with the plan review report, and with all applicable codes and ordinances. The attic has a fire sprinkler system. The fire sprinkler system is required to be maintained in compliance with NFPA 13 as regulated by the Fire Department. The windows for all 3 classroom wings will be replaced under permit BLD12-00612. **CJW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Second Notice 3/1/20133/8/2013 DONE
This permit finaled on the web by Ron Hagen
First Notice2/1/20132/1/20132/19/2013 DONE
DetailsTom Arcoraci
BLD-Final1/31/20132/1/20132/1/2013PPASS
DetailsTom Arcoraci
DOC - Permit Finaled2/1/20132/1/20132/1/2013PPASS
DetailsTom Arcoraci
FIRE-Final Inspection1/31/20132/1/20132/1/2013PPASS
DetailsForrest France
Site inspection passed.
BLD-Framing/Rough-in1/30/20131/31/20131/31/2013PPASS
DetailsTom Arcoraci
Access to attic areas must be after 3:30 PM, Per Boise School Dist. Please call John Hanson at # listed above, Thank-You. Phone #: ###-#### >> Inspection requested via web by John Hanson
Permit Ready to Issue  1/18/2013  
Inspection Record Card- Bld  1/18/2013 DONE
Issue PAID IN FULL permit  1/18/2013 DONE
(F) Reprint permit  1/18/2013 DONE
Inspection Record Card- Bld  1/18/2013 DONE
Inspection Record Card- Bld  1/18/2013 DONE
Extend Review Timeline  9/14/2012 DONE
DetailsChristina Prado
Extend Review Timeline  9/14/2012 DONE
DetailsChristina Prado
Plan assigned to (CJW)3/15/20123/15/20125/1/2012 PASS
DetailsCarl Westfall
BORAH HIGH SCHOOL - STRUCTURAL UPGRADE (20 days - April 11) ePlanReview case
Routing - PLAN CHECK4/27/2012 5/1/2012 PASS
DetailsCarl Westfall
Workflow in ePlanReview "returned" by Architect.
PLANS/APPL TAKEN TO FRONT DESK  5/1/2012 DONE
Telephone call  4/27/2012 DONE
Talked to another of Boise City's Consultant Structural Engineers. He seemed to confirm that the proposed structural changes were an enhancement.
Telephone call  4/27/2012 DONE
Talked to Bill Hamlin. Explained that he needs to go into ePlan and accept his task and then sign off the task.
Routing Off Site - STRUCTURAL4/24/2012 4/26/2012 PASS
DetailsCarl Westfall
E-mailed a copy of each drawings plus the Project Structural Engineer's written defence for the proposed structural changes to one of Boise City's Consultant Structural Engineer's. He responded in a letter confirming that the proposed structural changes are a seismic enhancement.
Plan Reviewer's activity  4/24/2012 DONE
Attached the drawings for the proposed seismic "upgrade" along with a description of the project structural engineer's rational to an E-mail and sent it to the original structural engineer for the roof overbuild project (that engineer is also a consultant for the Building Department).
Plan resubmittals received  4/20/2012 DONE
Bill Hamlin E-mailed a copy of a letter signed by Eric Wolfe, Project Engineer, and dated April 16, 2012. The letter defends his rational for the proposed structural changes.
Meeting  4/16/2012 DONE
Met with the Architect, the Project Structural Engineer, and a representative of the school district to discuss a way forward. The Project Structural Engineer was to provide a written defence for his design and it would be sent to a Consultant Structural Engineer for review.
Route to Impact Fee Review3/21/20123/26/20123/27/2012 PASS
DetailsCindy M. Gould
Structure improvements no impact fees
Routing - PLAN CHECK3/15/2012 3/21/2012 FAIL
DetailsCarl Westfall
The IBC plan review was started on Mar 20 and finished the next day. Additional structural analysis was required. See the plan review report.
1st review completed  3/21/2012 FAIL
Routing - FIRE3/15/2012 3/19/2012 PASS
DetailsScott Arellano
No comments attached.
Routing - Erosion and Sediment3/15/2012 3/16/2012 PASS
DetailsClint A Smith
ESC12-00138 plan waiver approved with conditions attached to the permit.
Pending Assignment by JCB3/15/2012 3/15/2012 DONE
DetailsJason Blais
Intake Approval  3/15/2012 PASS
DetailsSam Zahorka
Payment Received  2/22/2012 DONE
Payment received via Govolutions
Application received  2/22/2012 DONE
Application submitted via PDS Online on Feb 22 2012 12:30PM
Intake Approval  2/22/2012 FAIL