Third Notice | | 6/10/2014 | 6/10/2014 | | DONE |
|
|
|
This permit finaled on the web by Mike McHargue
|
Second Notice | | 5/4/2014 | 6/5/2014 | | DONE |
|
|
|
e-mailed to John Laude and Mike McHargue at Trilogy Dev.
|
First Notice | | 4/12/2014 | 4/24/2014 | | DONE |
|
|
|
mailed
|
Permanent Occupancy | | | 4/2/2014 | | DONE |
Christina Prado
|
|
|
|
BLD-Final | 8/13/2013 | 8/13/2013 | 8/13/2013 | P | PASS |
Mike Jordan
|
|
|
Carports Phone #: ###-#### >> Inspection requested via web by Mike McHargue
|
FIRE-Final Inspection | 8/12/2013 | 8/12/2013 | 8/13/2013 | P | PASS |
Troy Cobbley
|
|
|
life safety passed
|
BLD-Footing | 6/24/2013 | 6/25/2013 | 6/25/2013 | A | PASS |
Jim Sly
|
|
|
Inspect posts and approve for concrete in front of building 7 Phone #: ###-#### >> Inspection requested via web by Fred Depold
|
BLD-Footing | 6/13/2013 | 6/14/2013 | 6/14/2013 | A | PASS |
Mike Jordan
|
|
|
Footing inspection please Phone #: ###-#### >> Inspection requested via web by Fred Depold
|
BLD-Footing | 6/5/2013 | 6/5/2013 | 6/5/2013 | P | PASS |
Mike Jordan
|
|
|
footing inspection after 2pm please Phone #: ###-#### >> Inspection requested via web by Fred Depold
|
BLD-Footing | 5/23/2013 | 5/24/2013 | 5/24/2013 | A | PASS |
Mike Jordan
|
|
|
mike Phone #: ###-####
|
Issue PAID IN FULL permit | | | 12/10/2012 | | DONE |
Barbara Stitt
|
|
|
|
Print Occupancy Form | | | 12/10/2012 | | DONE |
Barbara Stitt
|
|
|
|
Case Summary (BLD) | | | 12/3/2012 | | DONE |
|
|
|
|
Plan assigned to (DRS) | 10/17/2012 | 10/17/2012 | 11/30/2012 | | PASS |
Dan Stuart
|
|
|
|
Routing - PLAN CHECK | 11/5/2012 | | 11/30/2012 | | PASS |
Dan Stuart
|
|
|
|
Plan resubmittals received | | | 11/29/2012 | | DONE |
Dan Stuart
|
|
|
|
Routing - PLAN CHECK | 10/18/2012 | | 11/5/2012 | | FAIL |
Dan Stuart
|
|
|
Resubmittals required. Copy of review and changemearks attached to ePlan review sent back to architect.
|
Plan resubmittals requested | | | 11/5/2012 | | DONE |
|
|
|
|
Plan Modification Accepted | | | 10/17/2012 | | DONE |
Tisha Gallop
|
|
|
started plan mod workflow for deferred submittals for engineering of carports.
|
Plan resubmittals received | | | 10/16/2012 | | DONE |
Tisha Gallop
|
|
|
received two paper copies of carport engineering; taken to Dan Stuart.
|
Extend Review Timeline | | | 9/14/2012 | | DONE |
Christina Prado
|
|
|
|
Plan assigned to (DRS) | 4/13/2012 | 4/13/2012 | 6/28/2012 | | PASS |
Dan Stuart
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/28/2012 | | PASS |
Dan Stuart
|
|
|
Deferred submittals pre-engineering
|
Permit Ready to Issue | | | 6/28/2012 | | DONE |
Barbara Stitt
|
|
|
|
Routing - Design Review | 5/24/2012 | | 6/27/2012 | | PASS |
Josh Wilson
|
|
|
|
Routing - PLAN CHECK | 5/24/2012 | | 5/31/2012 | | PASS |
Dan Stuart
|
|
|
Approved as deferred submittal as allowed by code. NO WORK shall be performed for these carports until plans have been submitted and approved by architect, structural engineer and all involved agencies.
|
Plan resubmittals received | | | 5/24/2012 | | DONE |
Dan Stuart
|
|
|
Declared as deferred submittal as allowed by code. NO WORK shall be performed for these carports until plans have been submitted and approved by architect, structural engineer and all involved agencies.
|
Routing - PLAN CHECK | 4/13/2012 | | 5/17/2012 | | FAIL |
Dan Stuart
|
|
|
Resubmittals required. See plan review attached to BLD12-00678, Bldg. #5, applicable to all buildings in this project.
|
1st review completed | | | 5/17/2012 | | FAIL |
Dan Stuart
|
|
|
|
Routing - Erosion and Sediment | 4/13/2012 | | 4/19/2012 | | PASS |
Clint A Smith
|
|
|
ESC12-00294 plan approved with conditions attached to the permit.
|
Routing PW Drainage | 4/13/2012 | | 4/18/2012 | | PASS |
Brian Murphy
|
|
|
|
Routing - Design Review | 4/13/2012 | | 4/18/2012 | | FAIL |
Josh Wilson
|
|
|
Design Review and CUP modification required.
|
Route to Impact Fee Review | 4/13/2012 | 4/18/2012 | 4/17/2012 | | PASS |
Shauna Surgeon
|
|
|
|
Routing - FIRE | 4/13/2012 | | 4/16/2012 | | PASS |
Scott Arellano
|
|
|
Attached IFC comments to plans
|
Routing - Addressing | 4/13/2012 | | 4/16/2012 | | PASS |
Terry Records
|
|
|
|
Routing - PUBLIC WORKS | 4/13/2012 | | 4/13/2012 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - PLANNING | 4/13/2012 | | 4/13/2012 | | PASS |
Susan Riggs
|
|
|
CUPO8-00045
|
Routing - PLANNING Land Div | 4/13/2012 | | 4/13/2012 | | PASS |
Dave Abo
|
|
|
Lot 7 of Union Square Subdivision No. 2
|
Intake Approval | | | 4/10/2012 | | PASS |
Dan Stuart
|
|
|
|
Application received | | | 3/29/2012 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 29 2012 1:49PM
|