Permit Information
Permit NumberBLD12-00739
StatusFinaled
Name DAVE EVANS CONSTRUCTION
Site Address 2211 N 26TH ST
Project NameBoise River Montessori
Customer Number 
ePlanReviewNo
Description
(BOISE RIVER MONTESSORI) - To Construct a new 1,400 square foot, one story, wood framed school building and related site improvements. All construction per the approved plans and attached comment list. JCM 12/5/12 - Occupant load for the daycare facility (includes new and existing daycare buildings on property) established by CUP11-00089 is 60 children plus staff. The facility owner, Antonio J. Gonzalez, Jr. provided written request (copy attached) asking the occupant load for this new building (located in NW corner of property) be established at 20 children + 4 staff and original daycare (MIS06-00188) modified to be 40 children + 5 staff for a total of 60 children plus 9 staff. New certificates of occupancy will be issued with new occupant loads and staff. drs
Contact Information
See Activities list for contact information
Color Key
Current location of plans being reviewed:  
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Third Notice 3/27/20134/4/2013 DONE
Third Notice 2/26/20133/22/2013 DONE
faxed
Third Notice 2/2/20132/21/2013 DONE
faxed to Dave Evans Const
Second Notice 1/13/20131/28/2013 DONE
First Notice 12/17/20121/3/2013 DONE
faxed to Dave Evans Const
Permanent Occupancy  12/7/2012 DONE
DetailsBarbara Stitt
Print Pending Permit.LaserJet4  12/5/2012  
Case Summary (BLD)  12/5/2012  
Permanent Occupancy  11/27/2012 DONE
DetailsTisha Gallop
Voided and re-issued new on on 12-7-12 per Dan Stuart
BLD-Final11/26/201211/26/201211/26/2012PPASS
DetailsTony Young
Dave Phone #: ###-####
Zoning Approval11/21/201211/21/201211/21/2012 DONE
DetailsSusan Riggs
BLD-Final11/15/201211/16/201211/16/2012APART
DetailsTony Young
call before//Dave Phone #: ###-####,, temp ok
PubWorks Occupancy Approval11/16/201211/16/201211/16/2012 DONE
DetailsTiffany Lowery
BLD-Conference11/14/201211/15/201211/15/2012APART
DetailsTony Young
call before//Dave Phone #: ###-####,, temp occ ok,,, need other trades
FIRE-Final Inspection11/13/201211/13/201211/13/2012PPASS
DetailsTroy Cobbley
Life safety passed. Dave is going to remove the manual flush bolts on the interior double doors and replace with magnetic/friction stops.
BLD-Ceiling Grid Inspection10/22/201210/22/201210/22/2012PPASS
DetailsTom Arcoraci
dave Phone #: ###-####
BLD-Other10/18/201210/18/201210/18/2012PFAIL
DetailsTony Young
dave Phone #: ###-####,, correction posted
BLD-Energy code compliance8/30/20128/31/20128/31/2012APASS
DetailsTony Young
Dave Phone #: ###-####
BLD-Framing/Rough-in8/27/20128/28/20128/28/2012APART
DetailsTony Young
dave Phone #: ###-####,, ok to insulate walls,, may need to move ducting in attic for energy compliance
BLD-Framing/Rough-in8/23/20128/23/20128/23/2012PPART
DetailsJim Storey
Dave Phone #: ###-####c/n on site ok to insulate
BLD-Framing/Rough-in8/20/20128/21/20128/21/2012APART
DetailsTony Young
Dave Phone #: ###-####,, need truss engineering
BLD-Other8/6/20128/7/20128/7/2012PPASS
DetailsTony Young
DAVE Phone #: ###-####,, ext shear ok
BLD-Framing/Rough-in8/1/20128/2/20128/2/2012AFAIL
DetailsTony Young
Dave-Shear nail inspection please--Please call at least 15-30 mins prior to inspection Phone #: ###-####,, ok to cover roof,,, need to nail or staple shear/brace per plan,, 3/8" away from edges,, flush nail,, nail double studs above hold downs,, space nailing on shear plan is a maximum distance between fasteners
BLD-Foundation7/9/20127/11/20127/11/2012ADONE
DetailsTony Young
Phone #: 2089410987 >> Inspection requested via mobile web by Bill
BLD-Footing7/9/20127/10/20127/10/2012APASS
DetailsTony Young
Phone #: 2089410987 >> Inspection requested via mobile web by Bill
Issue PAID IN FULL permit  6/28/2012 DONE
DetailsChristina Prado
Plan assigned to (JCM)4/5/2012 5/31/2012 PASS
DetailsJohn Menard
Routing - PLAN CHECK5/30/2012 5/31/2012 PASS
DetailsJohn Menard
PLANS/APPL TAKEN TO FRONT DESK  5/31/2012 DONE
DetailsJohn Menard
CHANGE STATUS TO (REV)  5/31/2012  
Plan assigned to (JCM)5/31/2012 5/31/2012 PASS
DetailsJohn Menard
Routing - Erosion and Sediment5/31/2012 5/31/2012 PASS
DetailsClint A Smith
ESC12-00320 plan approved with additional conditions attached to the permit.
