Permit NumberBLD12-00363
StatusFinaled
Name PETRA INC
Site Address 3815 W RICKENBACKER ST
Project NameJACKSON JET CENTER
Customer Number 
ePlanReviewYes
Description
Jackson Jet Center - Foundation Permit - To pour the concrete footings and foundation for a 25,595 sq. ft. aircraft hanger expansion on the east side of an existing hangar. To demo and install footings and foundation for a 2,405 sq. ft., two story office expansion at the north side of the existing eastern hangar. To demo and install footings and foundation for a 3,4755 sq. ft., two story office expansion at the south side of the existing western hangar. To pour column foundations for a new entry Porte-Cochere at the north terminal entry. This permit also includes related site improvements. Work under this permit shall not proceed beyond the pour of the foundation until final approval of plans and issuance of the full building permit. As owner or designated agent, I acknowledge that I am performing this work at my own risk without assurance that the permit for the entire building structure will be granted, and I agree to make any modifications to the early foundation work performed as may be required to comply with the City Codes and the final approved building plans and conditions. All per engineered plans on file. JCM
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Second Notice 11/24/201211/29/2012 DONE
First Notice11/8/201211/8/201211/14/2012 DONE
DetailsJim Storey
BLD-Final11/8/201211/8/201211/8/2012PPASS
DetailsJim Storey
DOC - Permit Finaled11/8/201211/8/201211/8/2012PPASS
DetailsJim Storey
BLD-Concrete5/1/20125/2/20125/2/2012APART
DetailsJim Storey
Jc Phone #: ###-#### si pending
BLD-Foundation4/25/20124/26/20124/26/2012APART
DetailsJim Storey
concrete is at 2//JC Phone #: ###-#### genral per the plan. placement postponed to fri am si will be on site for review.
BLD-Foundation4/23/20124/24/20124/24/2012APASS
DetailsJim Storey
request 8 am//Jerry Frank ###-####
Routing - PLAN CHECK4/18/2012 4/23/2012 PASS
DetailsJohn Menard
PLANS/APPL TAKEN TO FRONT DESK  4/23/2012 DONE
DetailsJohn Menard
Permit Ready to Issue  4/23/2012 DONE
DetailsTisha Gallop
Issue PAID IN FULL permit  4/23/2012 DONE
DetailsTisha Gallop
Plan assigned to (JCM)3/8/2012 4/23/2012 PASS
DetailsJohn Menard
Routing Off Site - STRUCTURAL4/16/2012 4/23/2012 PASS
DetailsJohn Menard
Routing PW Drainage3/8/2012 4/18/2012 PASS
DetailsBrian Murphy
Routing - PUBLIC WORKS4/18/2012 4/18/2012 PASS
DetailsBeverly Mountain
Routing - PLANNING Land Div4/18/2012 4/18/2012 PASS
DetailsDave Abo
Parcel over 5 acres in size.
Routing - Design Review4/18/2012 4/18/2012 PASS
DetailsJosh Wilson
Routing - Addressing4/18/2012 4/18/2012 PASS
DetailsTerry Records
Routing - FIRE3/8/20124/16/20124/17/2012 PASS
DetailsScott Arellano
Approved to be issued by the Fire Marshal.
1st review completed  4/17/2012 FAIL
Failed Plumbing
Routing - PLUMBING4/11/2012 4/11/2012 PASS
DetailsBill VanDegrift
corrections addressed on building plans
Meeting  3/28/2012 DONE
Meeting held in PDS conference room #1 with Pete Rockwell, Jim Glancey, John Menard and Scott Arellano to discuss fire flow requirements and fire wall separation.
Route to Impact Fee Review3/14/20123/19/20123/16/2012 PASS
DetailsCindy M. Gould
Routing - PLUMBING3/8/2012 3/15/2012 FAIL
DetailsJohn Menard
Route to Impact Fee Review3/8/20123/13/20123/8/2012 PASS
DetailsCindy M. Gould
I put impact fees on BLD12-00388 JACKSON JET CENTER HANGAR ADDITION
Routing - PUBLIC WORKS3/8/2012 3/8/2012 PASS
DetailsBeverly Mountain
Pending Assignment by JCM3/8/2012 3/8/2012 DONE
DetailsJohn Menard
Routing - Erosion and Sediment3/8/2012 3/8/2012 PASS
DetailsClint A Smith
ESC12-00153 approved with conditions attachedto the permit.
Routing - Design Review3/8/2012 3/8/2012 PASS
DetailsJosh Wilson
Telephone call  3/5/2012 DONE
DetailsChristina Prado
Emailed Allison & Billy giving intake fees due and advising to pay
Intake Approval  3/1/2012 FAIL
DetailsTim L. Woodard
Intake failed 2nd review. Sheets horizontally uploaded and no stamping area. TLW
Application received  2/27/2012 DONE
Application submitted via PDS Online on Feb 27 2012 8:11AM
Intake Approval  2/27/2012 FAIL
DetailsTim L. Woodard
Intake failed. Refer to vol. 2 of intake checklist in e-plan review.