Permit Information
Permit NumberBLD12-01399
StatusFinaled
Name HC COMPANY INC
Site Address 5777 N MEEKER AVE
Project NameBodybuilding.com
Customer Number 
ePlanReviewYes
Description
(BODYBUILDING.COM) To remodel an existing 77,050 square foot, two story office building with a 21,000 square foot basement building. This is a complete remodel of all existing floors. First Floor is 40,600 sq. ft. and Second Floor is 36,450 sq. ft.. The first floor square footage includes the new rear roof canopy. This remodel also includes extensive exterior changes including the demo and reconstruction of the exterior walls at the northeast, main entry, corner of the building, as well as, extensive exterior wall demo to install new window systems at all walls on both floors. To i nstall two new 13'x6' windows with light well retaining walls at the basement south wall. This building is fully fire sprinkled. The sprinklers are used for area increase. The building interior demolition was done under permit BLD12-00412. New site work to include parking and landscaping, entry plaza and patio area, as well as, a new volleyball and backetball courts. Planning approval done under DRH11-00300. All construction per approved plans and attached comment list. JCM
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
First Notice 9/8/201310/8/2013 DONE
Faxed 10-1-13
Print Statement  10/8/2013 DONE
DetailsTisha Gallop
e-mailed to Jeff Tonking/HC Company
Permanent Occupancy  8/29/2013 DONE
DetailsTisha Gallop
BLD-Final8/28/20138/28/20138/28/2013PPASS
DetailsJim Sly
chris Phone #: ###-####
OK for Perm Occ.
BLD-Final8/14/20138/15/20138/15/2013PPART
DetailsJim Sly
steve Phone #: ###-####
OK for Temp Occ. OK for Perm Occ. when Plumbing Perms.
BLD-Final8/14/20138/15/20138/15/2013APEND
DetailsJim Sly
Coordinate with fire if possible.
Walk thru with superintendant.......Waiting for fire to sign off.
FIRE-Final Inspection8/14/20138/15/20138/15/2013APASS
DetailsTroy Cobbley
Life safety passed
Temporary Occupancy8/15/201311/13/20138/15/2013 DONE
DetailsDarla L Downs
Zoning Approval8/15/20138/15/20138/15/2013 DONE
DetailsAndrea Tuning
PubWorks Occupancy Approval8/14/20138/14/20138/14/2013 DONE
DetailsTiffany Lowery
BLD-Conference8/12/20138/12/20138/12/2013PDONE
DetailsJim Sly
steve Phone #: ###-####
BLD-Ceiling Grid Inspection8/7/20138/8/20138/8/2013APASS
DetailsMike Jordan
Steve Phone #: ###-####. 2nd. Floor ceiling grid ok.
FIRE-Conference7/25/20137/26/20137/26/2013ADONE
DetailsForrest France
needs clarification on something//Steve Phone #: ###-#### *Regarding existing door holds and a curtain wall not shown on the approved plans and set to be removed*
BLD-Other7/25/20137/25/20137/25/2013PPASS
DetailsJim Sly
STEVE Phone #: ###-####
Southwest Shaft....2nd floor......OK
BLD-Other7/24/20137/25/20137/25/2013ANR
DetailsJim Sly
smoke stop at floor-veritcal shaft-Steve Phone #: ###-####
BLD-Other7/11/20137/11/20137/11/2013PPART
DetailsJim Sly
shaft insp//steve Phone #: ###-####
Select shafts....OK
BLD-Other7/10/20137/10/20137/11/2013PNR
DetailsJim Sly
Floor assembly & shaft opening x2 - Steve Phone #: ###-####
BLD-Ceiling Grid Inspection7/8/20137/8/20137/8/2013PPART
DetailsJim Sly
steve Phone #: ###-####
Bsmnt. OK
FIRE-Conference6/24/20136/25/20136/24/2013ADONE
DetailsTroy Cobbley
Steve and I discussed covering sprinkler piping prior to a rough-in inspection. I was ok with some covering as long as there was easy access. Phone #: ###-####
BLD-Framing/Rough-in6/20/20136/21/20136/21/2013ACANC
DetailsJim Sly
Steve phone ###-####
BLD-Ceiling Grid Inspection6/19/20136/20/20136/21/2013APART
DetailsJim Sly
Above ceiling - Steve Phone #: ###-####
2nd floor soffits OK
BLD-Framing/Rough-in5/22/20135/22/20135/22/2013PPART
DetailsJim Sly
STEVE Phone #: ###-####
Select walls, soffits and ceilings.
BLD-Other5/6/20135/6/20135/6/2013PPASS
DetailsJim Sly
Parapet plywood wall - Dan Phone #: ###-####
Parapet walls and Framing in South East restrooms on main floor OK .
BLD-Other5/1/20135/1/20135/1/2013PPART
DetailsJim Sly
steve Phone #: ###-####
Select soffit framing ....West end Basement.
