Third Notice | | 9/26/2012 | 9/25/2012 | | DONE |
|
|
|
|
Second Notice | | 9/3/2012 | 9/21/2012 | | DONE |
|
|
|
|
First Notice | | 8/13/2012 | 8/24/2012 | | DONE |
|
|
|
|
FIRE-Final Inspection | 8/2/2012 | 8/3/2012 | 8/3/2012 | A | PASS |
Troy Cobbley
|
|
|
life safety passed
|
BLD-Final | 7/30/2012 | 7/31/2012 | 8/3/2012 | A | DEFR |
Jim Storey
|
|
|
|
BLD-Final | 8/3/2012 | 8/3/2012 | 8/3/2012 | A | PASS |
Jim Storey
|
|
|
final ok
|
Permanent Occupancy | | | 8/3/2012 | | DONE |
|
|
|
|
FIRE-Final Inspection | 7/30/2012 | 7/31/2012 | 7/31/2012 | A | FAIL |
Troy Cobbley
|
|
|
Repair emergency lights.
|
BLD-Final | 7/30/2012 | 7/30/2012 | 7/30/2012 | A | DEFR |
Jim Storey
|
|
|
|
BLD-Final | 7/25/2012 | 7/25/2012 | 7/30/2012 | P | NR |
Jim Storey
|
|
|
|
BLD-Conference | 7/5/2012 | 7/5/2012 | 7/5/2012 | A | DONE |
Troy Cobbley
|
|
|
Jim and I met with the general contractor to discuss outstanding issues for sign offs on pnhase 1,2, and 3. Jim is going to take care of the door hardware requirements.
|
BLD-Conference | 7/5/2012 | 7/5/2012 | 7/5/2012 | A | PASS |
Jim Storey
|
|
|
need to provide hardware listing for exit door instaled under previous permit.
|
FIRE-Final Inspection | 6/28/2012 | 6/28/2012 | 6/28/2012 | P | FAIL |
Troy Cobbley
|
|
|
The issues with the project related fire alarm permit, for phase I, needs to be addressed. Egress issues may be present for the exterior doors that currently utilize door magnets. Tom (building superintendant), Jim Storey and I are going to meet and discuss the issue and possible solutions.
|
BLD-Final | 6/26/2012 | 6/27/2012 | 6/27/2012 | A | PART |
Jim Storey
|
|
|
pending fire/ wip for ramp and handrailing/ ok to instal equment.
|
FIRE-Conference | 6/22/2012 | 6/22/2012 | 6/22/2012 | P | DONE |
Troy Cobbley
|
|
|
The project super intendant and I went over fire extinguishers and exit signs.
|
BLD-Framing/Rough-in | 5/23/2012 | 5/23/2012 | 5/23/2012 | P | PASS |
Jim Storey
|
|
|
wall framing at old dock area ok to cover// scope of work is added to orig. permit of server space. up dated ele permit will be forth coming to this bld.
|
BLD-Conference | 5/3/2012 | 5/3/2012 | 5/3/2012 | A | PASS |
Jim Storey
|
|
|
framing ok/ reviewed progress ok.
|
BLD-Framing/Rough-in | 4/10/2012 | 4/10/2012 | 4/10/2012 | P | PASS |
Jim Storey
|
|
|
Justin Phone #: ###-####
|
BLD-Wall cover | 4/6/2012 | 4/6/2012 | 4/6/2012 | A | PART |
Jim Storey
|
|
|
gyp screwing ok at n and s interior sde walls.
|
BLD-Other | 4/5/2012 | 4/6/2012 | 4/6/2012 | A | CANC |
Jim Storey
|
|
|
fpp roof // perimtor screwing not complet// gyp screwing ok at n and s interior sde walls.
|
BLD-Framing/Rough-in | 4/4/2012 | 4/5/2012 | 4/5/2012 | A | PASS |
Jim Storey
|
|
|
FPP wall framing ok
|
BLD-Framing/Rough-in | 4/3/2012 | 4/4/2012 | 4/4/2012 | A | FAIL |
Jim Storey
|
|
|
FPP am appointment need header screw sch at king studs// rafter clip complet king stud screw penatration.
|
BLD-Conference | 3/27/2012 | 3/28/2012 | 3/28/2012 | A | PASS |
Jim Storey
|
|
|
am appointment// reviewed 1 hr const requirments.
|
BLD-Conference | 3/21/2012 | 3/21/2012 | 3/21/2012 | P | PART |
Jim Storey
|
|
|
wip
|
CHANGE STATUS TO (ISS) | | | 3/9/2012 | | DONE |
Tisha Gallop
|
|
|
status changed out of issue by mistake
|
Routing - FIRE | 3/6/2012 | | 3/9/2012 | | PASS |
Tim Frost
|
|
|
|
Routing - PLAN CHECK | 3/7/2012 | | 3/7/2012 | | |
|
|
|
|
BLD-Footing | 3/6/2012 | 3/6/2012 | 3/6/2012 | P | PASS |
Jim Storey
|
|
|
ft ok/ rebar ok per plan. recieved si scope and meet in the field.
|
OVERRIDE | | | 3/1/2012 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 3/1/2012 | | DONE |
Tisha Gallop
|
|
|
|
Telephone call | | | 3/1/2012 | | DONE |
Christina Prado
|
|
|
Called and gave Byron fees due and advised GC & RP are needed
|
Permit Ready to Issue | | | 3/1/2012 | | DONE |
Christina Prado
|
|
|
|
Plan assigned to (301) | 2/29/2012 | 2/29/2012 | 2/29/2012 | | DONE |
Jim Storey
|
|
|
|
Plan assigned to (301) | 2/27/2012 | 2/27/2012 | 2/29/2012 | | PASS |
Jim Storey
|
|
|
|
Print Pending Permit.LaserJet4 | | | 2/29/2012 | | |
|
|
|
|
1st review completed | | | 2/29/2012 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 2/29/2012 | | 2/29/2012 | | PASS |
Jim Storey
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/29/2012 | | DONE |
|
|
|
|
Print Occupancy Form | | | 2/29/2012 | | DONE |
Barbara Stitt
|
|
|
|
1st review completed | | | 2/29/2012 | | |
|
|
|
|
Routing - PLUMBING | 2/28/2012 | | 2/28/2012 | | PASS |
Jim Johnson
|
|
|
pass
|
Routing - MECHANICAL | 2/28/2012 | | 2/28/2012 | | PASS |
Troy James
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 2/27/2012 | | DONE |
Barbara Stitt
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 2/24/2012 | | DONE |
Tisha Gallop
|
|
|
|
Application received | | 2/23/2012 | 2/23/2012 | | DONE |
Barbara Stitt
|
|
|
|
Intake Approval | | | 2/23/2012 | | PASS |
Jim Storey
|
|
|
|