Third Notice | | 10/30/2012 | 10/18/2012 | | DONE |
|
|
|
This permit finaled on the web by Richard Schultz
|
Third Notice | | 9/30/2012 | 10/16/2012 | | DONE |
|
|
|
faxed
|
Second Notice | | 8/11/2012 | 9/25/2012 | | DONE |
|
|
|
faxed
|
First Notice | 7/19/2012 | 7/19/2012 | 8/1/2012 | | DONE |
Jim Storey
|
|
|
|
BLD-Final | 7/18/2012 | 7/19/2012 | 7/19/2012 | P | PASS |
Jim Storey
|
|
|
Thanks Matt. Phone #: ###-#### >> Inspection requested via web by Richard Schultz
|
DOC - Permit Finaled | 7/19/2012 | 7/19/2012 | 7/19/2012 | P | PASS |
Jim Storey
|
|
|
|
FIRE-Final Inspection | 7/18/2012 | 7/19/2012 | 7/19/2012 | A | PASS |
Forrest France
|
|
|
Vanilla permit fire life safety inspection completed and passed.
|
BLD-Conference | 7/17/2012 | 7/18/2012 | 7/18/2012 | A | PASS |
Jim Storey
|
|
|
Call Matt Thanks. Phone #: ###-#### >> Inspection requested via web by Richard Schultz
|
BLD-Other | 7/10/2012 | 7/10/2012 | 7/10/2012 | P | PASS |
Dave Hannah
|
|
|
Ceiling Grid insp. Thanks Matt. Phone #: ###-#### >> Inspection requested via web by Richard Schultz
|
BLD-Conference | 6/27/2012 | 6/27/2012 | 6/27/2012 | P | PASS |
Jim Storey
|
|
|
Call Matt for conference Thanks. Phone #: ###-#### >> Inspection requested via web by Richard Schultz ramp slope ok
|
BLD-Framing/Rough-in | 5/30/2012 | 5/30/2012 | 5/30/2012 | P | PART |
Jim Storey
|
|
|
matt Phone #: ###-#### left message for arch to call back// 22 ga studs installed spec. 20 ga no responce back.
|
FIRE-Sprinkler Rough-in | 5/25/2012 | 5/25/2012 | 5/25/2012 | P | PART |
Forrest France
|
|
|
Fire sprinkler modifications at the NW corner office area okayed for ceiling cover.
|
Plan assigned to (TLW) | 5/10/2012 | | 5/23/2012 | | PASS |
Tim L. Woodard
|
|
|
|
Routing - PLAN CHECK | 5/10/2012 | | 5/23/2012 | | PASS |
Tim L. Woodard
|
|
|
|
1st review completed | | | 5/23/2012 | | DONE |
Tim L. Woodard
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/23/2012 | | DONE |
Tim L. Woodard
|
|
|
|
Telephone call | | | 5/23/2012 | | DONE |
Tisha Gallop
|
|
|
sent e-mail to Matt Rhees plan review is complete, to have GC contact permit desk.
|
Permit Ready to Issue | | | 5/23/2012 | | DONE |
Christina Prado
|
|
|
|
Issue PAID IN FULL permit | | | 5/23/2012 | | DONE |
Christina Prado
|
|
|
|
Inspection Record Card- Bld | | | 5/23/2012 | | DONE |
Christina Prado
|
|
|
|
Routing - Addressing | 5/9/2012 | | 5/9/2012 | | PASS |
Terry Records
|
|
|
|
Routing - FIRE | 5/8/2012 | | 5/9/2012 | | PASS |
Scott Arellano
|
|
|
Attached IFC comments to plans
|
Payment Received | | | 5/8/2012 | | DONE |
|
|
|
Payment received via Govolutions
|
Routing - PUBLIC WORKS | 5/8/2012 | | 5/8/2012 | | PASS |
Beverly Mountain
|
|
|
|
Routing PW Sewer Rating | 5/8/2012 | | 5/8/2012 | | PASS |
Connie Baumgartner
|
|
|
|
Intake Approval | | | 5/8/2012 | | PASS |
Tim L. Woodard
|
|
|
|
Intake Approval | | | 4/25/2012 | | FAIL |
Jason Blais
|
|
|
This site is located in an M-1D zone. Please upload approval documentation from Planning & Zoning Design Review section for exterior changes.Provide engineered mechanical plans since a new system is being installed within this space. Contact Chief Plumbing/Mechanical Inspector for any exceptions.Provide HVAC load calculations verifying compliance with the Energy Code.
|
Application received | | | 4/24/2012 | | DONE |
|
|
|
Application submitted via PDS Online on Apr 24 2012 10:14AM
|