BLD-Framing/Rough-in4/24/20134/25/20134/25/2013APART
DetailsJim Sly
Steve Phone #: ###-####
Exterior walls...Front entry area.....OK
BLD-Concrete4/18/20134/19/20134/19/2013ACANC
DetailsJim Sly
Steve phone
BLD-Other4/18/20134/18/20134/18/2013PPASS
DetailsJim Sly
rebar for piers and trash enclosure//Steve Phone #: ###-####
OVERRIDE  4/16/2013  
CHANGE STATUS TO (ISS)  4/16/2013 DONE
DetailsBarbara Stitt
(F) Reprint permit  4/16/2013 DONE
DetailsBarbara Stitt
Print Occupancy Form  4/16/2013 DONE
DetailsBarbara Stitt
Telephone call  4/16/2013 DONE
DetailsChristina Prado
called Jeff to give fees due and advise plan mod is ready
Plan assigned to (JCM)2/11/2013 4/15/2013 PASS
DetailsJohn Menard
Routing - PLAN CHECK4/10/2013 4/12/2013 PASS
DetailsJohn Menard
BLD-Framing/Rough-in4/10/20134/11/20134/11/2013APART
DetailsJim Sly
steve - 2nd floor Phone #: ###-####
All framing 2nd floor OK except... West of Grid line 3.
Routing Off Site - STRUCTURAL4/10/2013 4/11/2013 PASS
DetailsJohn Menard
Routing - Design Review4/10/2013 4/10/2013 PASS
DetailsAndrea Tuning
Routing - PLAN CHECK4/1/2013 4/1/2013 PASS
DetailsJohn Menard
Routing Off Site - STRUCTURAL4/1/2013 4/1/2013 FAIL
DetailsJohn Menard
BLD-Conference3/25/20133/26/20133/26/2013ADONE
DetailsJim Sly
Steve ###-####
Plan resubmittals received  3/26/2013 DONE
DetailsJohn Menard
Received e-mail from project structural engineer submitting revised structural calculations and drawings. JCM
BLD-Framing/Rough-in3/25/20133/25/20133/25/2013PPART
DetailsJim Sly
steve Phone #: ###-####
BLD-Framing/Rough-in3/18/20133/18/20133/18/2013PPART
DetailsJim Sly
steve - this is not for the entry Phone #: ###-####
Select 1st floor and Basement walls.......OK.
BLD-Footing3/14/20133/14/20133/14/2013PPASS
DetailsJim Sly
steve Phone #: ###-####
Pending MTI insp. tests and approvals. OK'd only to pour foundation for front entry.
MISC ACTIONS  3/13/2013 DONE
Structural Engineer has ok'd foundation plan for new exterior entry. Ok to inspect, this area only per John Menard. All other structural resubmittals are still under review. Permit is still in review status for modifications. Contractor must have copies of approved structural sheets S2.1 and S5.1 on site for inspector. Plans have a red bubble that states these plans are approved for front entry way foundation only.
Telephone call  3/13/2013 DONE
Called Jeff Tonkin and let him know to come and pick up two approved plan sheets so he can get his foundation inspection for the front entry way. Called Jim Sly and let him know what is going on.
Plan resubmittals received  3/11/2013 DONE
DetailsJohn Menard
Received e-mail from project engineer with revised structural calculations and drawings for the entry portion of the building. Uploaded to ProjectDox and notified reviewing engineer. JCM
Routing Off Site - STRUCTURAL2/11/2013 2/28/2013 FAIL
DetailsJohn Menard
BLD-Other2/26/20132/27/20132/27/2013APASS
DetailsTom Arcoraci
insp on fire rated plywood at parapet wall //Steve Phone #: ###-####
BLD-Footing2/22/20132/22/20132/22/2013PCANC
DetailsJim Sly
Steve Phone #: ###-####
After I notified Steve that a plan modification for front entry and basketball/volleyball courts were submitted for approval by the City on 2/22/13, He cancelled inspection.
Plan Modification Accepted  2/22/2013 DONE
DetailsTisha Gallop
Plan Modification started in ePlanReview for the redesign of main entrance and addition of basketball & volleyball courts.
Routing - PLAN CHECK2/11/2013 2/22/2013 FAIL
DetailsJohn Menard
Routing - FIRE2/11/2013 2/13/2013 PASS
DetailsScott Arellano
Attached updated comments to plans.
Routing - PLUMBING2/11/2013 2/12/2013 PASS
DetailsDaryl Spivey
May require additional backflow protection.
Routing - Design Review2/11/2013 2/12/2013 FAIL
DetailsAndrea Tuning
The building elevations do not match the elevations that were approved with the Design Review Approval. The building permit can not be modified until a design review modification has been submitted, reviewed and approved.
