Information based on query as of Friday, August 16, 2024.
Permit Information
Permit NumberBLD12-00865
StatusFinaled
Name PENNON CONSTRUCTION COMPANY INC
Site Address 8600 W FRANKLIN RD
Project NameMATTRESS FIRM
Customer Number 
ePlanReviewNo
Description
(MATTRESS FIRM) - To demolish and remove an existing approximate 3,000 square foot, one story masonry building and to construct a new 3,705 square foot, one story retail building and related site improvements. The building will be constructed of masonry exterior walls, steel roof joists with metal roof deck and metal stud interior partitions. This building will not be fire sprinkled, based on an approved alternate letter, signed June 5, 2012. Plan Modification was submitted on 10/3/2012 to rotate the two accessible restrooms 90 degrees and swing the doors out. All construction per the approved plans and attached comment list. JCM (DRH12-00107)
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Second Notice 10/28/201211/14/2012 DONE
First Notice 10/15/201210/18/2012 DONE
mailed
BLD-Final10/4/201210/5/201210/5/2012APASS
DetailsJim Sly
Rick Phone #: ###-####
OK for Perm Occ.
FIRE-Final Inspection10/4/201210/5/201210/5/2012APASS
DetailsTroy Cobbley
Life safety passed. Revise floor plan is on site.
Permanent Occupancy  10/5/2012 DONE
Plan assigned to (JCM)10/3/201210/3/201210/4/2012 PASS
DetailsJohn Menard
Routing - PLAN CHECK10/3/2012 10/4/2012 PASS
DetailsJohn Menard
Plan Reviewer's activity  10/4/2012 PASS
DetailsJohn Menard
Reviewed and approved plan modification to rotate the restrooms 90 degrees and swing the restroom doors out. Only a floor plan was submitted, the other plans sheets were not revised. JCM
PLANS/APPL TAKEN TO FRONT DESK  10/4/2012 DONE
DetailsJohn Menard
Print Occupancy Form  10/4/2012 DONE
DetailsTisha Gallop
Override - Parcel Holds  10/4/2012  
Permit Ready to Issue  10/4/2012 DONE
CHANGE STATUS TO (ISS)  10/4/2012 DONE
DetailsBarbara Stitt
(F) Reprint permit  10/4/2012 DONE
DetailsBarbara Stitt
FIRE-Final Inspection10/2/201210/3/201210/3/2012PFAIL
DetailsTroy Cobbley
Duct smoke detectors have been installed and tested ok. Still need the approved revised floor plan for a life safety final.
Zoning Approval10/3/201210/3/201210/3/2012 DONE
DetailsAndrea Tuning
Override - Parcel Holds  10/3/2012  
Plan Modification Accepted  10/3/2012 DONE
Rec'd plan mod to rotate toilet rooms 90 degrees - two copies of sheet a2.11
BLD-Final10/2/201210/2/201210/2/2012PNR
DetailsTom Arcoraci
Rick Phone #: ###-####
FIRE-Final Inspection10/2/201210/2/201210/2/2012PFAIL
DetailsTroy Cobbley
Resubmit plans showing the actual wall layout. Provide hvac duct detector shutdown as per IMC 606.2.2
PubWorks Occupancy Approval10/2/201210/2/201210/2/2012 DONE
DetailsTiffany Lowery
Zoning Approval Temp10/2/201210/2/201210/2/2012 DONE
DetailsAndrea Tuning
The ADA space is not striped properly. The site should be restriped Wednesday October 3, 2012.
BLD-Wall cover9/27/20129/28/20129/28/2012APASS
DetailsMike Jordan
Early as possible - Rick Phone #: ###-####. Ceiling grid ok.
BLD-Conference9/21/20129/24/20129/24/2012PDONE
DetailsMike Jordan
Rick-Around noon if possible please Phone #: ###-####. Spoke to contractor about what he needs for c.o
BLD-Energy code compliance9/6/20129/7/20129/7/2012PPASS
DetailsMike Jordan
RIck Phone #: ###-####
BLD-Framing/Rough-in9/5/20129/5/20129/5/2012PPART
DetailsMike Jordan
rick Phone #: ###-####. Interior steel stud walls, soffits and hardlids, pending mechanical rough in inspection.
