Second Notice | | 9/2/2012 | 8/28/2012 | | DONE |
|
|
|
This permit finaled on the web by Brian Warbis
|
First Notice | 8/20/2012 | 8/20/2012 | 8/23/2012 | | DONE |
Mike Jordan
|
|
|
faxed
|
BLD-Final | 8/20/2012 | 8/20/2012 | 8/20/2012 | P | PASS |
Mike Jordan
|
|
|
bryan Phone #: ###-####
|
DOC - Permit Finaled | 8/20/2012 | 8/20/2012 | 8/20/2012 | P | PASS |
Mike Jordan
|
|
|
|
FIRE-Final Inspection | 8/20/2012 | 8/20/2012 | 8/20/2012 | A | PASS |
Forrest France
|
|
|
Vanilla shell fire life safety final okay pending address numbers are posted prior to structural final as discussed.
|
BLD-Framing/Rough-in | 6/29/2012 | 7/2/2012 | 7/2/2012 | P | PASS |
Dave Hannah
|
|
|
Steve Ove Phone #: ###-#### ok to insulate ext wall and cover int walls after elc rough in
|
Issue PAID IN FULL permit | | | 6/29/2012 | | DONE |
Christina Prado
|
|
|
|
Inspection Record Card- Bld | | | 6/29/2012 | | DONE |
Christina Prado
|
|
|
|
Telephone call | | | 6/5/2012 | | DONE |
|
|
|
emailed Trent fees due permit ready
|
Permit Ready to Issue | | | 6/5/2012 | | DONE |
|
|
|
|
Plan assigned to (TLW) | 6/1/2012 | | 6/1/2012 | | PASS |
Tim L. Woodard
|
|
|
|
Routing - PLAN CHECK | 6/1/2012 | | 6/1/2012 | | PASS |
Tim L. Woodard
|
|
|
|
1st review completed | | | 6/1/2012 | | DONE |
Tim L. Woodard
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/1/2012 | | DONE |
Tim L. Woodard
|
|
|
|
Telephone call | | | 6/1/2012 | | DONE |
Tisha Gallop
|
|
|
e-mailed applicant, plans approved, have GC call permit desk
|
Routing - Addressing | 5/23/2012 | | 5/23/2012 | | PASS |
Terry Records
|
|
|
|
Intake Approval | | | 5/22/2012 | | PASS |
Tim L. Woodard
|
|
|
|
Intake Approval | | | 5/11/2012 | | FAIL |
Tim L. Woodard
|
|
|
Ryan,
Please address the following items so a prescreen review can be completed. First, this project would be a major tenant improvement and need #520 application and checklist filled out and uploaded into the documents folder. Next is the submittal upload guide was not followed as required; a stamping area is required in the bottom right of each plan sheet for batch stamping. Down load the required submittal upload guide and comply with all requirements including the stamping area. When uploading new sheets be sure to name them exactly the same as the sheets in the system, this will inturn create a version two of the sheet. After all items are addressed go into the workflow portal and sign off on your task. Thanks Tim Woodard (208) 384 3817.
|
Application received | | | 5/10/2012 | | DONE |
|
|
|
Application submitted via PDS Online on May 10 2012 8:38AM
|