BLD-Final | 1/23/2013 | 1/23/2013 | 1/23/2013 | P | PASS |
Tony Young
|
|
|
signed perm occ on card but no insp in Tidemark
|
First Notice | | 2/2/2013 | 1/23/2013 | | DONE |
|
|
|
|
Permanent Occupancy | | | 1/23/2013 | | DONE |
Tisha Gallop
|
|
|
|
FIRE-Final Inspection | 1/22/2013 | 1/22/2013 | 1/22/2013 | P | PASS |
Forrest France
|
|
|
Life safety passed.
|
Issue PAID IN FULL permit | | | 10/15/2012 | | DONE |
Tisha Gallop
|
|
|
|
Plan assigned to (DRS) | 7/20/2012 | 7/20/2012 | 10/12/2012 | | PASS |
Dan Stuart
|
|
|
In Retrospect
|
Routing - PLAN CHECK | 10/12/2012 | | 10/12/2012 | | PASS |
Jason Blais
|
|
|
Architect emailed and indicated no change with Certificate of Value. Plans/permit taken to Permit Counter to process for issuance.
|
Print Occupancy Form | | | 10/12/2012 | | DONE |
Christina Prado
|
|
|
|
Permit Ready to Issue | | | 10/12/2012 | | DONE |
Tisha Gallop
|
|
|
|
Telephone call | | | 10/12/2012 | | DONE |
Tisha Gallop
|
|
|
called Jeff Likes and told him permit is ready, fees and need GC/form.
|
Routing - PLAN CHECK | 7/20/2012 | | 10/8/2012 | | PASS |
Dan Stuart
|
|
|
Dan Stuart
10/4/12 - Received copy of engineering and engineering analysis from Greg Leishman, Stapley Engineering, specific to the design floor load of 57 PSF being adequate for the specific use of the tenant In Retrosect for the limited retail clothing sales evaluated floor loads.Also inserted resubmittal sheets S1.1 & S7.1 into plans for new engineering plan work and requirements based on the submitted analysis letter.
10/8/12 - Received a letter from Nancy Zurcher, In Retrospect tenant and owner stating she understood the load limitations and that she was responsible to police compliance with the engineering analysis floor load and that she would post the maximum floor load sign at the retail sales floor.
|
Plan resubmittals received | | | 10/4/2012 | | DONE |
Christina Prado
|
|
|
received four sets of letter from engineer, two revised structural calcs and two sets of plans marked A1.1, A11.1, S1.1 & S7.1; gave to Dan Stuart for further review
|
Telephone call | | | 10/4/2012 | | DONE |
|
|
|
Called Jeff - Resubmittals included analysis from Greg Leishman for 57 PSF floor live load but did not include letter from Nancyn Zurcher stating she is aware of the load limitations and that she is responsible for enforcing the laod limits and occupant load as approved per her alaternate requests. Jeff will get letter to submit.
|
Plan resubmittals received | | | 8/21/2012 | | DONE |
Tisha Gallop
|
|
|
received letter from Stapley Eng with 1pg attachment and two copies of plan sheets A1.1, A11.1; taken to Dan Stuart.
|
Plan assigned to (DRS) | 3/19/2012 | 3/19/2012 | 6/12/2012 | | PASS |
Dan Stuart
|
|
|
|
Routing - PLAN CHECK | 5/23/2012 | | 6/12/2012 | | PASS |
Dan Stuart
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/12/2012 | | PASS |
|
|
|
|
Print Occupancy Form | | | 6/12/2012 | | DONE |
|
|
|
|
Telephone call | | | 6/12/2012 | | DONE |
Christina Prado
|
|
|
left message with Dave for Jeff -- Need GC and to know if ACHD inspection is required. Also gave fees due
|
Permit Ready to Issue | | | 6/12/2012 | | DONE |
Christina Prado
|
|
|
|
Plan resubmittals received | | | 6/8/2012 | | DONE |
|
|
|
Rec'd response letter and two copies of sheets ACS1.1; A1.1; A1.2; A11.1; taken to Dan S
|
Telephone call | | | 5/23/2012 | | DONE |
Dan Stuart
|
|
|
I called Jeff Likes to review resubmittal plans not being accurate between levels on sheets A1.1 & A1.2, for stair locations; compliance of stairs for rise and run to lower level; door at top of stairs to lower level; specify type of existing light fixtures on plans (1.5 Watts/sq. ft. - retail & .8 Watts/sq.ft. for storage) to clarify allowable watts compliance or changes required for compliance; panic hardware on exit doors (101A & 106A); indicate on plans that landings at exterior doors comply with current code or changes required for compliance; compliant ramp slope indicated on plans with compliant edge protection or changes required for compliance; method of handrail connections on open side of stairs to lower level and to basement at stacked washer/dryer; basement is declared habitable space so door/doorway clear width to meet code (32" clear); provide number for each door and provide door & hardware schedule showing code compliance for all doors (panic hardware on two required exit doors) or note at each door on plans showing compliance; secure inactive door leaf of main double doors with door stop on exterior side to secure leaf in place as a door sidelight due to manual flush bolts existing (not allowed for "M" occupancy); basement plan layout provided does not match structural plan or photo provided looking down hall - indicate corrections required or changes to be made as part of this permit; etc.
