BLD-Framing/Rough-in | 7/26/2012 | 7/27/2012 | 7/27/2012 | A | PASS |
Dave Hannah
|
|
|
Bill - call for access Phone #: ###-####
|
BLD-Footing | 7/20/2012 | 7/23/2012 | 7/23/2012 | A | PASS |
Dave Hannah
|
|
|
Bill Phone #: ###-####
|
Permit Ready to Issue | | | 7/20/2012 | | DONE |
Christina Prado
|
|
|
|
Issue PAID IN FULL permit | | | 7/20/2012 | | DONE |
Tisha Gallop
|
|
|
|
Print Occupancy Form | | | 7/20/2012 | | DONE |
Tisha Gallop
|
|
|
|
Routing - PLANNING | 7/16/2012 | | 7/17/2012 | | PASS |
Joshua Johnson
|
|
|
Signed off in e-plan review.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/17/2012 | | PASS |
|
|
|
|
Plan assigned to (DRS) | 6/11/2012 | | 7/17/2012 | | PASS |
Dan Stuart
|
|
|
ePlanReview case
|
Routing - PLAN CHECK | 6/11/2012 | | 7/17/2012 | | PASS |
Dan Stuart
|
|
|
|
Routing - FIRE | 6/11/2012 | | 6/27/2012 | | PASS |
Scott Arellano
|
|
|
Attached IFC comments to plans
|
1st review completed | | | 6/27/2012 | | FAIL |
Dan Stuart
|
|
|
Failed planning - 10 day appeal period not up.
|
Routing - PLUMBING | 6/11/2012 | | 6/12/2012 | | PASS |
Daryl Spivey
|
|
|
Per plans and 2003 UPC.
|
Routing - PLANNING | 6/11/2012 | | 6/11/2012 | | FAIL |
Sue Cummings
|
|
|
Sue Cummings - Plans failed. CUP hearing on 7/2/12. Plans to reroute to Josh Johnson when resubmittals arrive.
|
Routing - Erosion and Sediment | 6/11/2012 | | 6/11/2012 | | PASS |
Clint A Smith
|
|
|
ESC plan12-00578 plan waiver approved with additional conditions attached to the permit.
|
Intake Approval | | | 6/8/2012 | | PASS |
Sam Zahorka
|
|
|
|
Intake Approval | | | 5/29/2012 | | FAIL |
Sam Zahorka
|
|
|
See circled items on 520 T.I. submittal checklist.
|
Application received | | | 5/25/2012 | | DONE |
|
|
|
Application submitted via PDS Online on May 25 2012 2:46PM
|