BLD-Final | 1/2/2013 | 1/3/2013 | 1/3/2013 | P | DONE |
Tony Young
|
|
|
jeff Phone #: ###-####,,// done per office agreement,, guardrail meets code now
|
DOC - Permit Finaled | 1/3/2013 | 1/3/2013 | 1/3/2013 | P | PASS |
Tony Young
|
|
|
done per office agreement,, guardrail meets code now
|
BLD-Other | 12/13/2012 | 12/13/2012 | 12/13/2012 | A | PEND |
Tony Young
|
|
|
Work in progress, looks near completion.
|
Case Summary (BLD) | | | 11/1/2012 | | DONE |
Christina Prado
|
|
|
|
BLD-Conference | 10/23/2012 | 10/24/2012 | 10/24/2012 | A | PART |
Tony Young
|
|
|
call ahead to meet//Jeff Phone #: ###-####,, met with Jeff,, he will make the guardrail meet code,, treads on steps between deck meet code and have the engineer of record give letter of ok on tall posts for wind sail/shade
|
BLD-Conference | 10/22/2012 | 10/23/2012 | 10/23/2012 | A | FAIL |
Tony Young
|
|
|
conf with 325,,, correction notice posted to call in for a final inspection and also noted that the guardrail does not meet code at this time,, no inspection made except from the street view
|
BLD-Conference | 10/22/2012 | 10/23/2012 | 10/23/2012 | A | PART |
Bob Archibald
|
|
|
call 415,, ? on guard rail. Indtructed inspector to issue CN requesting final inspection and installation of guard rail.
|
BLD-Other | 10/19/2012 | 10/22/2012 | 10/22/2012 | P | PEND |
Tony Young
|
|
|
Status? Is project ready for final?
|
BLD-Conference | 6/29/2012 | 7/2/2012 | 7/2/2012 | P | PEND |
Tony Young
|
|
|
Status?
|
BLD-Framing/Rough-in | 3/30/2012 | 3/30/2012 | 3/30/2012 | P | PART |
Tony Young
|
|
|
JEFF Phone #: ###-####,, ok after corrections
|
BLD-Footing | 3/9/2012 | 3/12/2012 | 3/12/2012 | A | PART |
Tony Young
|
|
|
jeff Phone #: ###-####,, rebar ok now, will need to pull up off of soil 3",,
|
BLD-Foundation | 3/7/2012 | 3/8/2012 | 3/9/2012 | P | FAIL |
Tony Young
|
|
|
jeff Phone #: ###-####,, not per plan,, correction posted
|
PubWorks Subgrade Approval | 3/8/2012 | 3/8/2012 | 3/8/2012 | | DONE |
Terry Records
|
|
|
Footing subgrade approved by the geotechnical engineer
|
Routing Walk-In (PW Hillside) | 3/6/2012 | 3/6/2012 | 3/6/2012 | A | PASS |
Terry Records
|
|
|
Footing subgrade must be approved by the applicants geotechnical engineer prior to scheduling a footing inspection.
|
Routing Walk-In (BLD) | 3/6/2012 | 3/6/2012 | 3/6/2012 | A | DONE |
Perry Paine
|
|
|
|
Plan assigned to (PEP) | 3/6/2012 | 3/6/2012 | 3/6/2012 | | PASS |
Perry Paine
|
|
|
|
1st review completed | | | 3/6/2012 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/6/2012 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 3/6/2012 | | DONE |
Tisha Gallop
|
|
|
|
Issue PAID IN FULL permit | | | 3/6/2012 | | DONE |
Tisha Gallop
|
|
|
|
Case Summary (BLD) | | | 3/6/2012 | | |
|
|
|
|
Inspection Record Card- Bld | | | 3/6/2012 | | |
|
|
|
|
Application received | | 3/6/2012 | | | |
|
|
|
|