BLD-Final | 9/19/2012 | 9/19/2012 | 9/19/2012 | P | PASS |
Dave Hannah
|
|
|
John Phone #: ###-####
|
DOC - Permit Finaled | 9/19/2012 | 9/19/2012 | 9/19/2012 | P | PASS |
Dave Hannah
|
|
|
|
BLD-Final | 9/17/2012 | 9/17/2012 | 9/17/2012 | P | FAIL |
Dave Hannah
|
|
|
john Phone #: ###-#### c/n on site
|
BLD-Framing/Rough-in | 8/6/2012 | 8/7/2012 | 8/7/2012 | A | CANC |
Dave Hannah
|
|
|
framing and air seal//John Phone #: ###-####
|
BLD-Energy code compliance | 7/17/2012 | 7/18/2012 | 7/18/2012 | A | PASS |
Dave Hannah
|
|
|
JOHN Phone #: ###-####
|
BLD-Framing/Rough-in | 7/11/2012 | 7/11/2012 | 7/11/2012 | P | PART |
Jim Storey
|
|
|
john Phone #: ###-#### blk b3 girder thur to bearing/ support floor joist brace webs ad noted. ok to insulate.
|
BLD-Wall Bracing | 6/25/2012 | 6/25/2012 | 6/25/2012 | P | PART |
Dave Hannah
|
|
|
Dave Phone #: ###-#### ok to cover ext but still needs to install fl to fl strapes
|
BLD-Foundation | 5/31/2012 | 6/4/2012 | 6/4/2012 | A | PASS |
Dave Hannah
|
|
|
Phone #: 6951097 >> Inspection requested via mobile web by adam
|
BLD-Footing | 5/31/2012 | 6/1/2012 | 6/1/2012 | A | PASS |
Dave Hannah
|
|
|
Phone #: 6951097 >> Inspection requested via mobile web by adam
|
BLD-Foundation | 5/31/2012 | 6/1/2012 | 5/31/2012 | A | CANC |
Dave Hannah
|
|
|
Phone #: 6951097 >> Inspection requested via mobile web by adam Inspection cancelled via moblie web on Thursday, May 31, 2012.
|
Issue PAID IN FULL permit | | | 5/29/2012 | | DONE |
Christina Prado
|
|
|
|
OVERRIDE | | | 5/25/2012 | | |
|
|
|
|
Plan assigned to (CDM) | 5/7/2012 | 5/7/2012 | 5/25/2012 | | PASS |
Carl D Madsen
|
|
|
|
Plan resubmittals received | | | 5/25/2012 | | DONE |
|
|
|
Shear wall engineering packet 5-25-12 CDM
|
Routing - PLAN CHECK | 5/25/2012 | | 5/25/2012 | | PASS |
Carl D Madsen
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/25/2012 | | |
|
|
|
|
Inspection Record Card- Bld | | | 5/25/2012 | | DONE |
Christina Prado
|
|
|
|
Permit Ready to Issue | | | 5/25/2012 | | DONE |
Tisha Gallop
|
|
|
|
Telephone call | | | 5/25/2012 | | DONE |
Tisha Gallop
|
|
|
called Seidl Homes and left vm in general mailbox that permit is ready, fees and need GC form.
|
1st review completed | | | 5/24/2012 | | FAIL |
|
|
|
|
Case Summary (BLD) | | | 5/24/2012 | | DONE |
|
|
|
|
Routing - PLANNING | 5/24/2012 | | 5/24/2012 | | PASS |
David Moser
|
|
|
side load garage and revised site plan moved house to 50 foot front setaback from back of sidewalk
|
Routing - PLAN CHECK | 5/11/2012 | | 5/24/2012 | | FAIL |
Carl D Madsen
|
|
|
Needs to provide the engineering calculations for the wall bracing plan. Called John with Seidl Homes 5-24-12 CDM
|
Plan resubmittals received | | | 5/21/2012 | | DONE |
Christina Prado
|
|
|
Received two sets of new Site Plan and two reduced site plans. Taken to Carl Madsen for further review and routing
|
Routing - MECHANICAL | 5/14/2012 | | 5/14/2012 | | PASS |
Troy James
|
|
|
|
Routing - MECHANICAL | | | 5/11/2012 | | FAIL |
Troy James
|
|
|
sent corrections to Idaho Geo
|
Routing - PLANNING | 5/9/2012 | | 5/9/2012 | | PASS |
David Moser
|
|
|
|
Routing - PUBLIC WORKS | 5/8/2012 | | 5/9/2012 | | PASS |
Connie Baumgartner
|
|
|
|
Route to Impact Fee Review | 5/7/2012 | 5/10/2012 | 5/8/2012 | | PASS |
Cindy M. Gould
|
|
|
|
Routing - Addressing | 5/7/2012 | | 5/8/2012 | | PASS |
Terry Records
|
|
|
|
Application received | | 5/7/2012 | 5/7/2012 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 5/7/2012 | | DONE |
Alexandra L. DeYoung
|
|
|
|
Intake Approval | | | 5/7/2012 | | PASS |
Alexandra L. DeYoung
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 5/7/2012 | | DONE |
Alexandra L. DeYoung
|
|
|
|