Permit Information
Permit NumberBLD12-00443
StatusFinaled
Name LANDMARK GENERAL CONTRACTORS INC
Site Address 300 S BROADWAY AVE
Project NameChick-Fil-A Restaurant -
Customer Number 
ePlanReviewNo
Description
(CHICK-FIL-A RESTAURANT) - To demolish and remove and existing Perkins restaurant building and construct a new 4,615 square foot, one story, wood framed fast food restaurant with drive-thru window. This permit also includes a 110 square foot detached storage building as part of the trash enclosure area and other related site improvements. All construction per the approved plans and attached comment list. JCM
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Print Statement  1/10/2013 DONE
DetailsTisha Gallop
mailed to Landmark GC
Third Notice 12/9/20121/3/2013 DONE
faxed to Landmark General Cont
Second Notice 11/24/201212/4/2012 DONE
First Notice 10/26/201211/14/2012 DONE
BLD-Final10/16/201210/17/201210/16/2012APASS
DetailsDave Hannah
Chris Phone #: ###-####
FIRE-Final Inspection10/12/201210/15/201210/16/2012PPASS
DetailsForrest France
Fire life safety finaled.
Permanent Occupancy  10/16/2012 DONE
DetailsChristina Prado
PubWorks Occupancy Approval10/11/201210/11/201210/11/2012 DONE
DetailsTiffany Lowery
Zoning Approval10/11/201210/11/201210/11/2012 PASS
DetailsJosh Wilson
BLD-Other9/20/20129/20/20129/20/2012PPART
DetailsDave Hannah
CHRIS Phone #: ###-#### ceiling grid ok to cover
BLD-Energy code compliance8/27/20128/27/20128/30/2012PPASS
DetailsDave Hannah
Chris Phone #: ###-####
BLD-Framing/Rough-in8/23/20128/23/20128/23/2012PPART
DetailsDave Hannah
Chris Phone #: ###-#### ok to cover int walls ok to insulate ext walls
BLD-Framing/Rough-in8/13/20128/15/20128/16/2012APART
DetailsDave Hannah
Partial - Chris Phone #: ###-#### ok to insulate walls around freezers
BLD-Footing7/10/20127/11/20127/11/2012APART
DetailsTom Arcoraci
chris Phone #: ###-#### spec inspec on site
Issue PAID IN FULL permit  6/1/2012 DONE
DetailsBarbara Stitt
Issue PAID IN FULL permit  6/1/2012 DONE
DetailsBarbara Stitt
Print Occupancy Form  5/9/2012 DONE
Permit Ready to Issue  5/9/2012  
Telephone call  5/9/2012  
5-9-12 called Robert permit ready and fee given Also need ACHD,GC & RP ///DLD
Plan assigned to (JCM)3/7/2012 5/8/2012 PASS
DetailsJohn Menard
Routing - PLANNING5/7/2012 5/8/2012 PASS
DetailsDavid Moser
as per CUP11-00080
Routing - PLAN CHECK5/8/2012 5/8/2012 PASS
DetailsJohn Menard
Plan Reviewer's activity  5/8/2012 PASS
DetailsJohn Menard
Reviewed and approved structural and nonstructural revisions. JCM
PLANS/APPL TAKEN TO FRONT DESK  5/8/2012 DONE
DetailsJohn Menard
Routing - Design Review5/7/2012 5/7/2012 PASS
DetailsJosh Wilson
Resubmittals sheets SP-1 and L-1.0 OK JGW 5-7-12
Routing - PUBLIC WORKS5/2/2012 5/4/2012 PASS
DetailsConnie Baumgartner
Routing PW Drainage5/2/2012 5/4/2012 PASS
DetailsBrian Murphy
Routing - PLAN CHECK4/17/2012 5/2/2012  
DetailsJohn Menard
Plan resubmittals received  5/1/2012  
Received cover transmittal 2 copies of plan review report dated 4-10-12, 2 copies of response letter dated 4-25-12 from Jose Carlos de la Vega, 3 copies of sheets T1.1, PS-1.0, C-0.0, C-1.0, C-2.0, C-3.0, C-3.1, C-4.0, C-4.1, C-4.2, C-5.0, C-6.0, C-7.0, L-1.0, L-1.1, A-1.0, A-1.3, A-1.7, A-1.8, A-1.9, M-6.1, E1.1, E2.1, E3.1, cover transmittal recieved, 2 copies of email from Josh Wilson regarding required resubmittals, 2 copies of email with fire department approval for turning radius plans, 3 copies of sheets SP-1, C-2.0, L-1.0, A-3.6, turning radius plans, transmittal cover sheet, 3 copies of O & M plan, 3 copies of 3 copies of Drainage report, 3 copies of sheet C-3.0, transmittal cover sheet, 3 copies of plumbing plan review dated 3-22-12, 3 copies of sheets P-1.1, P-3.1, P-5.1, P-6.1, P-7.1 inserted into plans and then back to John Menard's desk

Plan resubmittals received  4/24/2012 DONE
DetailsTisha Gallop
by mail received three copies of response, structural calcs, and plan sheets S1.1, S2.1, S2.2, S3.1, S3.2, S4.1, S4.2, S5.1, S6.1; taken to John Menard.
