Plan Reviewer's activity | | | 10/17/2012 | | DONE |
Jason Blais
|
|
|
Notice of Compliance for completing the Upgrade Agreement work attached to this case and BLD09-01840 where the original Upgade Agreement was generated and attached.
|
First Notice | 10/10/2012 | 10/10/2012 | 10/15/2012 | | DONE |
Jim Sly
|
|
|
|
FIRE-Final Inspection | 10/10/2012 | 10/10/2012 | 10/10/2012 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
BLD-Final | 10/10/2012 | 10/10/2012 | 10/10/2012 | P | PASS |
Jim Sly
|
|
|
call before to meet//late as poss//Ken Phone #: ###-#### Certificate of Compliance issued.
|
DOC - Permit Finaled | 10/10/2012 | 10/10/2012 | 10/10/2012 | P | PASS |
Jim Sly
|
|
|
|
FIRE-Conference | 7/13/2012 | 7/16/2012 | 7/16/2012 | A | DONE |
Troy Cobbley
|
|
|
Tenant space 206 and the main lobby up to the stairs is complete. Per the insulation contractor space 204 was done previously by an unknown contractor.
|
BLD-Framing/Rough-in | 7/13/2012 | 7/16/2012 | 7/16/2012 | A | PART |
Jim Sly
|
|
|
Main lobby OK up to stairway...Room 208 OK Rooms 206 and 204 previously completed.
|
FIRE-Final Inspection | 7/13/2012 | 7/13/2012 | 7/13/2012 | P | CANC |
Troy Cobbley
|
|
|
Per Tom the contractor is unable to be on site. Please reschedule for monday.
|
BLD-Framing/Rough-in | 7/13/2012 | 7/13/2012 | 7/13/2012 | P | DEFR |
Tom Arcoraci
|
|
|
ken Phone #: ###-####
|
FIRE-Sprinkler Rough-in | 7/5/2012 | 7/5/2012 | 7/5/2012 | P | PASS |
Troy Cobbley
|
|
|
The insulation backing in Suite 101 (book store) is complete
|
BLD-Other | 7/5/2012 | 7/5/2012 | 7/5/2012 | P | PART |
Jim Sly
|
|
|
ken Phone #: ###-#### Bookstore completed.
|
FIRE-Final Inspection | 6/5/2012 | 6/5/2012 | 6/5/2012 | P | CANC |
Troy Cobbley
|
|
|
unit 208 - -Ken Phone #: ###-#### - Inspection canceled per phone conversation with Jim Sly. Project is not ready for inspection. Inspection will be scheduled for next monday.
|
BLD-Final | 6/5/2012 | 6/5/2012 | 6/5/2012 | P | CANC |
Jim Sly
|
|
|
Unit 208 - - Ken Phone #: ###-####
|
FIRE-Final Inspection | 6/4/2012 | 6/4/2012 | 6/4/2012 | P | FAIL |
Troy Cobbley
|
|
|
Inspection was actually for a conference. I met Jim Sly at the project site as well as the insulator contractor and discussed what jim and I would be looking for on our inspections. This included sprinkler obstructions. Work is being started in the Windmill book store.
|
BLD-Final | 6/4/2012 | 6/4/2012 | 6/4/2012 | P | PEND |
Jim Sly
|
|
|
brandon Phone #: ###-#### Had meeting with Workers to explain what we are looking for at final insp.
|
BLD-Conference | 5/23/2012 | 5/30/2012 | 5/30/2012 | A | DONE |
Jim Sly
|
|
|
ken Phone #: ###-#### Met with G&G Matter Architects to discuss plan to protect all Kraft faced insulation.
|
Inspection Record Card- Bld | | | 5/15/2012 | | DONE |
Alexandra L. DeYoung
|
|
|
|
Permit Ready to Issue | | | 5/15/2012 | | DONE |
Tisha Gallop
|
|
|
no new cert of value required since owner is GC and initial values were given to architect from owner.
|
Issue PAID IN FULL permit | | | 5/15/2012 | | DONE |
Alexandra L. DeYoung
|
|
|
|
1st review completed | | | 5/9/2012 | | DONE |
Tim L. Woodard
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/9/2012 | | DONE |
Tim L. Woodard
|
|
|
|
Plan assigned to (TLW) | 5/7/2012 | | 5/9/2012 | | PASS |
Tim L. Woodard
|
|
|
|
Routing - PLAN CHECK | 5/7/2012 | | 5/9/2012 | | PASS |
Tim L. Woodard
|
|
|
|
Routing - FIRE | 5/7/2012 | | 5/8/2012 | | PASS |
Scott Arellano
|
|
|
No comments attached to plans. Any modifications to the existing fire sprinkler system will require a separate permit.
|
1st review completed | | | 5/7/2012 | | DONE |
Tim L. Woodard
|
|
|
|
Telephone call | | | 5/3/2012 | | DONE |
Christina Prado
|
|
|
Emailed Architect; advised initial fees are due
|
Application received | | | 5/1/2012 | | DONE |
|
|
|
Application submitted via PDS Online on May 1 2012 9:15AM
|