BLD-Final | 6/25/2012 | 6/26/2012 | 6/26/2012 | A | PASS |
Tony Young
|
|
|
Jake Phone #: ###-####
|
DOC - Permit Finaled | 6/26/2012 | 6/26/2012 | 6/26/2012 | P | PASS |
Tony Young
|
|
|
c of o issued
|
BLD-Energy code compliance | 5/25/2012 | 5/29/2012 | 5/29/2012 | A | PASS |
Mike Jordan
|
|
|
Jason Phone #: ###-####
|
BLD-Energy code compliance | 5/24/2012 | 5/25/2012 | 5/25/2012 | P | CANC |
Mike Jordan
|
|
|
jake Phone #: ###-####
|
BLD-Framing/Rough-in | 5/25/2012 | 5/25/2012 | 5/25/2012 | P | FAIL |
Mike Jordan
|
|
|
jake Phone #: ###-####. Fireblock plumbing chase at 1st floor ceiling level. Fireblock top and bottom plates, 2nd. floor at laundry room. nail bottom chord of AG1 2 ply truss at 2" oc as per truss engineering. Ok to insulate. Correction notice posted.
|
BLD-Wall Bracing | 5/25/2012 | 5/25/2012 | 5/25/2012 | P | PASS |
Mike Jordan
|
|
|
jake Phone #: ###-####. Shear nailing ok.
|
BLD-Framing/Rough-in | 5/23/2012 | 5/24/2012 | 5/24/2012 | A | NR |
Mike Jordan
|
|
|
jake Phone #: ###-####. Needs plumbing rough in inspection, Noted no shear nail inspection, may have to remove exterior wheather barrier for inspection.
|
BLD-Foundation | 5/2/2012 | 5/2/2012 | 5/2/2012 | A | PART |
Mike Jordan
|
|
|
|
BLD-Foundation | 4/30/2012 | 5/1/2012 | 5/2/2012 | P | CANC |
Mike Jordan
|
|
|
Phone #: 8604108 >> Inspection requested via mobile web by ryan
|
BLD-Footing | 4/30/2012 | 4/30/2012 | 4/30/2012 | P | PASS |
Mike Jordan
|
|
|
Phone #: 8604108 >> Inspection requested via mobile web by ryan
|
Issue PAID IN FULL permit | | | 4/24/2012 | | DONE |
Tisha Gallop
|
|
|
|
OVERRIDE | | | 4/18/2012 | | |
|
|
|
|
Inspection Record Card- Bld | | | 4/18/2012 | | DONE |
|
|
|
|
Telephone call | | | 4/18/2012 | | DONE |
Christina Prado
|
|
|
Called and gave Tanya fees due
|
Permit Ready to Issue | | | 4/18/2012 | | DONE |
Christina Prado
|
|
|
|
Plan assigned to (CDM) | | 4/2/2012 | 4/17/2012 | | PASS |
Carl D Madsen
|
|
|
|
Routing - PLAN CHECK | 4/5/2012 | | 4/17/2012 | | PASS |
Carl D Madsen
|
|
|
|
1st review completed | | | 4/17/2012 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 4/17/2012 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/17/2012 | | |
|
|
|
|
Routing - MECHANICAL | 4/5/2012 | | 4/5/2012 | | PASS |
Troy James
|
|
|
|
Routing - MECHANICAL | 4/3/2012 | | 4/5/2012 | | FAIL |
Troy James
|
|
|
emailed correction to Brownco
|
Route to Impact Fee Review | 4/2/2012 | 4/5/2012 | 4/3/2012 | | PASS |
Cindy M. Gould
|
|
|
|
Routing - PLANNING | 4/3/2012 | | 4/3/2012 | | PASS |
Todd Tucker
|
|
|
|
Routing - Addressing | 4/2/2012 | | 4/3/2012 | | PASS |
Terry Records
|
|
|
|
Routing - PUBLIC WORKS | 4/3/2012 | | 4/3/2012 | | PASS |
Connie Baumgartner
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 4/2/2012 | | DONE |
Christina Prado
|
|
|
|
Intake Approval | | | 4/2/2012 | | PASS |
Christina Prado
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 4/2/2012 | | DONE |
Christina Prado
|
|
|
|
Application received | | 4/2/2012 | | | |
|
|
|
|