Letter of compliance/Occupancy | | | 11/16/2018 | | DONE |
|
|
|
|
BLD-Final | 2/27/2013 | 2/27/2013 | 2/28/2013 | P | PASS |
Tony Young
|
|
|
Josh Phone #: ###-####
|
DOC - Permit Finaled | 2/28/2013 | 2/28/2013 | 2/28/2013 | P | PASS |
Tony Young
|
|
|
|
BLD-Final | 2/25/2013 | 2/26/2013 | 2/27/2013 | P | PART |
Tony Young
|
|
|
josh Phone #: ###-####,, walk through,, need landing or steps out rear doors,, handrails, address, etc
|
BLD-Conference | 2/21/2013 | 2/22/2013 | 2/22/2013 | A | PASS |
Tom Arcoraci
|
|
|
josh Phone #: ###-####
|
Routing - PLANNING | 2/19/2013 | | 2/19/2013 | | PASS |
Scott Spjute
|
|
|
|
BLD-Energy code compliance | 11/28/2012 | 11/28/2012 | 11/28/2012 | P | PASS |
Tony Young
|
|
|
josh Phone #: ###-####
|
BLD-Framing/Rough-in | 11/26/2012 | 11/26/2012 | 11/26/2012 | P | PART |
Tony Young
|
|
|
Josh Phone #: ###-####,, need fireblocking,, ok to insulate
|
Routing - MECHANICAL | 11/14/2012 | | 11/14/2012 | | PASS |
Troy James
|
|
|
|
BLD-Framing/Rough-in | 11/13/2012 | 11/13/2012 | 11/13/2012 | P | PASS |
Tony Young
|
|
|
Shear inspection please-Josh Phone #: ###-####
|
Routing Walk-In (BLD) | 10/16/2012 | 10/16/2012 | 10/16/2012 | A | PASS |
Perry Paine
|
|
|
spoke withbuilder about short wall extending from the floor line to above the foundation line...ok to be 2x4 and R-15 insulated.
|
Telephone call | | | 10/16/2012 | | DONE |
|
|
|
spoke withbuilder about short wall extending from the floor line to above the foundation line...ok to be 2x4 and R-15 insulated.
|
BLD-Foundation | 7/6/2012 | 7/9/2012 | 7/9/2012 | P | PASS |
Tom Arcoraci
|
|
|
Josh Phone #: ###-####
|
BLD-Footing | 6/27/2012 | 6/28/2012 | 6/28/2012 | A | PASS |
Tony Young
|
|
|
Josh Phone #: ###-####
|
BLD-Footing | 6/26/2012 | 6/27/2012 | 6/27/2012 | P | PART |
Tony Young
|
|
|
Josh Phone #: ###-####,, work in progress
|
PubWorks Subgrade Approval | 6/20/2012 | 6/20/2012 | 6/20/2012 | | DONE |
Terry Records
|
|
|
|
Routing Walk-In (Zoning) | 5/29/2012 | 5/29/2012 | 5/29/2012 | A | PASS |
Todd Tucker
|
|
|
|
Routing Walk-In (BLD) | 5/29/2012 | 5/29/2012 | 5/29/2012 | A | DONE |
Perry Paine
|
|
|
|
Plan assigned to (PEP) | 5/29/2012 | 5/29/2012 | 5/29/2012 | | PASS |
Perry Paine
|
|
|
|
Case Summary (BLD) | | | 5/29/2012 | | |
|
|
|
|
Inspection Record Card- Bld | | | 5/29/2012 | | |
|
|
|
|
1st review completed | | | 5/29/2012 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/29/2012 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 5/29/2012 | | DONE |
Christina Prado
|
|
|
|
Issue PAID IN FULL permit | | | 5/29/2012 | | DONE |
Christina Prado
|
|
|
|
Routing PW Grading-Hillside | 4/19/2012 | | 4/19/2012 | | PASS |
Colleen T Carroll
|
|
|
Footing subgrade must be approved by the applicants geotechnical engineer prior to scheduling footing inspection.
|
Application received | | 4/19/2012 | | | |
|
|
|
|