Permit Information
Permit NumberBLD12-00684
StatusFinaled
Name TRILOGY DEVELOPMENT INC
Site Address 1487 S GOLDKING WAY
Project NameUnion Square Apartments Bld11
Customer Number 
ePlanReviewNo
Description
(Union Square Apartments, BLD - 11) To construct a wood frame, three story, 11,232 sq. ft., 18 Unit Multi Family Dwellings (18 -1B/1B Jr.), per reviewed plans. All units exceed 800 sq. ft., are fully sprinklered W/ alarm. Work includes associated site work, footing & foundation, structural & non-structural framing; electrical, mechanical, plumbing, sprinkler & alarm work; fire-resistive construction between units, at stair enclosures or rated corridor breezeways; accessible Type 'B' units; interior cabinetry, wall, floor and ceiling finishes and fixtures. All per the reviewed plans. drs DRH12-00022 CUP08-00045
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Case Summary (BLD)  1/24/2014 DONE
First Notice 5/10/20138/12/2013 DONE
This permit finaled on the web by Mike McHargue
Permanent Occupancy  4/30/2013 DONE
DetailsChristina Prado
Zoning Approval4/15/20134/15/20134/15/2013 PASS
DetailsJosh Wilson
Building 11 is complete.
Override - Parcel Holds  4/15/2013  
PubWorks Occupancy Approval4/10/20134/10/20134/10/2013 DONE
DetailsBrian Murphy
Per occupancy sign off card
Change Expiration Date Only  3/12/2013 DONE
DetailsBarbara Stitt
BLD-Final2/28/20132/28/20132/28/2013PPASS
DetailsMike Jordan
Michael Phone #: ###-####. Will be ok for perm occ. once zoning signs perms.
FIRE-Final Inspection2/27/20132/28/20132/28/2013APASS
DetailsTroy Cobbley
life safety passed
Temporary Occupancy2/1/20135/2/20132/1/2013 DONE
DetailsBarbara Stitt
BLD-Final1/31/20131/31/20131/31/2013PPART
DetailsMike Jordan
MIKE Phone #: ###-####. OK for eprm occ.
Zoning Approval Temp1/30/20131/30/20131/30/2013 DONE
DetailsSarah Schafer
BLD-Final1/23/20131/23/20131/23/2013PPEND
DetailsJim Sly
We are requesting a Final Inspection "Consultation" for our first building Phone #: ###-#### >> Inspection requested via web by Kelly Perryman

Explained requirements to obtain Certificate of Occupancy.
BLD-Other10/25/201210/25/201210/25/2012PPASS
DetailsMike Jordan
base layer, 1hr. corridor lids ok.
BLD-Other10/24/201210/24/201210/24/2012PNR
DetailsMike Jordan
BLD-Other10/24/201210/24/201210/24/2012ANR
DetailsMike Jordan
BLD-Other10/23/201210/23/201210/23/2012PPASS
DetailsMike Jordan
1st. floor party walls and horizontal assemblies ok. Base layer 2nd floor corridor ceiling ok, face layer 1st floor corridor ceiling ok.
BLD-Other10/22/201210/23/201210/23/2012APART
DetailsMike Jordan
1st floor party walls and face layers of 5/8 type x rock, corridor base layers of 5/8 type x rock at floor ceiling assemblies.
BLD-Other10/22/201210/22/201210/22/2012PPART
DetailsMike Jordan
Face layer 5/8 type x rock at horizontal assembly. 1st. floor.
BLD-Conference10/22/201210/22/201210/22/2012APART
DetailsMike Jordan
BAse layer for horizontal assembly, 1st. foor.
BLD-Other10/19/201210/19/201210/19/2012PPASS
DetailsMike Jordan
2nd floor horizontal assemblies and fire partions in dwelling units ok for cover.
BLD-Other10/19/201210/19/201210/19/2012APART
DetailsMike Jordan
BAse and face layers for horizontal assembly, 2nd. floor.
BLD-Other10/18/201210/18/201210/19/2012PPART
DetailsMike Jordan
2nd floor horizontal assembly, base layers.
BLD-Other10/17/201210/18/201210/18/2012APASS
DetailsMike Jordan
2nd. floor 1hr. horizontal assembly, base layer of 5/8 type x rock ok.
BLD-Conference10/17/201210/17/201210/17/2012PDONE
DetailsMike Jordan
Went over horizontal assembly detail with sheet rock foreman.
