BLD-Conference | 1/28/2013 | 1/29/2013 | 1/29/2013 | P | DONE |
Mike Jordan
|
|
|
ED Phone #: ###-####
|
FIRE-Conference | 1/28/2013 | 1/29/2013 | 1/29/2013 | A | DONE |
Troy Cobbley
|
|
|
Went over sprinkler and fire extinguisher requirements with ED.
|
Issue PAID IN FULL permit | | | 1/11/2013 | | DONE |
|
|
|
|
Extend Review Timeline | | | 10/16/2012 | | DONE |
Christina Prado
|
|
|
|
Expiration Notice | 9/26/2012 | 10/17/2012 | 9/26/2012 | | DONE |
Christina Prado
|
|
|
|
Expiration Notice | 9/24/2012 | 10/15/2012 | 9/24/2012 | | DONE |
Christina Prado
|
|
|
Returned in mail, sent 2nd notice 9-26
|
Plan assigned to (CJW) | 4/18/2012 | 4/18/2012 | 8/8/2012 | | PASS |
Carl Westfall
|
|
|
BOISE INDOOR SOCCER (20 days - May 14)
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/8/2012 | | DONE |
|
|
|
|
Print Occupancy Form | | | 8/8/2012 | | DONE |
Christina Prado
|
|
|
|
Telephone call | | | 8/8/2012 | | DONE |
|
|
|
LM for Larry permit ready
|
Permit Ready to Issue | | | 8/8/2012 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 5/14/2012 | | 8/7/2012 | | PASS |
Carl Westfall
|
|
|
Drawings approved after the resubmittal review.
|
Plan resubmittals received | | | 8/6/2012 | | |
|
|
|
8-6-12 received 1 letter to Jason & 2 copies of sheets A1.0A2.0 & A3.0 taken to Carl W.
|
Plan Reviewer's activity | | | 5/23/2012 | | |
|
|
|
A resubmittal was received on May 22, 2012. The resubmittal was not reviewed because approval of the project depended on whether the Building Official would accept the substandard stairway that was constructed without a permit. If he rejected the stairway, then further revised drawings would be required and the time spent on the resubmittal review would be wasted. After the Building Official made a site visit, it was determined that the stairway needed to be demolished and a new stairway constructed. Revised drawings were then submitted on August 6, 2012.
|
Plan resubmittals received | | | 5/22/2012 | | DONE |
Christina Prado
|
|
|
Received one response letter addressed to Carl W and two plans sheets marked A2.0. Routed plans and letter to Carl Westfall for further review
|
Route to Impact Fee Review | 5/10/2012 | 5/15/2012 | 5/17/2012 | | PASS |
Cindy M. Gould
|
|
|
Additional room in an existing building no impact fees
|
Routing - FIRE | 5/10/2012 | 5/10/2012 | 5/14/2012 | | PASS |
Scott Arellano
|
|
|
If the occupant load exceeds 299, a manual fire alarm system with audible and visual notification in all public and common use spaces, will be required. See fire code review comments for additional details.
|
1st review completed | | | 5/14/2012 | | FAIL |
|
|
|
Failed Plan Check
|
Routing - PLAN CHECK | 4/18/2012 | | 5/10/2012 | | FAIL |
Carl Westfall
|
|
|
The IBC plan review was started on May 9 and was finished the next day. Revised drawings were required. See the plan review report.
|
Pending Assignment by JCB | 4/17/2012 | | 4/18/2012 | | DONE |
Jason Blais
|
|
|
|
Intake Approval | | | 4/17/2012 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 4/17/2012 | | DONE |
Christina Prado
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 4/17/2012 | | DONE |
Christina Prado
|
|
|
|
Application received | | 4/17/2012 | | | |
|
|
|
|