BLD-Other8/31/20128/31/20128/31/2012PPASS
DetailsTom Arcoraci
roof insp//Rick (please call if anything is wrong because he is in Washington) Phone #: ###-####
BLD-Concrete7/25/20127/26/20127/26/2012PPART
DetailsMike Jordan
Rebar- - Rick Phone #: ###-####. Welded wore mesh for interior slab on grade. Work in progress on installing chairs.
BLD-Other7/23/20127/23/20127/23/2012PPASS
DetailsMike Jordan
masonary insp//Dennis Phone #: ###-####. 0 to 4ft. elevation for masonry wall, north, south and west walls. Also verified firestop system on west wall at control joints.
BLD-Foundation7/16/20127/16/20127/16/2012PCANC
DetailsMike Jordan
Rick Phone #: ###-####
BLD-Energy code compliance7/16/20127/16/20127/16/2012PPASS
DetailsMike Jordan
Rick Phone #: ###-####. Rigid foam insulation on interior side of foundation.
BLD-Foundation7/13/20127/16/20127/16/2012APART
DetailsMike Jordan
rick early if possible Phone #: ###-####. stemwall for dumpster enclosure.
BLD-Concrete7/11/20127/12/20127/12/2012PPART
DetailsMike Jordan
SPouring at 4 for stem wall for foundations/footings-- Rick Phone #: ###-####
BLD-Foundation7/10/20127/11/20127/11/2012APART
DetailsMike Jordan
Around noon if possible - - Rick Phone #: ###-####. Perimeter footings, work in progress. Will have special inspections.
BLD-Conference7/6/20127/9/20127/9/2012ADONE
DetailsMike Jordan
Phone #: 3606243765 >> Inspection requested via mobile web by Rick Magistrale
Issue PAID IN FULL permit  6/29/2012 DONE
DetailsTisha Gallop
Routing Off Site - STRUCTURAL6/15/2012 6/26/2012 PASS
DetailsJohn Menard
Routing - PLAN CHECK6/19/2012 6/26/2012  
DetailsJohn Menard
Routing - Design Review6/26/2012 6/26/2012 PASS
DetailsAndrea Tuning
Routing - PLAN CHECK6/26/2012 6/26/2012 PASS
DetailsJohn Menard
PLANS/APPL TAKEN TO FRONT DESK  6/26/2012 DONE
DetailsJohn Menard
Print Occupancy Form  6/26/2012 DONE
Telephone call  6/26/2012 DONE
DetailsChristina Prado
Called and left message for architect giving fees due and advising RP, ACHD letter and GC form are required prior to issuance
Permit Ready to Issue  6/26/2012 DONE
DetailsChristina Prado
Plan assigned to (JCM)4/18/2012 6/26/2012 PASS
DetailsJohn Menard
Routing - FIRE6/15/2012 6/19/2012 PASS
DetailsScott Arellano
Plan resubmittals received  6/15/2012 DONE
DetailsTisha Gallop
received one copy of structural calcs, response from engineering and plan sheets S2.1, S3.1; taken to John Menard.