BLD-Energy code compliance10/17/201210/17/201210/17/2012PPASS
DetailsMike Jordan
BLD-Conference10/12/201210/12/201210/12/2012PPASS
DetailsTom Arcoraci
BLD-Framing/Rough-in10/10/201210/10/201210/10/2012PPART
DetailsTom Arcoraci
Need to have Jim come out for a framing re inspection Phone #: ###-#### >> Inspection requested via web by Kelly Perryman
BLD-Framing/Rough-in10/5/201210/5/201210/5/2012PPART
DetailsTom Arcoraci
Phone #: ###-#### >> Inspection requested via web by Kelly Perryman dicussed fire stopping
BLD-Wall Bracing8/24/20128/24/20128/24/2012PPASS
DetailsMike Jordan
kelly Phone #: ###-####. Exterior shear wall and all required straps installed. ok to cover.
BLD-Conference8/20/20128/20/20128/20/2012PDONE
DetailsMike Jordan
Spoke to framing subcontractor abput truss blocking.
BLD-Conference8/9/20128/10/20128/10/2012ADONE
DetailsMike Jordan
Meeting with subcotractors. Met with subcontractors on site to discuss all rated penetrations and what will be required.
BLD-Conference7/26/20127/26/20127/27/2012PDONE
DetailsMike Jordan
BLD-Conference7/24/20127/24/20127/24/2012ADONE
DetailsMike Jordan
Reviewed plans, framing, and firerated construction details with framer and general contractor.
Permit Ready to Issue  7/18/2012 DONE
DetailsChristina Prado
Issue PAID IN FULL permit  7/18/2012 DONE
DetailsChristina Prado
Plan assigned to (DRS)4/13/20124/13/20126/28/2012 PASS
DetailsDan Stuart
Routing - PLANNING Land Div4/13/2012 6/28/2012 PASS
DetailsDave Abo
Routing - PUBLIC WORKS4/13/2012 6/28/2012 PASS
DetailsConnie Baumgartner
Routing - Erosion and Sediment4/13/2012 6/28/2012 PASS
DetailsClint A Smith
ESC12-00371 appproved with conditions attached to the permit.
Routing - PLAN CHECK5/24/2012 6/28/2012 PASS
DetailsDan Stuart
Approved with red line notes and all attached plan reviws of all reviewing agencies.
Routing Off Site - STRUCTURAL5/24/2012 6/28/2012 PASS
Details
PLANS/APPL TAKEN TO FRONT DESK  6/28/2012 PASS
Routing - PLANNING5/24/2012 6/27/2012 PASS
DetailsSusan Riggs
Print Occupancy Form  6/27/2012 DONE
Routing - MECHANICAL5/24/2012 6/1/2012 PASS
DetailsTroy James
Routing - Design Review5/24/2012 5/31/2012 PASS
DetailsJosh Wilson
Routing - PLANNING4/13/2012 5/31/2012 PASS
DetailsSusan Riggs
Routing - PLUMBING5/30/2012 5/30/2012 PASS
DetailsBill VanDegrift
added sizing note.
Plan resubmittals received  5/24/2012 DONE
Resubmittals re-routed for re-review to applicable agencies.
Routing - PLAN CHECK4/13/2012 5/17/2012 FAIL
DetailsDan Stuart
Resubmittals required. See plan review attached to BLD12-00678, Bldg. #5, applicable to all buildings in this project.
Routing Off Site - STRUCTURAL4/13/2012 4/30/2012 FAIL
Details
Routing - PLUMBING4/13/2012 4/19/2012 FAIL
DetailsBill VanDegrift
see bld12-00678 for comments
Routing - Design Review4/13/2012 4/18/2012 FAIL
DetailsJosh Wilson
Design Review and CUP modification required.
Telephone call  4/18/2012 DONE
DetailsJosh Wilson
Applicant contacted to inform of need for CUP and DR modifications. Submitted site plan does not match approved plans in CUP10-00070 for location and layout of apartment buildings. Design Review modification will be required for minor changes to pool building layout and apartment building elevations.
Routing - MECHANICAL4/13/2012 4/17/2012 FAIL
DetailsTroy James
talked to cathy with ECI about corrections to be made
Routing - FIRE4/13/2012 4/17/2012 PASS
DetailsScott Arellano
Attached IFC comments to permit case.
Route to Impact Fee Review4/13/20124/18/20124/16/2012 PASS
DetailsShauna Surgeon
Routing - Addressing4/13/2012 4/16/2012 PASS
DetailsTerry Records
For Apt #'s See Addressing Documents- Apartment Bldgs should use Apt #'s created by the City to meet Addressing requirements.
Intake Approval  4/10/2012 PASS
DetailsDan Stuart
Application received  3/29/2012 DONE
Application submitted via PDS Online on Mar 29 2012 1:46PM