Case Summary (BLD) | | | 1/24/2014 | | DONE |
|
|
|
|
First Notice | | 6/22/2013 | 8/12/2013 | | DONE |
|
|
|
This permit finaled on the web by Mike McHargue
|
PubWorks Occupancy Approval | 6/12/2013 | 6/12/2013 | 6/12/2013 | | DONE |
Tiffany Lowery
|
|
|
|
Permanent Occupancy | | | 6/12/2013 | | DONE |
Christina Prado
|
|
|
|
BLD-Final | 6/11/2013 | 6/11/2013 | 6/11/2013 | P | PASS |
Mike Jordan
|
|
|
Lets try this again >> Inspection requested via web by Fred Depold. Ok for perm occ.
|
BLD-Final | 6/6/2013 | 6/7/2013 | 6/7/2013 | P | NR |
Mike Jordan
|
|
|
This building is ready for final, Monday 7/10 works however if for any reason your schedule lightens up before Monday we are ready and Mikey will earn brownie points with the owners :-) >> Inspection requested via web by Fred Depold. Complete firecaulking on all rated penetrations, provide tempered glazing were required. Need blower door test results posted.
|
FIRE-Final Inspection | 6/4/2013 | 6/5/2013 | 6/5/2013 | A | PASS |
Troy Cobbley
|
|
|
Fire Life Safety passed. All smoke alarms tested ok.
|
BLD-Footing | 3/11/2013 | 3/12/2013 | 3/12/2013 | A | CANC |
Mike Jordan
|
|
|
mike Phone #: ###-####. Inspection done yesterday in the pm.
|
BLD-Conference | 3/11/2013 | 3/11/2013 | 3/11/2013 | P | PART |
Mike Jordan
|
|
|
Footing for stair foundation, east stairs per RFI from engineer.
|
BLD-Wall cover | 2/6/2013 | 2/7/2013 | 2/7/2013 | A | PASS |
Mike Jordan
|
|
|
This should be the final trip to approve taping in the last units Phone #: ###-#### >> Inspection requested via web by Fred Depold. Remainder of rooms ok to toape.
|
BLD-Wall cover | 2/6/2013 | 2/6/2013 | 2/6/2013 | A | NR |
Mike Jordan
|
|
|
|
BLD-Wall cover | 2/5/2013 | 2/5/2013 | 2/5/2013 | P | PASS |
Mike Jordan
|
|
|
sheet rock inspection balance of building approve to tape
As late in day as possible say 4 would be great if possible >> Inspection requested via web by Fred Depold. south end and middle units, floors 1-3 ok to tape. North units floor 1 and 3 ok. Still working on 2nd. floor.
|
BLD-Wall cover | 2/4/2013 | 2/4/2013 | 2/4/2013 | P | PASS |
Mike Jordan
|
|
|
sheet rock screw off inspection >> Inspection requested via web by Fred Depold
|
BLD-Wall cover | 1/31/2013 | 2/1/2013 | 2/1/2013 | A | PART |
Mike Jordan
|
|
|
Inspect sheet rock screw application to approve taping in building 7 top floor.
Early morning if possible
Thankyou- Fred Phone #: ###-#### >> Inspection requested via web by Fred Depold. Third floor, center units only ok to tape.
|
BLD-Energy code compliance | 1/23/2013 | 1/24/2013 | 1/24/2013 | A | PASS |
Jim Sly
|
|
|
Inspect insulation please and approve for wall cover. Phone #: ###-#### >> Inspection requested via web by Kelly Perryman
|
BLD-Energy code compliance | 1/16/2013 | 1/17/2013 | 1/17/2013 | A | PASS |
Tom Arcoraci
|
|
|
Ready to inspect fire caulking and all penetrations sealed
Thanks- Fred Phone #: ###-#### >> Inspection requested via web by Kelly Perryman
|
BLD-Wall Bracing | 12/11/2012 | 12/11/2012 | 12/11/2012 | P | PASS |
Mike Jordan
|
|
|
Shear Phone #: ###-#### >> Inspection requested via web by Kelly Perryman. Exterior shear and holdowns ok.
|
FIRE-Conference | 12/6/2012 | 12/7/2012 | 12/7/2012 | A | DONE |
Troy Cobbley
|
|
|
Kelly and I discussed the placement of smoke alarms in the resident rooms.
|
BLD-Wall Bracing | 12/5/2012 | 12/6/2012 | 12/6/2012 | A | FAIL |
Mike Jordan
|
|
|
Provide blocking at corridor walls, tighten all holdowns, re-nail all areas that were missed.
