Permanent Occupancy | | | 7/9/2012 | | DONE |
Christina Prado
|
|
|
|
BLD-Final | 6/29/2012 | 7/2/2012 | 7/3/2012 | P | PASS |
Dave Hannah
|
|
|
Jeff Phone #: ###-####
|
BLD-Final | 7/3/2012 | 7/3/2012 | 7/3/2012 | P | PASS |
Dave Hannah
|
|
|
Steve Ove Phone #: ###-####
|
FIRE-Final Inspection | 6/29/2012 | 7/2/2012 | 7/2/2012 | A | PASS |
Forrest France
|
|
|
Noted conditions for final occupancy field verified for completion. Life safety final approved.
|
FIRE-Final Inspection | 6/14/2012 | 6/14/2012 | 6/14/2012 | A | NR |
Forrest France
|
|
|
|
FIRE-Final Inspection | 6/6/2012 | 6/6/2012 | 6/6/2012 | A | PART |
Forrest France
|
|
|
TCO approved. Final pending repairs.
|
BLD-Final | 6/4/2012 | 6/5/2012 | 6/5/2012 | P | PART |
Dave Hannah
|
|
|
Jeff Phone #: ###-#### ok for temp occ
|
FIRE-Final Inspection | 6/4/2012 | 6/5/2012 | 6/5/2012 | A | PART |
Forrest France
|
|
|
Temporary occupancy approved per contractor agreement with J. Blais and R. Gervais. Final pending corrections underway in the warehouse area. Remainder of C/N items are finished.
|
Temporary Occupancy | 6/5/2012 | 9/3/2012 | 6/5/2012 | | DONE |
Alexandra L. DeYoung
|
|
|
|
FIRE-Conference | 6/4/2012 | 6/4/2012 | 6/4/2012 | P | DONE |
Forrest France
|
|
|
Regarding C/N items, project schedule.
|
BLD-Final | 5/31/2012 | 6/1/2012 | 6/4/2012 | P | NR |
Dave Hannah
|
|
|
Building Final - Please call Steve Ove ###-#### Phone #: ###-#### >> Inspection requested via web by Brian Warbis needs a fire final first
|
FIRE-Final Inspection | 5/31/2012 | 6/1/2012 | 6/1/2012 | P | FAIL |
Forrest France
|
|
|
C/N items include; post building address, provide current certification for the PFE at the east side, provide thermal barrier at the exposed paper faced insulation in the warehouse area, remove hasp at the SW exit door, reverse door swing at E4 or provide documentation for alternate approval.
|
BLD-Framing/Rough-in | 5/17/2012 | 5/18/2012 | 5/18/2012 | A | PASS |
Dave Hannah
|
|
|
Please call Steve Ove when heading to site ###-#### Phone #: ###-#### >> Inspection requested via web by Brian Warbis
|
OVERRIDE | | | 5/16/2012 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 5/16/2012 | | DONE |
Alexandra L. DeYoung
|
|
|
|
Print Occupancy Form | | | 5/16/2012 | | DONE |
Alexandra L. DeYoung
|
|
|
|
Permit Ready to Issue | | | 5/16/2012 | | |
|
|
|
|
Plan assigned to (CJW) | 4/11/2012 | 4/11/2012 | 5/3/2012 | | PASS |
Carl Westfall
|
|
|
TREY MCINTYRE PROJECT (20 days - May 7) ePlanReview case
|
Routing - PLAN CHECK | 5/1/2012 | | 5/3/2012 | | PASS |
Carl Westfall
|
|
|
Drawings approved after resubmittal review.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/3/2012 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 4/11/2012 | | 4/30/2012 | | FAIL |
Carl Westfall
|
|
|
|
1st review completed | | | 4/30/2012 | | FAIL |
Carl Westfall
|
|
|
|
Routing - FIRE | 4/11/2012 | | 4/13/2012 | | PASS |
Scott Arellano
|
|
|
No plan review report attached. Plans are approved as shown.
|
Routing - Erosion and Sediment | 4/11/2012 | | 4/12/2012 | | PASS |
Clint A Smith
|
|
|
ESC12-00348 plan waiver approved with conditions attached to the permit.
|
Routing - PUBLIC WORKS | 4/11/2012 | | 4/12/2012 | | PASS |
Beverly Mountain
|
|
|
|
Routing - Addressing | 4/11/2012 | | 4/12/2012 | | PASS |
Terry Records
|
|
|
|
Routing PW Sewer Rating | 4/12/2012 | | 4/12/2012 | | PASS |
Connie Baumgartner
|
|
|
|
Pending Assignment by JCB | 4/11/2012 | | 4/11/2012 | | DONE |
Jason Blais
|
|
|
|
Routing - Design Review | 4/11/2012 | | 4/11/2012 | | PASS |
Sarah Schafer
|
|
|
Sarah Schafer - ESC Waiver letter indicates exterior concrete pedestrian ramp?
Exterior ramp and parking restriping is approved through the building permit.
|
Plan Reviewer's activity | | | 4/11/2012 | | DONE |
Jason Blais
|
|
|
Sent architect an email to contact ACHD for evaluation of any impact fees due or any required inspection. Written verification from ACHD needs to be provided to our Permit Counter prior to the building permit being issued.
|
Payment Received | | | 4/10/2012 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 4/5/2012 | | DONE |
|
|
|
Application submitted via PDS Online on Apr 5 2012 4:47PM
|