Print Statement | | | 10/23/2012 | | DONE |
|
|
|
|
First Notice | | 9/27/2012 | 10/15/2012 | | DONE |
|
|
|
|
BLD-Final | 9/14/2012 | 9/17/2012 | 9/17/2012 | A | PASS |
Jim Sly
|
|
|
Dave Phone #: ###-#### OK for Perm Occ.
|
Permanent Occupancy | | | 9/17/2012 | | DONE |
|
|
|
|
FIRE-Final Inspection | 9/13/2012 | 9/14/2012 | 9/14/2012 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed.
|
Zoning Approval | 9/14/2012 | 9/14/2012 | 9/14/2012 | | DONE |
Andrea Tuning
|
|
|
|
BLD-Conference | 8/23/2012 | 8/23/2012 | 8/23/2012 | P | DONE |
Jim Sly
|
|
|
Dave phone Checked Welding and through bolting at semi-circular front canopy.........OK. MTI special insp. welding.
|
BLD-Other | 8/23/2012 | 8/23/2012 | 8/23/2012 | P | PASS |
Jim Sly
|
|
|
Dave - ceiling grid Phone #: ###-#### Grid OK
|
BLD-Other | 8/22/2012 | 8/23/2012 | 8/23/2012 | A | CANC |
Jim Sly
|
|
|
PLease look at structural bolting on canopy--Dave Phone #: ###-#### Resched.......
|
BLD-Wall Bracing | 7/25/2012 | 7/26/2012 | 7/26/2012 | A | PART |
Jim Sly
|
|
|
Dave Phone #: ###-#### Need to look at shear on other side of new shear wall......Other framing appears OK...OK to one side....and 2 side in some areas.
|
BLD-Other | 7/16/2012 | 7/16/2012 | 7/16/2012 | P | PASS |
Jim Sly
|
|
|
dave Phone #: ###-#### Walk-thru with super.....
|
BLD-Footing | 7/10/2012 | 7/11/2012 | 7/11/2012 | P | PART |
Tom Arcoraci
|
|
|
dave Phone #: ###-#### spec inspection
|
Issue PAID IN FULL permit | | | 6/18/2012 | | DONE |
Tisha Gallop
|
|
|
|
1st review completed | | | 5/25/2012 | | DONE |
Tim L. Woodard
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/25/2012 | | DONE |
Tim L. Woodard
|
|
|
|
Case Summary (BLD) | | | 5/25/2012 | | DONE |
Tim L. Woodard
|
|
|
|
Print Occupancy Form | | | 5/25/2012 | | DONE |
|
|
|
|
Telephone call | | | 5/25/2012 | | DONE |
Christina Prado
|
|
|
Called and gave John fees due and advised GC/RCE is required prior to issuance
|
Permit Ready to Issue | | | 5/25/2012 | | DONE |
Christina Prado
|
|
|
|
Plan assigned to (TLW) | 5/7/2012 | | 5/25/2012 | | PASS |
Tim L. Woodard
|
|
|
|
Routing - PLAN CHECK | 5/9/2012 | | 5/25/2012 | | PASS |
Tim L. Woodard
|
|
|
Tim Woodard
|
Plan resubmittals received | | | 5/21/2012 | | DONE |
Tisha Gallop
|
|
|
received by mail two copies of structural calcs and plan sheets S-111, S-511, A201, A403, A404; taken to Tim Woodard.
|
Routing PW Sewer Rating | 5/8/2012 | | 5/9/2012 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - PUBLIC WORKS | 5/8/2012 | | 5/9/2012 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - Addressing | 5/8/2012 | | 5/8/2012 | | PASS |
Terry Records
|
|
|
|
Application received | | 5/7/2012 | 5/7/2012 | | DONE |
Barbara Stitt
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 5/7/2012 | | DONE |
Barbara Stitt
|
|
|
|
Intake Approval | | | 5/7/2012 | | PASS |
Tim L. Woodard
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 5/7/2012 | | DONE |
Barbara Stitt
|
|
|
|