BLD-Final | 4/5/2012 | 4/6/2012 | 4/6/2012 | A | PASS |
Jim Sly
|
|
|
Dan Phone #: ###-#### OK for Perm Occ.
|
Permanent Occupancy | | | 4/6/2012 | | DONE |
Tisha Gallop
|
|
|
|
FIRE-Final Inspection | 4/5/2012 | 4/5/2012 | 4/5/2012 | P | PASS |
Troy Cobbley
|
|
|
life safety passed
|
Plan Reviewer's activity | | | 4/3/2012 | | DONE |
Tim L. Woodard
|
|
|
Review Commondities list with Scott A. and appears all amounts are under maximum allowable quanities. Ok to proceed. TLW
|
Plan resubmittals received | | | 4/2/2012 | | DONE |
Christina Prado
|
|
|
Received two copies of new floor plan as well as one copy of the current commodity lest. Given to Tim Woodard for further review
|
FIRE-Conference | 3/28/2012 | 3/28/2012 | 3/28/2012 | P | DONE |
Troy Cobbley
|
|
|
The tenant and I discussed door hardware on the three exterior doors with keyed hardware. He is going to discuss with plan review about not using the west side of the building.
|
BLD-Final | 3/22/2012 | 3/23/2012 | 3/23/2012 | A | CANC |
Jim Sly
|
|
|
Dan Phone #: ###-#### Need fire final
|
FIRE-Final Inspection | 3/22/2012 | 3/22/2012 | 3/22/2012 | P | FAIL |
Troy Cobbley
|
|
|
Resubmit a revised floor plan that matches the actual installation, address mezzanine with ladder with the plan reviewer, repair the exit signs, provide emergency lighting in the "sales" area, keyed hardware allowed on the main exit door only all other doors to have single action "ADA" type, provide annual inspection for all fire extinguishers, provide correct fire extinguisher size in "shop" and mount at less than 5', address the need for the locking door at the restroom corridor with the plan reviewer, provide type, quantity and storage arrangement of hazardous materials to plan reviewer to set maximum allowable quantities.
|
Print Occupancy Form | | | 3/22/2012 | | DONE |
|
|
|
|
Telephone call | | | 3/22/2012 | | DONE |
|
|
|
t/c w scott - permit ready
|
Permit Ready to Issue | | | 3/22/2012 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 3/22/2012 | | DONE |
Christina Prado
|
|
|
|
Plan assigned to (TLW) | 3/14/2012 | | 3/21/2012 | | PASS |
Tim L. Woodard
|
|
|
|
Routing - PLAN CHECK | 3/14/2012 | | 3/21/2012 | | PASS |
Tim L. Woodard
|
|
|
|
1st review completed | | | 3/21/2012 | | DONE |
Tim L. Woodard
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/21/2012 | | DONE |
Tim L. Woodard
|
|
|
|
Case Summary (BLD) | | | 3/21/2012 | | DONE |
Tim L. Woodard
|
|
|
|
Application received | | 3/14/2012 | 3/14/2012 | | DONE |
Tisha Gallop
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 3/14/2012 | | DONE |
Tisha Gallop
|
|
|
|