First Notice | | 11/3/2012 | 11/14/2012 | | DONE |
|
|
|
|
BLD-Final | 10/24/2012 | 10/24/2012 | 10/24/2012 | P | PASS |
Jim Storey
|
|
|
Marvin ###-#### p&z n/a final ok
|
FIRE-Final Inspection | 10/24/2012 | 10/24/2012 | 10/24/2012 | P | PASS |
Forrest France
|
|
|
Correction notice items verified for completion. Max occupant sign to be posted as discussed. Fire life safety finaled.
|
FIRE-Final Inspection | 10/23/2012 | 10/24/2012 | 10/24/2012 | A | FAIL |
Troy Cobbley
|
|
|
Provide occupant load sign, provide remote annunciator for the duct smoke detector and provide testing for verification of function or remove duct smoke detector since it is not required per IMC 606, mount the fire extinguisher and provide all city approved drawings for inspection.
|
Permanent Occupancy | | | 10/24/2012 | | DONE |
Tisha Gallop
|
|
|
|
FIRE-Conference | 10/17/2012 | 10/17/2012 | 10/17/2012 | P | DONE |
Forrest France
|
|
|
bill Phone #: ###-#### Regarding fire life safety inspection items.
|
Zoning Approval | 10/11/2012 | 10/11/2012 | 10/11/2012 | | PASS |
Josh Wilson
|
|
|
|
BLD-Energy code compliance | 9/7/2012 | 9/7/2012 | 9/7/2012 | P | PASS |
Jim Storey
|
|
|
bill Phone #: ###-####
|
BLD-Framing/Rough-in | 9/5/2012 | 9/6/2012 | 9/6/2012 | P | PASS |
Jim Storey
|
|
|
Bill Phone #: ###-####
|
BLD-Conference | 8/22/2012 | 8/22/2012 | 8/22/2012 | P | PASS |
Jim Storey
|
|
|
Bill Petty Phone #: ###-####
|
Print Occupancy Form | | | 8/13/2012 | | DONE |
Tisha Gallop
|
|
|
|
Permit Ready to Issue | | | 8/13/2012 | | DONE |
Tisha Gallop
|
|
|
|
Issue PAID IN FULL permit | | | 8/13/2012 | | DONE |
Barbara Stitt
|
|
|
|
Telephone call | | | 5/24/2012 | | DONE |
Christina Prado
|
|
|
Sent email to Jeff advising permit plan review is complete
|
Plan assigned to (SRZ) | 3/30/2012 | 3/30/2012 | 5/10/2012 | | PASS |
Sam Zahorka
|
|
|
1st review due 4-26-12
1st review completed. Waiting for CDHD to PASS
|
1st review completed | | | 5/10/2012 | | DONE |
Sam Zahorka
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/10/2012 | | DONE |
Sam Zahorka
|
|
|
|
Routing - PLAN CHECK | 3/30/2012 | | 5/1/2012 | | PASS |
Sam Zahorka
|
|
|
|
Routing Off Site - C.D.H | 3/30/2012 | | 5/1/2012 | | PASS |
Sam Zahorka
|
|
|
Uploaded paid receipt in project dox approved drawings folder.
|
Routing PW Drainage | 4/2/2012 | | 5/1/2012 | | PASS |
Brian Murphy
|
|
|
|
Routing - FIRE | 3/30/2012 | 4/11/2012 | 4/16/2012 | | PASS |
Scott Arellano
|
|
|
Attached IFC comments to plans.
|
Route to Impact Fee Review | 4/10/2012 | 4/13/2012 | 4/10/2012 | | PASS |
Cindy M. Gould
|
|
|
|
Routing PW Environmental | 4/2/2012 | | 4/4/2012 | | PASS |
Walt Baumgartner
|
|
|
GI w/ shell & core, ok per Bench SD
|
Routing PW Solid Waste | 4/2/2012 | | 4/3/2012 | | PASS |
Peter J. McCullough
|
|
|
|
Routing - PUBLIC WORKS | 3/30/2012 | | 4/2/2012 | | PASS |
Connie Baumgartner
|
|
|
|
Routing PW Sewer Rating | 4/2/2012 | | 4/2/2012 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - PLANNING | 3/30/2012 | | 3/30/2012 | | PASS |
Cody Riddle
|
|
|
Cody Riddle - CUP11-00081
|
Routing - Design Review | 3/30/2012 | | 3/30/2012 | | PASS |
Josh Wilson
|
|
|
Josh Wilson - DRH11-00210
|
Routing - PLUMBING | 3/30/2012 | | 3/30/2012 | | PASS |
Bill VanDegrift
|
|
|
Per plans and 2003 UPC.
|
Routing - Addressing | 3/30/2012 | | 3/30/2012 | | PASS |
April Wing
|
|
|
|
Payment Received | | | 3/29/2012 | | DONE |
|
|
|
Payment received via Govolutions
|
Intake Approval | | | 3/29/2012 | | PASS |
Jason Blais
|
|
|
|
Intake Approval | | | 3/29/2012 | | PASS |
Sam Zahorka
|
|
|
Sam Zahorka passed prescreen on 3/26/12. Plan Review Fees were paid on 3/29/12.
|
Application received | | | 3/9/2012 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 9 2012 8:26AM
|