Permit Information
Permit NumberBLD12-00742
StatusFinaled
Name Scott Findlay
Site Address 1534 S VISTA AVE
Project NameHoppie Building
Customer Number 
ePlanReviewYes
Description
(SHELL & CORE - Hoppie Building - 2nd Floor) Permit is to upgrade an existing non-compliant situation. **An upgrade agreement is attached to the permit** Approval contingent upon adhering to the approved plans on file. Work to include: construction of interior nonbearing 1-hour walls to create a corridor to the second exit stairway, replace existing doors with new 20 min doors (including new hardware and closers), and finishes in compliance with chapter 8 of the 2009 IBC. This
building is not fire sprinklered. **TLW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Third Notice 7/14/20149/8/2014 DONE
DetailsChristina Prado
Case Summary (BLD)  8/29/2014 DONE
Telephone call  7/11/2014 DONE
DetailsCandy A. Nichols
as per Karla Berg-as of 10/12/12 they were fired from this job.
she said Future Techs did not do the work. I changed the primary to parcel owner so Future Tech would not get any more letters.
Second Notice 6/15/20147/9/2014 DONE
Agreement of Future work4/11/20133/5/20146/13/2014 DONE
DetailsTim L. Woodard
Upgrade Agreement for this building attached to this case.
4/5/12 A revised Upgrade Agreement is attached to this case as there is a new building owner.
6/12/14 Upgrade Agreement work complete. Copy of recorded Notice of Compliance attached to this case.
First Notice6/2/20146/2/20146/5/2014 DONE
DetailsJim Storey
BLD-Final6/2/20146/2/20146/2/2014PPASS
DetailsJim Storey
DOC - Permit Finaled6/2/20146/2/20146/2/2014PPASS
DetailsJim Storey
BLD-Final5/28/20145/30/20145/30/2014PNR
DetailsJim Storey
allison Phone #: ###-####
FIRE-Final Inspection5/28/20145/30/20145/30/2014APASS
DetailsForrest France
Scope of work completed. However, noted seven doors in need of adjustment at the closures to ensure self-closing and latching functionality. Doors include; suites 1,5,7,9,10,12 and the janitors room. To be repaired and verified at structural final as agreed.
BLD-Other4/17/20134/17/20134/15/2013PPEND
DetailsJim Storey
Phase four of upgrade aggreement still outstanding, work in progress.
Zoning Approval10/11/201210/11/201210/11/2012 PASS
DetailsJosh Wilson
Inspection Record Card- Bld  9/6/2012 DONE
Inspection Record Card- Bld  9/6/2012 DONE
BLD-Framing/Rough-in6/15/20126/15/20126/18/2012PPASS
DetailsJim Storey
alicia Phone #: ###-#### need rated access in ceilling.
Inspection Record Card- Bld  5/25/2012 DONE
Permit Ready to Issue  5/25/2012 DONE
Issue PAID IN FULL permit  5/25/2012 DONE
PLANS/APPL TAKEN TO FRONT DESK  4/27/2012 DONE
DetailsTim L. Woodard
Plan assigned to (TLW)4/11/2012 4/27/2012 PASS
DetailsTim L. Woodard
ePlanReview case
Routing - Design Review4/26/2012 4/26/2012 PASS
DetailsJosh Wilson
Ok CZC12-00096
1st review completed  4/25/2012 DONE
DetailsTim L. Woodard
Routing - PLAN CHECK4/11/2012 4/25/2012 PASS
DetailsTim L. Woodard
Approved with redline clarifications. TLW
Routing - FIRE4/11/2012 4/13/2012 PASS
DetailsScott Arellano
No comments attached.
Routing - Design Review4/11/2012 4/12/2012 FAIL
DetailsSarah Schafer
Sarah Schafer - Minor exterior change at rear of building
A zoning certificate is required for the exterior changes. I notified the applicant and they will be bring it in.
Intake Approval  4/11/2012 PASS
Tim Woodard approved the intake.
Pending Assignment by JCB4/11/2012 4/11/2012 DONE
DetailsJason Blais
Intake Approval  4/9/2012 FAIL
DetailsTim L. Woodard
Tom,

Please have forms 302, 304, and 306 signed / scanned and reuploaded. Be sure to sign off on your task when that is complete. Call if you have any questions ###-####
Payment Received  4/5/2012 DONE
Payment received via Govolutions
Application received  4/5/2012 DONE
Application submitted via PDS Online on Apr 5 2012 11:59AM