Third Notice | | 7/10/2012 | 7/12/2012 | | DONE |
|
|
|
|
Second Notice | | 6/16/2012 | 7/5/2012 | | DONE |
|
|
|
faxed to CSDI
|
First Notice | | 6/3/2012 | 6/6/2012 | | DONE |
|
|
|
|
Permanent Occupancy | | | 5/24/2012 | | DONE |
Tisha Gallop
|
|
|
|
FIRE-Final Inspection | 5/22/2012 | 5/23/2012 | 5/23/2012 | A | PASS |
Troy Cobbley
|
|
|
life safety passed
|
BLD-Final | 5/22/2012 | 5/23/2012 | 5/23/2012 | P | PASS |
Mike Jordan
|
|
|
Rocco Phone #: ###-####. ok for perm occ.
|
FIRE-Final Inspection | 5/22/2012 | 5/22/2012 | 5/22/2012 | P | FAIL |
Troy Cobbley
|
|
|
Not ready for a final yet due to the electrician not relocating the duct smoke detector as discussed. To be rescheduled.
|
BLD-Other | 5/17/2012 | 5/17/2012 | 5/17/2012 | P | PASS |
Mike Jordan
|
|
|
ceiling grid//Rocko Phone #: ###-####
|
BLD-Framing/Rough-in | 4/20/2012 | 4/23/2012 | 4/23/2012 | A | PART |
Mike Jordan
|
|
|
Rocco Phone #: ###-####. ok to rock 1hr. fire partitions from 10 ft. above ff to lid only.
|
Route to Impact Fee Review | 4/20/2012 | 4/25/2012 | 4/20/2012 | | PASS |
Cindy M. Gould
|
|
|
No impact fees for tenant improvements
|
Routing - FIRE | 4/19/2012 | 4/20/2012 | 4/20/2012 | | PASS |
Tim Frost
|
|
|
With conditions and comments
|
Plan assigned to (TLW) | 3/30/2012 | | 4/20/2012 | | PASS |
Tim L. Woodard
|
|
|
Level 3 TI (Mall)
|
Routing - PLAN CHECK | 4/20/2012 | | 4/20/2012 | | PASS |
Tim L. Woodard
|
|
|
|
1st review completed | | | 4/20/2012 | | PASS |
|
|
|
Passed
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/20/2012 | | DONE |
Tim L. Woodard
|
|
|
|
Print Occupancy Form | | | 4/20/2012 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 4/20/2012 | | DONE |
Tisha Gallop
|
|
|
|
Telephone call | | | 4/20/2012 | | DONE |
Tisha Gallop
|
|
|
spoke to Jeffrey Langan (CSDI) and told him permit is ready and fees, need GC form
|
Issue PAID IN FULL permit | | | 4/20/2012 | | DONE |
Tisha Gallop
|
|
|
|
Routing - PLAN CHECK | 3/30/2012 | | 4/19/2012 | | PASS |
Tim L. Woodard
|
|
|
|
Routing - PUBLIC WORKS | | | 4/19/2012 | | PASS |
Tim L. Woodard
|
|
|
Approved on Routeing sheet by CB. TLW
|
Case Summary (BLD) | | | 4/19/2012 | | DONE |
Tim L. Woodard
|
|
|
|
Pending Assignment by JCB | 3/28/2012 | | 3/30/2012 | | DONE |
Dan Stuart
|
|
|
|
Routing - Addressing | 3/30/2012 | | 3/30/2012 | | PASS |
Terry Records
|
|
|
|
Application received | | 3/28/2012 | 3/28/2012 | | DONE |
Barbara Stitt
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 3/28/2012 | | DONE |
Christina Prado
|
|
|
|
Intake Approval | | | 3/28/2012 | | PASS |
Dan Stuart
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 3/28/2012 | | DONE |
Christina Prado
|
|
|
|