Case Summary (BLD) | | | 5/10/2016 | | DONE |
|
|
|
|
Letter of compliance/Occupancy | | | 4/29/2016 | | DONE |
|
|
|
|
BLD-Final | 10/11/2012 | 10/12/2012 | 10/12/2012 | P | PASS |
Dave Hannah
|
|
|
mike Phone #: ###-####
|
DOC - Permit Finaled | 10/12/2012 | 10/12/2012 | 10/12/2012 | P | PASS |
Dave Hannah
|
|
|
|
Routing PW Grading-Hillside | 10/12/2012 | | 10/12/2012 | | PASS |
Jim Wyllie
|
|
|
Bonding received for installation of landscaping. Building occupancy okay. Jim Wyllie (###-####)
|
BLD-Conference | 10/5/2012 | 10/5/2012 | 10/5/2012 | P | DONE |
Dave Hannah
|
|
|
mike - call 30 mins prior to meet Phone #: ###-####
|
BLD-Other | 8/2/2012 | 8/2/2012 | 8/2/2012 | P | PASS |
Tom Arcoraci
|
|
|
Fire Protected Soffit inspection Phone #: ###-#### >> Inspection requested via web by Josh Edwards
|
BLD-Other | 8/1/2012 | 8/1/2012 | 8/1/2012 | P | FAIL |
Dave Hannah
|
|
|
Fire Stop Soffit Inspection Phone #: ###-#### >> Inspection requested via web by Josh Edwards soffits ok but boxing of lights failed crew is scabing in sheetrock around can lighs joints not lapped lids not atteched they dident box out speackers or lights on patio.
|
BLD-Energy code compliance | 7/30/2012 | 7/30/2012 | 7/30/2012 | P | PASS |
Dave Hannah
|
|
|
|
BLD-Wall cover | 7/30/2012 | 7/30/2012 | 7/30/2012 | P | PASS |
Dave Hannah
|
|
|
Looking for insulation and framing correction inspection so i can begin drywall. thank you Phone #: ###-#### >> Inspection requested via web by Josh Edwards
|
BLD-Framing/Rough-in | 7/24/2012 | 7/25/2012 | 7/25/2012 | A | PART |
Dave Hannah
|
|
|
Josh Phone #: ###-#### >> Inspection requested via web by Josh Edwards c/n on site ok to insulate after mec r/i is approved
|
Routing - MECHANICAL | 7/25/2012 | | 7/25/2012 | | PASS |
Troy James
|
|
|
resubmitted new acca report due to the duct changes
|
Plan resubmittals received | | | 7/12/2012 | | DONE |
|
|
|
new acca report
|
Routing - MECHANICAL | 7/12/2012 | | 7/12/2012 | | PASS |
Troy James
|
|
|
resubmitted acca report
|
BLD-Wall Bracing | 7/3/2012 | 7/3/2012 | 7/3/2012 | P | DONE |
Dave Hannah
|
|
|
josh Phone #: ###-####
|
BLD-Wall Bracing | 7/2/2012 | 7/3/2012 | 7/3/2012 | A | PASS |
Dave Hannah
|
|
|
josh Phone #: ###-####
|
BLD-Foundation | 5/31/2012 | 5/31/2012 | 5/31/2012 | P | PASS |
Dave Hannah
|
|
|
Mana Phone #: ###-####
|
BLD-Foundation | 5/30/2012 | 5/31/2012 | 5/31/2012 | A | NR |
Dave Hannah
|
|
|
Mana Phone #: ###-####
|
BLD-Footing | 5/29/2012 | 5/30/2012 | 5/30/2012 | A | PASS |
Dave Hannah
|
|
|
MANA Phone #: ###-####
|
PubWorks Subgrade Approval | 5/23/2012 | 5/23/2012 | 5/23/2012 | | DONE |
Terry Records
|
|
|
Footing subgrade approved
|
Plan assigned to (CDM) | | 5/1/2012 | 5/23/2012 | | PASS |
Carl D Madsen
|
|
|
|
Routing - PLAN CHECK | 5/23/2012 | | 5/23/2012 | | PASS |
Carl D Madsen
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/23/2012 | | |
|
|
|
|
Inspection Record Card- Bld | | | 5/23/2012 | | DONE |
|
|
|
|
Telephone call | | | 5/23/2012 | | DONE |
Christina Prado
|
|
|
Called Joe and gave fees due
|
Permit Ready to Issue | | | 5/23/2012 | | DONE |
Christina Prado
|
|
|
|
Issue PAID IN FULL permit | | | 5/23/2012 | | DONE |
Barbara Stitt
|
|
|
|
Routing - PLAN CHECK | 5/9/2012 | | 5/22/2012 | | FAIL |
Carl D Madsen
|
|
|
Additional information requested on beams and girder trusses. Called Joe Roth 5-22-12 CDM
|
1st review completed | | | 5/22/2012 | | FAIL |
|
|
|
|
Case Summary (BLD) | | | 5/22/2012 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 5/22/2012 | | DONE |
|
|
|
|
Plan resubmittals received | | | 5/22/2012 | | DONE |
Tisha Gallop
|
|
|
received two copies of page s-3; taken to Carl Madsen
|
Routing - Erosion and Sediment | 5/7/2012 | | 5/9/2012 | | PASS |
Clint A Smith
|
|
|
ESC12-00433 plan approved with conditions attached to the permit.
|
Routing - FIRE | 5/9/2012 | | 5/9/2012 | | PASS |
Scott Arellano
|
|
|
Per subdivsion plat note #12, all dwellings on lot's 16-23 on block #6, shall be fire sprinklered in accordance with NFPA 13D.
|
Routing - MECHANICAL | 5/9/2012 | | 5/9/2012 | | PASS |
Troy James
|
|
|
|
Routing - MECHANICAL | 5/7/2012 | | 5/7/2012 | | FAIL |
Troy James
|
|
|
emailed corrections to Build Energy
|
Routing - PLANNING | 5/4/2012 | | 5/7/2012 | | PASS |
Sue Cummings
|
|
|
|
Routing - PUBLIC WORKS | 5/3/2012 | | 5/4/2012 | | PASS |
Connie Baumgartner
|
|
|
|
Routing PW Grading-Hillside | | | 5/3/2012 | | PASS |
Terry Records
|
|
|
|
Routing - Addressing | 5/1/2012 | | 5/3/2012 | | PASS |
Terry Records
|
|
|
|
Route to Impact Fee Review | 5/1/2012 | 5/4/2012 | 5/1/2012 | | PASS |
Shauna Surgeon
|
|
|
|
Application received | | 5/1/2012 | 5/1/2012 | | DONE |
Christina Prado
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 5/1/2012 | | DONE |
Christina Prado
|
|
|
|
Intake Approval | | | 5/1/2012 | | PASS |
Christina Prado
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 5/1/2012 | | DONE |
Christina Prado
|
|
|
|