BLD-Final | 9/21/2012 | 9/24/2012 | 9/24/2012 | A | PASS |
Tom Arcoraci
|
|
|
paul - call for access Phone #: ###-####
|
DOC - Permit Finaled | 9/24/2012 | 9/24/2012 | 9/24/2012 | P | PASS |
Tom Arcoraci
|
|
|
|
BLD-Final | 8/28/2012 | 8/29/2012 | 8/29/2012 | A | FAIL |
Jim Storey
|
|
|
paul please call for access Phone #: ###-#### gyp protection on steel col. in garage// firestop gyp at comon wall.c/n on site
|
BLD-Energy code compliance | 4/25/2012 | 4/26/2012 | 4/26/2012 | A | PASS |
Jim Storey
|
|
|
Larry Phone #: ###-####
|
BLD-Framing/Rough-in | 4/23/2012 | 4/24/2012 | 4/24/2012 | A | PASS |
Jim Storey
|
|
|
Larry Phone #: ###-####
|
BLD-Framing/Rough-in | 4/19/2012 | 4/20/2012 | 4/20/2012 | P | NR |
Tony Young
|
|
|
Please call prior to arrival -- Larry Phone #: ###-####,, need trades 1st
|
Issue PAID IN FULL permit | | | 4/10/2012 | | DONE |
Barbara Stitt
|
|
|
|
OVERRIDE | | | 4/9/2012 | | |
|
|
|
|
Inspection Record Card- Bld | | | 4/9/2012 | | DONE |
|
|
|
|
Telephone call | | | 4/9/2012 | | DONE |
Christina Prado
|
|
|
Called and gave Paul fees due. He seemed surprised by the amount so I sent him to PW for sewer fee questions
|
Permit Ready to Issue | | | 4/9/2012 | | DONE |
Christina Prado
|
|
|
|
Plan assigned to (CDM) | 3/29/2012 | 3/29/2012 | 4/7/2012 | | PASS |
Carl D Madsen
|
|
|
|
Case Summary (BLD) | | | 4/7/2012 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 4/7/2012 | | 4/7/2012 | | PASS |
Carl D Madsen
|
|
|
Third party structural inspection is required. 4-7-12 CDM
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/7/2012 | | |
|
|
|
|
Plan resubmittals received | | | 4/3/2012 | | DONE |
Christina Prado
|
|
|
Received two copies of structural calcs: gave to Carl Madsen for additional review
|
Plan resubmittals received | | | 3/29/2012 | | DONE |
Tisha Gallop
|
|
|
received one copy of structural calcs, truss engineering and two copies of plan sheets S1.0, S1.1, S2.0, S3.0, A2.0, A2.1, A3.0, A3.1; taken to Carl Madsen.
|
Plan assigned to (CDM) | 3/6/2012 | 3/6/2012 | 3/22/2012 | | PASS |
Carl D Madsen
|
|
|
|
Routing - PLAN CHECK | | | 3/22/2012 | | FAIL |
Carl D Madsen
|
|
|
Complete rescheck is required 3-22-12 CDM. Called Paul Bushman.
|
Case Summary (BLD) | | | 3/22/2012 | | DONE |
|
|
|
|
1st review completed | | | 3/22/2012 | | FAIL |
|
|
|
Complete rescheck is required 3-22-12 CDM. Called Paul Bushman.
|
Routing - PLAN CHECK | 3/22/2012 | | 3/22/2012 | | FAIL |
Carl D Madsen
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/22/2012 | | |
|
|
|
|
Routing - Erosion and Sediment | 3/13/2012 | | 3/14/2012 | | PASS |
Clint A Smith
|
|
|
Issue general permit per foundation and grading mostly completed under old permit.
|
Routing - FIRE | 3/14/2012 | | 3/14/2012 | | PASS |
Scott Arellano
|
|
|
No comments.
|
Routing - MECHANICAL | 3/14/2012 | | 3/14/2012 | | PASS |
Troy James
|
|
|
|
Routing - MECHANICAL | 3/8/2012 | | 3/12/2012 | | FAIL |
Troy James
|
|
|
emailed corrections to Arctic Air
|
Route to Impact Fee Review | 3/6/2012 | 3/9/2012 | 3/9/2012 | | PASS |
Cindy M. Gould
|
|
|
reference PRK07-00224
|
Routing - PLANNING | 3/8/2012 | | 3/8/2012 | | PASS |
Sue Cummings
|
|
|
|
Routing - Addressing | 3/6/2012 | | 3/8/2012 | | PASS |
Terry Records
|
|
|
|
Routing - PUBLIC WORKS | 3/8/2012 | | 3/8/2012 | | PASS |
Beverly Mountain
|
|
|
|
Routing PW Grading-Hillside | | | 3/8/2012 | | PASS |
Terry Records
|
|
|
Final grading must be approved by the applicants geotechnical engineer.
|
Application received | | 3/6/2012 | 3/7/2012 | | DONE |
Tisha Gallop
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 3/6/2012 | | DONE |
Tisha Gallop
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 3/6/2012 | | DONE |
Tisha Gallop
|
|
|
|
Intake Approval | | | 3/6/2012 | | PASS |
Tisha Gallop
|
|
|
|