Routing - PUBLIC WORKS2/11/2013 2/11/2013 PASS
DetailsConnie Baumgartner
Issue PAID IN FULL permit  11/2/2012 DONE
DetailsBarbara Stitt
Print Occupancy Form  11/2/2012 DONE
DetailsBarbara Stitt
Permit Ready to Issue  10/30/2012 DONE
DetailsTisha Gallop
Plan assigned to (JCM)7/10/20127/10/20129/5/2012 PASS
DetailsJohn Menard
Reassigned to John Menard
Routing - PLUMBING8/30/2012 9/5/2012 PASS
DetailsJohn Menard
Routing Off Site - STRUCTURAL8/30/2012 9/5/2012 PASS
DetailsJohn Menard
Received letter from consulting structural engineer approving final structural revisions. JCM
PLANS/APPL TAKEN TO FRONT DESK  9/5/2012 DONE
DetailsJohn Menard
Routing - PLAN CHECK8/3/2012 9/5/2012 PASS
DetailsJohn Menard
Routing - PUBLIC WORKS8/13/2012 8/13/2012 PASS
DetailsBeverly Mountain
Plan mod fees updated bam
Routing Off Site - STRUCTURAL8/3/2012 8/10/2012 FAIL
DetailsJohn Menard
Routing - FIRE8/3/2012 8/7/2012 PASS
DetailsScott Arellano
Attached Fire Code comments to plans.
Routing - PLAN CHECK7/10/2012 7/19/2012 FAIL
DetailsJohn Menard
1st review completed  7/19/2012 FAIL
DetailsJohn Menard
Routing - PLUMBING7/12/2012 7/17/2012 PASS
DetailsBill VanDegrift
plans approved with resubmitted civil showing 6" rain water line to site system and red lines dated 6/16/12 and 7/17/12.
Routing - PLANNING7/12/2012 7/12/2012 PASS
DetailsAndrea Tuning
Second Review
Routing - FIRE6/13/2012 7/12/2012 FAIL
DetailsScott Arellano
Corrections needed. See attached plan review report or change marks within e-plan review.
Plan assigned to (CJW)6/13/20126/13/20127/10/2012 DEFR
DetailsCarl Westfall
(20 days - July 9) ePlanReview case - Reassigned to John Menard
Routing - PLAN CHECK6/13/2012 7/10/2012 PASS
DetailsCarl Westfall
Plan resubmittals received  7/10/2012 DONE
Received electronic resubmittals of civil, landscape, mechanical and structural plans.
Routing PW Drainage6/15/2012 6/25/2012 PASS
DetailsBrian Murphy
Routing Off Site - STRUCTURAL6/13/2012 6/20/2012 FAIL
DetailsJohn Menard
Routing Off Site - C.D.H6/13/2012 6/18/2012 PASS
DetailsJohn Menard
Routing - Erosion and Sediment6/13/2012 6/18/2012 PASS
DetailsClint A Smith
ESC12-00599 plan approved with conditions attached to the permit.
Routing PW Sewer Rating6/15/2012 6/18/2012 PASS
DetailsConnie Baumgartner
Routing PW Environmental6/15/2012 6/18/2012 PASS
DetailsWalt Baumgartner
Routing PW Street Lights6/15/2012 6/15/2012 PASS
DetailsMike D Hedge
Routing PW Solid Waste6/15/2012 6/15/2012 PASS
DetailsPeter J. McCullough
Routing - PLUMBING6/13/2012 6/15/2012 FAIL
DetailsBill VanDegrift

1)submit civil plan showing rain water piping see P3.1
2) provide waste and vents for washers on 2nd floor.
3)detail 4 page P6.0-3 toilets max on a 3" horizontal waste line.
4)fixture schedule lists a D1 dosposal. verify approval with public works.
5)all kitchen fixtures and equipment to be indirectly wasted except hand sinks.
6)max. 120 degrees hot water to kitchen hand sinks.
7)aditional cross connection protection may be required.
8) address item 1- items 6 through 7 are comments see redlines.
Routing - PUBLIC WORKS6/13/2012 6/15/2012 PASS
DetailsBeverly Mountain
Route to Impact Fee Review6/13/20126/18/20126/14/2012 PASS
DetailsCindy M. Gould
Routing - Design Review6/13/2012 6/14/2012 FAIL
DetailsAndrea Tuning
The applicant will need to revise the site plan and landscape plan to include two new planter islands within the new parking field to the south of the building. The applicant will also be required to remove the pea gravel from the planter islands adjacent to the public roadways and replace it with an organic bark mulch. Andrea Tuning - DRH11-00300
Routing - Addressing6/13/2012 6/14/2012 PASS
DetailsTerry Records
Pending Assignment by JCB6/13/2012 6/13/2012 DONE
DetailsJason Blais
Plan Reviewer's activity  6/13/2012 DONE
DetailsJason Blais
Emailed architect to have him contact ACHD to evaluate any impact fees due. Written verification from ACHD is required to be provided to our Permit Counter prior to the building permit being issued.
Intake Approval  6/12/2012 PASS
DetailsTim L. Woodard
Stan,

Please revise plans according to Version 2 of the Checklist. I have bracketted anything that is still required and made additional notes under "Building Plans". The additional notes include the requirements for upload; such as: horizontal plan sheets, clear stamping area, and some sheets did not upload at all (L1.0 / L1.1). Please call with questions. I tried calling you around 11:55 pm, but no answer.

Tim Woodard
###-####

Plan Review Fees paid on 6/12/12.
Application received  6/1/2012 DONE
Application submitted via PDS Online on Jun 1 2012 1:22PM