Permanent Occupancy | | | 7/17/2012 | | DONE |
Barbara Stitt
|
|
|
|
BLD-Final | 7/13/2012 | 7/13/2012 | 7/13/2012 | P | PASS |
Jim Storey
|
|
|
Zach Phone #: ###-####
|
Zoning Approval | 7/13/2012 | 7/13/2012 | 7/13/2012 | | DONE |
Sarah Schafer
|
|
|
|
FIRE-Final Inspection | 7/12/2012 | 7/12/2012 | 7/12/2012 | P | PASS |
Forrest France
|
|
|
Fire life safety inspection completed satisfactory.
|
BLD-Other | 7/10/2012 | 7/10/2012 | 7/10/2012 | P | PASS |
Tom Arcoraci
|
|
|
Derek Phone #: ###-#### - ceiling cover
|
BLD-Framing/Rough-in | 6/15/2012 | 6/15/2012 | 6/15/2012 | P | PART |
Jim Storey
|
|
|
call for lock box code//Derrick Phone #: ###-#### okt ogyp pannel required to ne wraped to maintane 1 hr wall .
|
Issue PAID IN FULL permit | | | 6/13/2012 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 6/12/2012 | | DONE |
Tim L. Woodard
|
|
|
|
Inspection Record Card- Bld | | | 6/12/2012 | | DONE |
|
|
|
|
Print Occupancy Form | | | 6/12/2012 | | DONE |
Christina Prado
|
|
|
|
Telephone call | | | 6/12/2012 | | DONE |
Christina Prado
|
|
|
left message with RRC giving fees due and advising permit is ready
|
Permit Ready to Issue | | | 6/12/2012 | | DONE |
Christina Prado
|
|
|
|
1st review completed | | | 6/11/2012 | | DONE |
Tim L. Woodard
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/11/2012 | | DONE |
Tim L. Woodard
|
|
|
|
Plan assigned to (TLW) | 5/25/2012 | | 6/11/2012 | | PASS |
Tim L. Woodard
|
|
|
|
Routing - PLAN CHECK | 5/31/2012 | | 6/11/2012 | | PASS |
Tim L. Woodard
|
|
|
Approved with redlines and report. TLW
|
Routing - PUBLIC WORKS | 5/25/2012 | | 6/11/2012 | | PASS |
Connie Baumgartner
|
|
|
Approved on routing slip.
|
Routing PW Sewer Rating | 5/30/2012 | | 5/31/2012 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - Addressing | 5/25/2012 | | 5/30/2012 | | PASS |
Terry Records
|
|
|
Research was needed to complete plans.
|
Routing PW Environmental | 5/30/2012 | | 5/30/2012 | | PASS |
Walt Baumgartner
|
|
|
Approved but Facility subject to pretreatment sewer discharge requirements. Plans donot indicated processes, inspection to follow.
|
Recd Pcfee & Taken To Pln CK | | | 5/25/2012 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 5/25/2012 | | DONE |
|
|
|
|
Intake Approval | | | 5/25/2012 | | PASS |
Tim L. Woodard
|
|
|
|
Application received | | 5/16/2012 | 5/16/2012 | | DONE |
Barbara Stitt
|
|
|
|