BLD-Final | 8/16/2013 | 8/16/2013 | 8/16/2013 | P | PASS |
Tony Young
|
|
|
|
DOC - Permit Finaled | 8/16/2013 | 8/16/2013 | 8/16/2013 | P | PASS |
Tony Young
|
|
|
c of c/o issued
|
BLD-Final | 6/27/2013 | 6/28/2013 | 6/28/2013 | P | DONE |
Tony Young
|
|
|
trent Phone #: ###-####
|
Zoning Approval | 6/28/2013 | 6/28/2013 | 6/28/2013 | | DONE |
Sarah Schafer
|
|
|
|
BLD-Energy code compliance | 12/4/2012 | 12/5/2012 | 12/5/2012 | A | PASS |
Tony Young
|
|
|
Trent Phone #: ###-####,, house ok
|
BLD-Framing/Rough-in | 12/3/2012 | 12/3/2012 | 12/3/2012 | P | PASS |
Jim Sly
|
|
|
Trent Phone #: ###-####
|
Attached Document | | | 11/21/2012 | | |
|
|
|
|
Routing Walk-In (BLD) | 9/7/2012 | 9/7/2012 | 9/7/2012 | A | DONE |
Sarah Schafer
|
|
|
|
Routing Walk-In (Zoning) | 9/7/2012 | 9/7/2012 | 9/7/2012 | P | PASS |
Sarah Schafer
|
|
|
Approved per DRH12-00215.
|
Inspection Record Card- Bld | | | 9/7/2012 | | DONE |
Barbara Stitt
|
|
|
|
(F) Reprint permit | | | 9/7/2012 | | DONE |
Barbara Stitt
|
|
|
|
Case Summary (BLD) | | | 9/7/2012 | | |
|
|
|
|
BLD-Foundation | 7/27/2012 | 7/30/2012 | 7/30/2012 | A | PART |
Tony Young
|
|
|
Trent- after 9 Phone #: ###-####,, garage foundation monolithic ok,,, work in progress,, ok to pour when ready
|
BLD-Conference | 7/11/2012 | 7/11/2012 | 7/11/2012 | A | PASS |
Tony Young
|
|
|
Work has been authorized and may continue on garage after conference with legal and director. Original North and West walls toppled by wind may be reinstalled on sill plates. No other work authorized under current Stop Work Order.
|
Stop Work Order | 6/26/2012 | 6/26/2012 | 6/26/2012 | | DONE |
Tony Young
|
|
|
Stop Work Order issued for exceeding scope of work.
|
Routing Walk-In (BLD) | 6/26/2012 | 6/26/2012 | 6/26/2012 | P | PASS |
Perry Paine
|
|
|
|
BLD-Foundation | 5/30/2012 | 5/30/2012 | 5/30/2012 | P | PART |
Tony Young
|
|
|
request late PM//Trent Phone #: ###-#### basement foam block walls work in progress
|
BLD-Footing | 5/15/2012 | 5/15/2012 | 5/15/2012 | P | PART |
Tony Young
|
|
|
Trent Phone #: ###-#### //concrete at 1pm, house footings,, basement
|
Routing Walk-In (Zoning) | 4/23/2012 | 4/23/2012 | 4/23/2012 | A | PASS |
Perry Paine
|
|
|
|
Routing Walk-In (BLD) | 4/23/2012 | 4/23/2012 | 4/23/2012 | A | DONE |
Perry Paine
|
|
|
|
Case Summary (BLD) | | | 4/23/2012 | | |
|
|
|
|
Inspection Record Card- Bld | | | 4/23/2012 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/23/2012 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 4/23/2012 | | DONE |
Tisha Gallop
|
|
|
|
OVERRIDE | | | 4/17/2012 | | |
|
|
|
|
Plan assigned to (PEP) | 4/17/2012 | 4/17/2012 | 4/17/2012 | | PASS |
Perry Paine
|
|
|
|
Routing Walk-In (BLD) | 4/17/2012 | 4/17/2012 | 4/17/2012 | A | PASS |
Perry Paine
|
|
|
2nd Phase submittal questions
|
Routing Walk-In (BLD) | 4/16/2012 | 4/16/2012 | 4/17/2012 | P | DONE |
Perry Paine
|
|
|
|
Case Summary (BLD) | | | 4/17/2012 | | |
|
|
|
|
Inspection Record Card- Bld | | | 4/17/2012 | | |
|
|
|
|
1st review completed | | | 4/17/2012 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/17/2012 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 4/17/2012 | | DONE |
Tisha Gallop
|
|
|
|
Telephone call | | | 4/17/2012 | | DONE |
Tisha Gallop
|
|
|
called Anne and told her permit is ready and fees.
|
Issue PAID IN FULL permit | | | 4/17/2012 | | DONE |
Christina Prado
|
|
|
|
Routing Walk-In (Zoning) | 4/16/2012 | 4/16/2012 | 4/16/2012 | P | PASS |
Matthew A Halitsky
|
|
|
|
Application received | | 4/16/2012 | | | |
|
|
|
|
Routing - MECHANICAL | 4/19/2012 | | | | |
|
|
|
To Troy for 2nd phase of project. BLD12-00840
|