|
BLD-Framing/Rough-in | 12/5/2012 | 12/5/2012 | 12/5/2012 | P | NR |
Mike Jordan
|
|
|
Need Shear Inspection >> Inspection requested via web by Kelly Perryman
|
BLD-Foundation | 8/24/2012 | 8/27/2012 | 8/27/2012 | A | PASS |
Mike Jordan
|
|
|
Dane Phone #: ###-####. South half stemwall ok.
|
BLD-Foundation | 8/22/2012 | 8/23/2012 | 8/23/2012 | A | PART |
Mike Jordan
|
|
|
dane Phone #: ###-####. Stemwalls north half only ok.
|
BLD-Footing | 8/17/2012 | 8/20/2012 | 8/20/2012 | A | PASS |
Mike Jordan
|
|
|
Dane Phone #: ###-####
|
Permit Ready to Issue | | | 8/16/2012 | | DONE |
Barbara Stitt
|
|
|
|
Issue PAID IN FULL permit | | | 8/16/2012 | | DONE |
Barbara Stitt
|
|
|
|
Print Occupancy Form | | | 8/16/2012 | | DONE |
Barbara Stitt
|
|
|
|
Plan assigned to (DRS) | 4/13/2012 | 4/13/2012 | 6/28/2012 | | PASS |
Dan Stuart
|
|
|
|
Routing - PLANNING Land Div | 4/13/2012 | | 6/28/2012 | | PASS |
Dave Abo
|
|
|
|
Routing - PUBLIC WORKS | 4/13/2012 | | 6/28/2012 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - Erosion and Sediment | 4/13/2012 | | 6/28/2012 | | PASS |
Clint A Smith
|
|
|
ESC###-####7 appproved with conditions attached to the permit.
|
Routing Off Site - STRUCTURAL | 5/24/2012 | | 6/28/2012 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 6/28/2012 | | 6/28/2012 | | PASS |
Dan Stuart
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/28/2012 | | PASS |
|
|
|
|
Routing - MECHANICAL | 5/24/2012 | | 6/1/2012 | | PASS |
Troy James
|
|
|
|
Routing - Design Review | 5/24/2012 | | 5/31/2012 | | PASS |
Josh Wilson
|
|
|
|
Routing - PLAN CHECK | 5/24/2012 | | 5/31/2012 | | PASS |
Dan Stuart
|
|
|
Approved with red line notes and all attached plan reviews of all agencies.
|
Routing - PLANNING | 4/13/2012 | | 5/31/2012 | | PASS |
Susan Riggs
|
|
|
|
Routing - PLUMBING | 5/30/2012 | | 5/30/2012 | | PASS |
Bill VanDegrift
|
|
|
3 TOILETS MAX ON 3" HORIZONTAL WASTE
|
Plan resubmittals received | | | 5/24/2012 | | DONE |
Dan Stuart
|
|
|
Resubmittals routed back to all agencies requiring re-review.
|
Routing - PLAN CHECK | 4/13/2012 | | 5/17/2012 | | FAIL |
Dan Stuart
|
|
|
Resubmittals required. See plan review attached to BLD12-00678, Bldg. #5, applicable to all buildings in this project.
|
Routing Off Site - STRUCTURAL | 4/13/2012 | | 4/30/2012 | | FAIL |
|
|
|
|
Routing - PLUMBING | 4/13/2012 | | 4/19/2012 | | FAIL |
Bill VanDegrift
|
|
|
see bld12-00678 for comments
|
Routing - Design Review | 4/13/2012 | | 4/18/2012 | | FAIL |
Josh Wilson
|
|
|
Design Review and CUP modification required.
|
Routing - MECHANICAL | 4/13/2012 | | 4/17/2012 | | FAIL |
Troy James
|
|
|
talked to cathy with ECI for corrections to be made
|
Routing - FIRE | 4/13/2012 | | 4/17/2012 | | PASS |
Scott Arellano
|
|
|
Attached IFC comments to plans
|
Route to Impact Fee Review | 4/13/2012 | 4/18/2012 | 4/16/2012 | | PASS |
Shauna Surgeon
|
|
|
|
Routing - Addressing | 4/13/2012 | | 4/16/2012 | | PASS |
Terry Records
|
|
|
For Apt #'s See Addressing Documents- Apartment Bldgs should use Apt #'s created by the City to meet Addressing requirements.
|
Intake Approval | | | 4/10/2012 | | PASS |
Dan Stuart
|
|
|
|
Application received | | | 3/29/2012 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 29 2012 1:46PM
|