BLD-Final | 8/20/2012 | 8/21/2012 | 8/21/2012 | A | PASS |
Mike Jordan
|
|
|
ADAM Phone #: ###-####
|
DOC - Permit Finaled | 8/21/2012 | 8/21/2012 | 8/21/2012 | P | PASS |
Mike Jordan
|
|
|
All issues resolved.
|
BLD-Final | 8/14/2012 | 8/15/2012 | 8/15/2012 | A | FAIL |
Mike Jordan
|
|
|
Adam Phone #: ###-####. Egress window in upstairs bedroom must comply with Sec R612.2. Clear opening of window is less than 24 inches from finished floor and greater than 72 inches from finished grade. Due to being an egresss window, must comply with Sec R612.4.2 for compliance on egress opening limiting devices. Correction notice was posted.
|
BLD-Energy code compliance | 6/18/2012 | 6/18/2012 | 6/18/2012 | P | PASS |
Mike Jordan
|
|
|
Adam Phone #: ###-####
|
BLD-Framing/Rough-in | 6/12/2012 | 6/13/2012 | 6/13/2012 | P | PASS |
Mike Jordan
|
|
|
Adam Phone #: ###-####
|
BLD-Framing/Rough-in | 6/7/2012 | 6/8/2012 | 6/8/2012 | A | FAIL |
Mike Jordan
|
|
|
Adam Phone #: ###-####Provide attic access Aove master bedroom and living room, Complete lateral bracing on A2A atiic trusses, ACAP piggy back trusses require full bearing on bottom chord, repair bolts at garage portal frame. Correction notice posted, ok to insulate.
|
Elevation Cert Rec'd-Final | | | 6/8/2012 | | DONE |
|
|
|
Elevation Certificate for building under construction has been received and is acceptable. Framing inspection may proceed. Final Elevation Certificate will be required prior issuance of final occupancy permit. Jim Wyllie (###-####)
|
BLD-Wall Bracing | 5/29/2012 | 5/30/2012 | 5/30/2012 | P | PART |
Mike Jordan
|
|
|
ADAM Phone #: ###-####. Exterior shear nail ok. ok to cover.
|
BLD-Wall Bracing | 5/24/2012 | 5/29/2012 | 5/29/2012 | P | FAIL |
Mike Jordan
|
|
|
Adam Phone #: ###-####. nailing not as per plan, provide portal frame at livingroom window, provide the 800 lb. floor to floor hold down strap and the additional 800lb. hold down strap at bathroom window behind the garage. Install the 1000lb straps for portal frame at garage.
|
Override - Parcel Holds | 5/29/2012 | 1/1/1900 | 5/29/2012 | | |
|
|
|
this is for wall bracing only
|
BLD-Foundation | 5/9/2012 | 5/11/2012 | 5/11/2012 | A | PART |
Mike Jordan
|
|
|
Bill Phone #: ###-####
|
BLD-Footing | 5/9/2012 | 5/10/2012 | 5/10/2012 | A | PASS |
Mike Jordan
|
|
|
Bill Phone #: ###-####
|
Override - Parcel Holds | 5/9/2012 | 1/1/1900 | 5/9/2012 | | |
|
|
|
foundation
|
Override - Parcel Holds | 5/9/2012 | 1/1/1900 | 5/9/2012 | | |
|
|
|
footing
|
Issue PAID IN FULL permit | | | 5/3/2012 | | DONE |
Alexandra L. DeYoung
|
|
|
|
Telephone call | | | 4/5/2012 | | DONE |
Barbara Stitt
|
|
|
Left a voice message for Abram that permit is ready & fees due on 4-5-12 @8:15am//BAS
|
OVERRIDE | | | 4/4/2012 | | |
|
|
|
|
Route to Impact Fee Review | 4/4/2012 | 4/9/2012 | 4/4/2012 | | PASS |
Cindy M. Gould
|
|
|
|
Override - Parcel Holds | | | 4/4/2012 | | |
|
|
|
|
Permit Ready to Issue | | | 4/4/2012 | | DONE |
Barbara Stitt
|
|
|
|
Routing - MECHANICAL | 4/4/2012 | | 4/4/2012 | | PASS |
Troy James
|
|
|
|
Routing - PLAN CHECK | 4/4/2012 | | 4/4/2012 | | PASS |
Carl D Madsen
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/4/2012 | | |
|
|
|
|
Inspection Record Card- Bld | | | 4/4/2012 | | DONE |