Intake Approval  6/15/2012 PASS
DetailsChristina Prado
called action couriers for pick up
Routing - Design Review6/15/2012 6/15/2012 FAIL
DetailsAndrea Tuning
As a part of the Design Review approval, the applicant was required to provide one accessible space. This will require the applicant to provide 16-feet for the space and the access aisle. This has not not been provided at this time. ANT
Routing - PLAN CHECK5/22/2012 6/15/2012 PASS
DetailsJohn Menard
Plan resubmittals received  6/11/2012 DONE
rec'd two copies of response letter, calcs, and sheets a0.01; a1.11; a2.11; a2.31; a2.41; a3.11; a5.11; a6.11; s2.1; s3.1 - inserted by arch rep and taken back to John M
Route to Impact Fee Review5/18/20125/23/20125/24/2012 PASS
DetailsCindy M. Gould
Routing - FIRE5/18/20125/18/20125/22/2012 PASS
DetailsScott Arellano
Attached IFC comments to plans
1st review completed  5/22/2012 FAIL
Failed Structural, Planning, Plan Check
Plan resubmittals requested  5/18/2012 DONE
DetailsJohn Menard
E-mailed the architect a copy of the third structural review requesting additional revisions. JCM
Plan resubmittals requested  5/18/2012 DONE
DetailsJohn Menard
E-mailed the architect a copy of the plan review requesting revisions. JCM
Routing Off Site - STRUCTURAL5/16/2012 5/18/2012 FAIL
DetailsJohn Menard
Received comment list for third structural review from consulting structural engineer. JCM
Routing - PLAN CHECK4/25/2012 5/18/2012 FAIL
DetailsJohn Menard
Telephone call  5/15/2012 DONE
DetailsChristina Prado
called Action Couriers for pick up
Plan resubmittals received  5/15/2012 DONE
DetailsTisha Gallop
received one response letter, two copies of structural calcs, three copies of S2.1, S3.1; inserted by arch. rep. and taken back to John Menard
Plan resubmittals requested  5/7/2012 DONE
DetailsJohn Menard
E-mailed the architect a copy of the 2nd structural review requesting additional revisions. JCM
Routing Off Site - STRUCTURAL5/1/2012 5/4/2012 FAIL
DetailsJohn Menard
Received comment list from consultin engineer requesting revisions. JCM
Plan resubmittals received  5/1/2012 DONE
DetailsChristina Prado
Received one response letter: five sets of plans marked C3.00; three sets of plans marked S1.1, S2.1 & S3.1 as well as three sets of Structural calcs. Plans inserted by Arch. rep and taken to John Menard for further review
Telephone call  5/1/2012 DONE
DetailsChristina Prado
Called Action courers for pick up
Routing - PLANNING4/24/2012 4/25/2012 FAIL
DetailsAndrea Tuning
This site has not been successfully rezoned or received Design Review Approval. The rezone is anticipated to be completed on 5-15-12 and the Design Review approval is anticipated to be completed on 5-16-12. The applicant will be required to modify the plans to reflect the Conditions of Approval of the Rezone and DR and will be eligible to submit building permits on May 26, 2012 once the appeal period has expired.
Routing - PLUMBING4/23/2012 4/24/2012 PASS
DetailsDaryl Spivey
Routing - PUBLIC WORKS4/19/2012 4/23/2012 PASS
DetailsConnie Baumgartner
Routing - Erosion and Sediment4/23/2012 4/23/2012 PASS
DetailsClint A Smith
ESC12-00362 plan approved with conditions attached to the permit.
Routing PW Solid Waste  4/23/2012 PASS
DetailsPeter J. McCullough
Lot does not connect to any adjacent lot, existing parking and building location.
Routing PW Drainage4/20/2012 4/23/2012 PASS
DetailsBrian Murphy
Routing Off Site - STRUCTURAL4/19/2012 4/23/2012 FAIL
DetailsJohn Menard
Received comment list from consulting structural engineer requesting revisions. JCM
Plan resubmittals requested  4/23/2012 DONE
DetailsJohn Menard
E-mailed the architect a copy of the structural review requesting revisions. JCM
Routing PW Sewer Rating4/20/2012 4/20/2012 PASS
DetailsConnie Baumgartner
Pending Assignment by JCM4/18/2012 4/18/2012 DONE
DetailsJohn Menard
Routing - PLANNING Land Div4/18/2012 4/18/2012 PASS
DetailsTodd Tucker
Plans ACCEPTED BY PLAN TECH  4/18/2012 DONE
DetailsChristina Prado
Recd Pcfee & Taken To Pln CK  4/18/2012 DONE
DetailsChristina Prado
Pending Assignment by JCM4/18/2012 4/18/2012 DONE
DetailsJohn Menard
Application received 4/18/2012