Information based on query as of Friday, August 16, 2024.
Permit Information
Permit NumberBLD12-01123
StatusIssued
Name PIONEER WATERPROOFING COMPANY INC
Site Address 1001 W IDAHO ST
Project NameWASHINGTON FEDERAL
Customer Number 
ePlanReviewNo
Description
(WASHINGTON FEDERAL - GARAGE REPAIR) 6/25/12 Plan Modification - Expand scope of work to include removal of existing topping slab and replace with new reinforced topping slab over existing precast beams. drs To make repairs to existing concrete columns, "T"- Beams, and support ledges in accordance with the engineered details and referenced standards of the reviewed plans. Change out steel support structure for security gate. Special Inspection is required as indicated in the Statement of Special Inspections, to include the epoxy injection procedure, form and pour/pump procedure, reinforcing bar replacement and Sheet S0.01, Tests & Inspections; and as required by the Evaluation Services Report (ESR) for special products proposed for use in this project. The scope and intent of work is to "restore the structural elements of the garage to their design sections and strength" and damage being repaired is classified as "not substantial" based on substantial definition in 3405, IBC, per engineer. drs
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final10/30/201210/31/201211/6/2012ANR
DetailsDave Hannah
call when go out//Jeff Phone #: ###-#### site is ok but I need a letter from mti on the spec. inspection work.
BLD-Concrete8/16/20128/16/20128/16/2012PPART
DetailsDave Hannah
Call prior to going Phone #: 2088598844 >> Inspection requested via mobile web by Wes Watts crew getting ready to place first two section of new deck mti is doing the spec inspection and conc testing thats installed looks good mti will sign off befor placement
Routing - PUBLIC WORKS GRADING7/23/2012 7/23/2012 PASS
DetailsClint A Smith
ESC12-00747 plan waiver approved with additional conditions attached to the permit.
CHANGE STATUS TO (ISS)  7/11/2012 DONE
(F) Reprint permit  7/11/2012 DONE
Plan assigned to (DRS)6/26/20126/26/20127/10/2012 PASS
DetailsDan Stuart
Routing - PLAN CHECK6/26/2012 7/10/2012 PASS
DetailsDan Stuart
Structural review approved. Plans to permit desk to issue permit.
Telephone call  7/10/2012 DONE
DetailsChristina Prado
called Dale to give fees due
Override - Parcel Holds  7/10/2012  
Inspection Record Card- Bld  7/10/2012 DONE
DetailsChristina Prado
Routing Off Site - STRUCTURAL6/26/2012 7/3/2012 PASS
Details
Telephone call  6/26/2012 DONE
DetailsTisha Gallop
called Action Couriers for pick up
Plan Reviewer's activity  6/26/2012 DONE
One copy of plans and calcs to Tisha to route to outside structural engineering review.
Plan Modification Accepted  6/25/2012 DONE
DetailsTisha Gallop
Plan modification accepted for Bld12-01123 (Washington Federal - Garage Repair) for removal of cracked and damaged topping slab. Provide a new reinforced concrete topping slab over the precast beams over underground the garage. Submitted on plan sheets P2S0.01, P2S1.01, P2S2.01, P2S3.01, P2S4.01 P2S5.01; routed to Dan Stuart.
Issue PAID IN FULL permit  6/15/2012 DONE
DetailsChristina Prado
Plan assigned to (DRS)5/11/20125/11/20125/30/2012 PASS
DetailsDan Stuart
Routing - PLAN CHECK5/29/2012 5/30/2012 PASS
DetailsDan Stuart
Reubmittals for special product standards and uses and completed statement of special inspections provided. MTI listed as special inspection agency.
Plan Reviewer's activity  5/30/2012 DONE
Attached copies of ACI RAP 1; ACI RAP 4; ACI RAP 5; EPOXY 100; GALVASHIELD; ZINC REBAR AND LA REPAIR MORTAR & STATEMENT OF SPECIAL INSPECTION FORM 310 TO PERMIT.
PLANS/APPL TAKEN TO FRONT DESK  5/30/2012 PASS
Inspection Record Card- Bld  5/30/2012 DONE
Permit Ready to Issue  5/30/2012 DONE
DetailsTisha Gallop
Telephone call  5/30/2012 DONE
DetailsTisha Gallop
called Lee Harrison and left vm permit is ready, fees, need GC/rce/form.
Routing - PLAN CHECK5/11/2012 5/21/2012 FAIL
DetailsDan Stuart
Further clarification required concerning special inspection call-out, products and special inspection agency selected. Spoke on phone with Lee Harrison and then Larry (?), of Axiom Innovative Engineering PLLC. Sent e-mail to Lee concerning phone conversation and information to be provided and ask him to forward to Larry. Larry was the engineer designer.
1st review completed  5/21/2012 FAIL
DetailsDan Stuart
Fail in building plan review.
Pending Assignment by JCB5/10/2012 5/11/2012 DONE
DetailsJason Blais
Intake Approval  5/10/2012 PASS
DetailsSam Zahorka
Plans ACCEPTED BY PLAN TECH  5/10/2012 DONE
DetailsChristina Prado
Recd Pcfee & Taken To Pln CK  5/10/2012 DONE
DetailsChristina Prado
Application received 5/9/2012