Christina Prado
|
|
|
|
Plan assigned to (CDM) | 2/24/2012 | 2/24/2012 | 4/2/2012 | | PASS |
Carl D Madsen
|
|
|
|
Routing - PLAN CHECK | 3/29/2012 | | 4/2/2012 | | PASS |
Carl D Madsen
|
|
|
|
CHANGE STATUS TO (REV) | | | 4/2/2012 | | DONE |
Tisha Gallop
|
|
|
permit changed into FEE status by mistake
|
Routing - PUBLIC WORKS | 3/29/2012 | | 3/29/2012 | | PASS |
Connie Baumgartner
|
|
|
|
Routing PW Flood Plain | 3/29/2012 | | 3/29/2012 | | PASS |
Jim Wyllie
|
|
|
Two additional Elevation Certificates are required. One certicicate prior to framing inspection and one certificate after all construction, including final grading and landscaping, is completed. Jim Wyllie (###-####)
|
Plan resubmittals received | | | 3/28/2012 | | |
|
|
|
Received 2 copies of sheets A1.1, A2.1, A2.1, A3.2, A3.3, A3.4, A3.5, A4.1, A5.1, A6.1, A6.2 and taken to Carl Madsen
|
Plan resubmittals received | | | 3/27/2012 | | DONE |
Christina Prado
|
|
|
Received two full new sets of plans marked A1.1, A2.1, A3.1, A3.2, A3.3, A3.4, A3.5, A4.1, A5.1, A5.1, A6.1 & A6.2. Gave both sets to Carl Madsen for further review and routing
|
Routing - PLANNING | 3/27/2012 | | 3/27/2012 | | PASS |
Sue Cummings
|
|
|
Resubmitted. Still O.K. SC
|
Routing PW Flood Plain | 2/28/2012 | | 3/23/2012 | | FAIL |
Jim Wyllie
|
|
|
Elevation Certificate needs to be corrected. Elevation information for foundation, finish floor, crawl space and bench mark not provided. JIm Wyllie (###-####)
|
Routing - PUBLIC WORKS | 3/23/2012 | | 3/23/2012 | | FAIL |
Connie Baumgartner
|
|
|
Failed by Jim Wylie for flood plain concerns
|
1st review completed | | | 3/7/2012 | | FAIL |
|
|
|
Failed pending floodplain approval by Public Works and Mechanical. 3-8-12 CDM
|
Case Summary (BLD) | | | 3/7/2012 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 2/29/2012 | | 3/7/2012 | | PASS |
Carl D Madsen
|
|
|
|
Routing - MECHANICAL | 2/28/2012 | | 2/29/2012 | | FAIL |
Troy James
|
|
|
emailed corrections to Northwest Heating
|
Routing - PLANNING | 2/28/2012 | | 2/28/2012 | | PASS |
Colleen T Carroll
|
|
|
The side street is not developed. The applicant must take access from Gatewood Court.
|
Routing - PUBLIC WORKS | 2/27/2012 | | 2/28/2012 | | FAIL |
Connie Baumgartner
|
|
|
Failed by Jim Wylie for flood plain elevation requirements.
|
Elevation Cert Rec'd-Prelim | | | 2/28/2012 | | FAIL |
|
|
|
Property is located in the Eightmile Creek Floodplain. Building construction must comply with the Boise City Floodplain Ordinance. Elevation Certificate and supporting building plan documentation not provided. Jim Wyllie (###-####)
|
Route to Impact Fee Review | 2/24/2012 | 2/29/2012 | 2/27/2012 | | PASS |
Cindy M. Gould
|
|
|
|
Application received | | 2/24/2012 | 2/27/2012 | | DONE |
Tisha Gallop
|
|
|
|
Routing - Addressing | 2/27/2012 | | 2/27/2012 | | PASS |
Terry Records
|
|
|
Address was to changed to 2801 S Gatewood Ct from 2735 S Gatewood Ct to reflect the site plan submitted.
|
Plans ACCEPTED BY PLAN TECH | | | 2/24/2012 | | DONE |
Tisha Gallop
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 2/24/2012 | | DONE |
Tisha Gallop
|
|
|
|
Intake Approval | | | 2/24/2012 | | PASS |
Tisha Gallop
|
|
|
|
Routing PW Flood Plain | 3/21/2012 | | | | |
Jim Wyllie
|
|
|
|