Information based on query as of Tuesday, July 16, 2024.
Permit Information
Permit NumberBLD12-01109
StatusFinaled
Name Steven Panzella
Site Address 1387 S VINNELL WAY
Project NameDepartment of Labor
Customer Number 
ePlanReviewYes
Description
(GSA - DEPARTMENT OF LABOR – 1st Floor) Permit is to remodel an existing 1,766 square foot area for a new department in which GSA occupies the entire floor. Approval contingent upon adhering to the approved plans on file. Work to include: [construction of interior non-bearing walls to create eight separate office areas, one storage area, and a copy area], installation of new accessible doors and hardware, relocate light fixtures, new light switching, relocate mechanical, and finishes in compliance with chapter 8 of the 2006 IBC. This building is fully Fire Sprinklered with an approved Fire Alarm system. Any alterations or modifications to the buildings Fire Sprinkler or Fire Alarm system WILL REQUIRE A SEPARATE PERMIT and shall be installed per NFPA 13 & NFPA 72 as regulated by the Boise Fire Department. **TLW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Third Notice 10/30/201210/17/2012 DONE
Third Notice 10/1/201210/16/2012 DONE
faxed
Second Notice 9/3/20129/26/2012 DONE
faxed
First Notice 8/20/20128/24/2012 DONE
faxed
Permanent Occupancy  8/10/2012 DONE
DetailsTisha Gallop
BLD-Final6/12/20126/13/20126/13/2012APASS
DetailsMike Jordan
Steve Phone #: ###-####. OK for perm occ.
FIRE-Final Inspection6/12/20126/12/20126/12/2012PPASS
DetailsTroy Cobbley
life safety passed
BLD-Other5/30/20125/30/20125/30/2012PPART
DetailsMike Jordan
Steve - ceiling insp Phone #: ###-####. Ceiling grid ok pending other trades rough ins.
BLD-Framing/Rough-in5/21/20125/21/20125/21/2012PPASS
DetailsMike Jordan
Steve Phone #: ###-####
Print Occupancy Form  5/21/2012 DONE
DetailsChristina Prado
Print Occupancy Form  5/21/2012 DONE
DetailsChristina Prado
Permit Ready to Issue  5/21/2012 DONE
DetailsChristina Prado
Issue PAID IN FULL permit  5/21/2012 DONE
DetailsChristina Prado
Plan assigned to (TLW)5/10/2012 5/18/2012 PASS
DetailsTim L. Woodard
Routing - PLAN CHECK5/10/2012 5/18/2012 PASS
DetailsTim L. Woodard
Approved with Redlines in E-plan review. TLW
1st review completed  5/18/2012 DONE
DetailsTim L. Woodard
PLANS/APPL TAKEN TO FRONT DESK  5/18/2012 DONE
DetailsTim L. Woodard
Routing - Addressing5/10/2012 5/11/2012 PASS
DetailsTerry Records
Routing - FIRE5/11/2012 5/11/2012 PASS
DetailsTim Frost
Intake Approval  5/10/2012 PASS
DetailsTim L. Woodard
Application received  5/8/2012 DONE
Application submitted via PDS Online on May 8 2012 3:24PM