First Notice | 2/25/2013 | 2/25/2013 | 3/22/2013 | | DONE |
Jim Storey
|
|
|
|
BLD-Final | 2/22/2013 | 2/25/2013 | 2/25/2013 | A | PASS |
Jim Storey
|
|
|
we finally attached the mech so this should close out the BLD. We be ready...meet you in B25. John may have business too. thx. Phone #: ###-#### >> Inspection requested via web by Greg Kirkes
|
DOC - Permit Finaled | 2/25/2013 | 2/25/2013 | 2/25/2013 | P | PASS |
Jim Storey
|
|
|
|
BLD-Final | 10/31/2012 | 11/1/2012 | 11/1/2012 | A | NR |
Jim Storey
|
|
|
Phone #: ###-#### >> Inspection requested via web by Frederick Sand
|
FIRE-Final Inspection | 10/25/2012 | 10/30/2012 | 10/31/2012 | A | PASS |
Forrest France
|
|
|
Fire life safety passed.
|
Issue PAID IN FULL permit | | | 5/4/2012 | | DONE |
Rita DeYoung
|
|
|
|
CHANGE STATUS TO (ISS) | | | 5/4/2012 | | DONE |
Rita DeYoung
|
|
|
|
Telephone call | | | 4/17/2012 | | DONE |
Rita DeYoung
|
|
|
spoke with Paul regarding fees
|
1st review completed | | | 4/5/2012 | | DONE |
John Menard
|
|
|
|
Permit Ready to Issue | | | 4/5/2012 | | DONE |
Rita DeYoung
|
|
|
|
Plan assigned to (JCM) | 4/2/2012 | | 4/5/2012 | | PASS |
John Menard
|
|
|
|
Routing - PLAN CHECK | 4/2/2012 | | 4/5/2012 | | PASS |
John Menard
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/5/2012 | | DONE |
John Menard
|
|
|
|
Routing - FIRE | 4/2/2012 | | 4/4/2012 | | PASS |
Scott Arellano
|
|
|
No comments attached. A fire alarm permit will be required to connect the duct smoke detector to the building fire alarm system.
|
Intake Approval | | | 4/2/2012 | | PASS |
John Menard
|
|
|
|
Pending Assignment by JCM | 4/2/2012 | | 4/2/2012 | | DONE |
John Menard
|
|
|
|
Application received | | | 3/6/2012 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 6 2012 10:17AM
|
Intake Approval | | | 3/6/2012 | | FAIL |
|
|
|
The minimum size of drawing sheets allowed is 24" x 18". Please upload properly sized drawing sheets. Per John Menard, please provide an existing roof framing plan.
|