Permit Information
Permit NumberBLD12-00383
StatusFinaled
Name LEONARD PETROLEUM EQUIPMENT
Site Address 10751 W OVERLAND RD
Project NameFred Meyer Fuel #439 - 5 Mile
Customer Number 
ePlanReviewYes
Description
(FRED MEYER FUEL STATION CANOPY ADDITION) The existing fuel center will be expanded with the addition of 2 multi-product dispensers. The existing 3,985 sq. ft. steel framed canopy will be expanded by 1,435 sq. ft. to cover the new dispensers. Associated asphalt and curbing changes will take place and a propane distribution tank will be added to the site. A separate Fire Department permit will be required for the propane tank install. All construction per the approved plans. JCM
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Third Notice 9/24/20129/20/2012 DONE
complete 9-20
Second Notice 9/3/20129/19/2012 DONE
DetailsChristina Prado
faxe 9-19
First Notice 8/20/20128/24/2012 DONE
PubWorks Occupancy Approval8/13/20128/13/20128/13/2012 DONE
DetailsTiffany Lowery
Permanent Occupancy  8/10/2012 DONE
DetailsTisha Gallop
FIRE-Final Inspection6/22/20126/25/20126/25/2012APASS
DetailsForrest France
Fire life safety inspection passed. Contractor to provide address numbers at the fuel island canopy as discussed.
BLD-Final6/22/20126/25/20126/25/2012APART
DetailsMike Jordan
Tom Phone #: ###-####. Ok for temp occ once fire/life/safety signs off. Will be ok for perm occ. once public works signs perm.
Temporary Occupancy6/25/20129/23/20126/25/2012 DONE
DetailsBarbara Stitt
CHANGE STATUS TO (ISS)  6/25/2012 DONE
DetailsChristina Prado
Changed to tmp status by mistake by BGM
BLD-Final6/21/20126/22/20126/22/2012PNR
DetailsMike Jordan
Trey Phone #: ###-####. Provide approved plans and fire/life/safety inspection.
FIRE-Final Inspection6/21/20126/22/20126/22/2012PFAIL
DetailsTroy Cobbley
No approved plans on site or the small documents. So no real inspection was performed. I did however test the emergency stop system which functioned correctly.
Temporary Occupancy6/22/20129/20/20126/22/2012 DONE
DetailsBrian Murphy
BLD-Framing/Rough-in6/5/20126/6/20126/6/2012ADEFR
DetailsMike Jordan
Tom Phone #: ###-####. Welding and bolting. Reviewed special inspection reports. ok.
BLD-Footing5/29/20125/30/20125/30/2012PPART
DetailsMike Jordan
Tom Giannini Phone #: ###-####. Footings for new canopy columns. Will have special inspections.
Print Occupancy Form  5/29/2012 DONE
DetailsTisha Gallop
Issue PAID IN FULL permit  5/29/2012 DONE
DetailsTisha Gallop
Permit Ready to Issue  5/18/2012 DONE
Telephone call  5/18/2012 DONE
email Kent with Leonard, permit ready, fees due
PLANS/APPL TAKEN TO FRONT DESK  4/13/2012 DONE
DetailsJohn Menard
Plan assigned to (JCM)3/8/2012 4/13/2012 PASS
DetailsJohn Menard
Routing PW Drainage4/4/2012 4/13/2012 PASS
DetailsBrian Murphy
Routing PW Street Lights4/4/2012 4/12/2012 PASS
DetailsMike D Hedge
Routing PW Environmental4/4/2012 4/6/2012 PASS
DetailsWalt Baumgartner
Routing - Erosion and Sediment3/7/2012 4/6/2012 PASS
DetailsClint A Smith
ESC12-00164 plan approved with conditions attached to the permit.
Routing - FIRE3/8/20123/8/20123/13/2012 PASS
DetailsTim Frost
No comments attached.
Routing PW Drainage3/8/2012 3/13/2012 FAIL
DetailsBrian Murphy
Need drainage plan and O & M
1st review completed  3/13/2012 DONE
DetailsJohn Menard
Plan Reviewer's activity  3/9/2012 PASS
DetailsJohn Menard
Reviewed and approved structural and nonstructural requirements. JCM
Routing - PLAN CHECK3/8/2012 3/9/2012 PASS
DetailsJohn Menard
Route to Impact Fee Review3/8/20123/13/20123/8/2012 PASS
DetailsCindy M. Gould
I put impact fees on BLD12-00388
Routing PW Environmental3/8/2012 3/8/2012 PASS
DetailsWalt Baumgartner
Routing - PUBLIC WORKS3/8/2012 3/8/2012 PASS
DetailsBeverly Mountain
Routing - Design Review3/8/2012 3/8/2012 PASS
DetailsJosh Wilson
Pending Assignment by JCM3/8/2012 3/8/2012 DONE
DetailsJohn Menard
Payment Received  3/6/2012 DONE
Payment received via Govolutions
Intake Approval  3/1/2012 FAIL
DetailsTim L. Woodard
Please refer to Version 2 of the Submittal checklist attached in the documents section of this case. Notice I've marked all requirements with a half circle to the side. Above and beyond those items it appears that the submittal checklist guide standards were not followed. Within the "Submittal Upload Guide" it requires a clear stamping area on each sheet. Please resubmit all plan sheets affect by the revisions required during in this pre-screen. Call ###-#### if you would like to ask me any questions about this process.

Sincerly Tim Woodard
Plans Examiner II
Application received  2/29/2012 DONE
Application submitted via PDS Online on Feb 29 2012 10:19AM