|
Telephone call | | | 5/23/2012 | | DONE |
Dan Stuart
|
|
|
Called nancy Zurcher to let her know permit would be delayed as resubmittals were not correct or incomplete per original plan review comments.Ask me to send her a copy of the second review.
|
Plan resubmittals requested | | | 5/23/2012 | | DONE |
|
|
|
Copy of 2nd plan review e-mailed to Jeff Likes, Architect and Nancy Zurcher, tenant / owner per her request.
|
Routing - PLAN CHECK | 4/19/2012 | | 5/23/2012 | | FAIL |
Dan Stuart
|
|
|
Resubmittals required. Plans submitted not accurate or incomplete information. Copy of comments discussed with architect, Jeff Likes on phone and a copy e-mailed to him as follow up. Also notified Nancy Zurcher that plans failed and resubmittals would be required.
|
Telephone call | | | 5/16/2012 | | DONE |
|
|
|
Call from Nancy Zurcher concerning plan submittal review for In Retrospect retail business. Plan review would be the first of next week due to other plan reviews in progress.
|
Plan resubmittals received | | | 5/9/2012 | | DONE |
Christina Prado
|
|
|
Received two sets of plans marked ACS1.1, A1.1, A1.2 & A11.1 as wells as one Response Letter, one Special Inspections Form(301), one HVAC Investigation Report and one United Water sheet. Plans and documents taken to Dan Stuart for additional review
|
Routing - FIRE | 4/17/2012 | 4/17/2012 | 4/19/2012 | | PASS |
Scott Arellano
|
|
|
With conditions and comments
|
1st review completed | | | 4/19/2012 | | FAIL |
|
|
|
Failed - Plan Check
|
Route to Impact Fee Review | 4/17/2012 | 4/20/2012 | 4/17/2012 | | PASS |
Shauna Surgeon
|
|
|
The commercial impact fees were not more than residential impact fees.Nothing due.
|
Plan resubmittals requested | | | 4/17/2012 | | DONE |
|
|
|
Copy of plan review e-mailed to Jeff Likes for response / resubmittals.
|
Routing - PLAN CHECK | 3/21/2012 | | 4/17/2012 | | FAIL |
Dan Stuart
|
|
|
Resubmittals required. Copy of plan review e-mailed to architect and owner. Plans forwarded to fire code analyst for review.
|
Routing - Design Review | 3/20/2012 | | 3/21/2012 | | PASS |
Sarah Schafer
|
|
|
Changing use from office to retail. OK-- No exterior changes proposed. Retail use is allowed per the zone and parking is provided as required by code. JGW
|
Routing PW Sewer Rating | 3/20/2012 | | 3/20/2012 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - PUBLIC WORKS | 3/19/2012 | | 3/20/2012 | | PASS |
Connie Baumgartner
|
|
|
|
Pending Assignment by JCB | 3/16/2012 | | 3/19/2012 | | DONE |
Jason Blais
|
|
|
|
Routing - Addressing | 3/19/2012 | | 3/19/2012 | | PASS |
Terry Records
|
|
|
|
Plan Reviewer's activity | | | 3/19/2012 | | DONE |
Jason Blais
|
|
|
Sent architect an email to contact ACHD for evaluation of any impact fees due or any inspection required. Written verification from ACHD will need to be provided to our Permit Counter prior to the building permit being issued.
|
Application received | | 3/16/2012 | 3/16/2012 | | DONE |
Tisha Gallop
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 3/16/2012 | | DONE |
Tisha Gallop
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 3/16/2012 | | DONE |
Tisha Gallop
|
|
|
|