Routing - Erosion and Sediment4/16/2012 4/17/2012 PASS
DetailsClint A Smith
ESC12-00194 plan approved with conditions attached to the permit.
Routing - FIRE4/10/2012 4/13/2012 PASS
DetailsScott Arellano
Attached IFC comments to plans
1st review completed  4/13/2012 FAIL
Failed Public Works, Planning, Plan Check
Route to Impact Fee Review4/10/20124/13/20124/12/2012 PASS
DetailsCindy M. Gould
credit given for the removal of existing building of 5508 sq ft. No impact fees due
Plan resubmittals requested  4/10/2012 DONE
DetailsJohn Menard
E-mailed the agent/Rep a copy of the plan review comment list requesting revisions. JCM
Routing - PLAN CHECK3/23/2012 4/10/2012 FAIL
DetailsJohn Menard
Plan resubmittals received  3/27/2012  
Recieved 2 copies of ESC narrative and 2 copies of sheet C-3.1
Routing - PLANNING3/22/2012 3/23/2012 FAIL
DetailsJosh Wilson
Resubmittals required sheets SP-1 and L-1.0 Conditions of Design Review and Conidtional Use Permit not met. Applicant contacted with list of items.

DRH11-00278 Josh W.
CUP 11-00080 Dave M.
Routing - PLUMBING3/21/2012 3/22/2012 PASS
DetailsDaryl Spivey
1. 2" water service backflow can be a DCVA.
2. Require a 1" RPBP on water filter system.
3 Backflow on coffe and tea locations require a testable backflow assembly. a Watts #7 is not approved for use.
4. Floor sinks to be located where visible for cleaning.
5. Resubmit with 1500 gal grease intercepter as required by Public Works.
6. All floor drains are to be vented per 2003 UPC.
Routing PW Sewer Design3/14/2012 3/15/2012 PASS
DetailsJon R. Gunnerson
Connect onto existting sanitary sewer service line provided.
Routing Off Site - STRUCTURAL3/7/2012 3/15/2012 FAIL
DetailsJohn Menard
Received comment list from consulting structural engineer requesting revisions. JCM
Routing - PUBLIC WORKS3/9/2012 3/15/2012 FAIL
DetailsConnie Baumgartner
failed by Brian Murphy ###-####
Plan resubmittals requested  3/15/2012 DONE
DetailsJohn Menard
E-mailed the applicant a copy of the structural review requesting revisions. JCM
Routing PW Drainage3/12/2012 3/14/2012 FAIL
DetailsBrian Murphy
NEEDS O M REVISIONS,C-33 FILTER SAND,MONITOR WELL AND REMOVAL OF DRIAN IN DUMPSTER
Routing PW Solid Waste3/12/2012 3/12/2012 PASS
DetailsPeter J. McCullough
Routing PW Environmental3/12/2012 3/12/2012 PASS
DetailsWalt Baumgartner
Engineer will make correction for grease interceptor size and resubmit P-1.1. sheet for plumbing review.
Routing PW Sewer Rating3/12/2012 3/12/2012 PASS
DetailsConnie Baumgartner
Routing - PLANNING Land Div3/8/2012 3/9/2012 PASS
DetailsTodd Tucker
Routing - Addressing3/9/2012 3/9/2012 PASS
DetailsTerry Records
Plan routing begun/NEW & ADDTN  3/8/2012  
Telephone call  3/7/2012  
3-7-12 called Action Couriers for pick up ///dld
Intake Approval  3/7/2012 PASS
OK to submit
Pending Assignment by JCM3/7/2012 3/7/2012 DONE
DetailsJohn Menard
Application received 3/7/2012