PLANS/APPL TAKEN TO FRONT DESK  5/31/2012 DONE
DetailsJohn Menard
Print Occupancy Form  5/31/2012 DONE
Telephone call  5/31/2012 DONE
spoke with Scott, permit ready, fees given need ACHD
Permit Ready to Issue  5/31/2012 DONE
Routing - FIRE5/29/2012 5/30/2012 PASS
DetailsScott Arellano
Attached IFC comments to plans
Routing - PLAN CHECK5/14/2012 5/29/2012  
DetailsJohn Menard
Route to Impact Fee Review5/10/20125/15/20125/17/2012 PASS
DetailsCindy M. Gould
1st review completed  5/14/2012 FAIL
Failed Public Works, Plan Check, Fire
Routing - FIRE5/11/2012 5/14/2012 FAIL
DetailsScott Arellano
Faxed and emailed resubmittal items to architect.
Routing - PLUMBING5/11/2012 5/11/2012 PASS
DetailsDaryl Spivey
Per plans and 2003 UPC.
Plan resubmittals received  5/11/2012 DONE
DetailsAlexandra L. DeYoung
rec'd two copies of response letter and sheets A1.0 and A2.1 - inserted by GC and taken back to fire.
Routing - PLAN CHECK4/25/2012 5/10/2012 FAIL
DetailsJohn Menard
Plan Reviewer's activity  5/10/2012 FAIL
DetailsJohn Menard
Reviewed structural and nonstructural code requirements. JCM
Plan resubmittals requested  5/10/2012 DONE
DetailsJohn Menard
E-mailed the architect a copy of the plan review requesting revisions. JCM
Routing - PUBLIC WORKS4/24/2012 4/25/2012 PASS
DetailsConnie Baumgartner
Routing PW Drainage4/24/2012 4/25/2012 PASS
DetailsBrian Murphy
Routing - PLAN CHECK4/13/2012 4/24/2012  
DetailsJohn Menard
Plan resubmittals received  4/23/2012 DONE
DetailsTisha Gallop
received two copies of Technical Memo, Geotechnical Report and five copies of plan sheet C1; inserted by eng. rep. and taken back to John Menard.
Plan resubmittals received  4/17/2012 DONE
DetailsChristina Prado
Received two sets of ESC plans and two sets of Stormwater Prevention Plan & Esc Plan documents. Inserted by Christina into existing plans
Routing - PLANNING4/12/2012 4/13/2012 PASS
DetailsSusan Riggs
Routing - Erosion and Sediment4/11/2012 4/12/2012 FAIL
DetailsClint A Smith
ESC12-00320 plan waiver denied due to the type of project and location. Notified the applicant of the denial and the requiremnts that must be submitted. Must provide a ESC plan with narrative.
Routing PW Drainage4/9/2012 4/11/2012 FAIL
DetailsBrian Murphy
NEEDS 3 TO 1 SIDESLOPES
Routing PW Sewer Rating4/6/2012 4/9/2012 PASS
DetailsConnie Baumgartner
Routing - Addressing4/6/2012 4/6/2012 PASS
DetailsTerry Records
Routing - PLANNING Land Div4/5/2012 4/6/2012 PASS
DetailsDave Abo
Parcel "A" of Record of Survey 6117.
Plans ACCEPTED BY PLAN TECH  4/5/2012 DONE
DetailsChristina Prado
Recd Pcfee & Taken To Pln CK  4/5/2012 DONE
DetailsChristina Prado
Pending Assignment by JCM4/5/2012 4/5/2012 DONE
DetailsJohn Menard
Application received 4/5/2012   
Routing PW Solid Waste    CANC
DetailsPeter J. McCullough
Routing - PUBLIC WORKS4/6/2012   FAIL
DetailsBeverly Mountain
Failed by Brian Murphy
Routing - PLAN CHECK5/31/2012