Second Notice | | 12/9/2013 | 12/30/2013 | | DONE |
Christina Prado
|
|
|
complete 12-30-13
|
Print Statement | | | 12/30/2013 | | DONE |
Christina Prado
|
|
|
|
First Notice | | 11/22/2013 | 11/29/2013 | | DONE |
Christina Prado
|
|
|
|
Permanent Occupancy | | | 11/12/2013 | | DONE |
Tisha Gallop
|
|
|
|
BLD-Final | 10/31/2013 | 11/1/2013 | 11/1/2013 | P | PASS |
Mike Jordan
|
|
|
mike Phone #: ###-####. Ok for perm occ.
|
FIRE-Final Inspection | 10/31/2013 | 11/1/2013 | 10/31/2013 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
BLD-Final | 9/19/2013 | 9/20/2013 | 9/20/2013 | P | PART |
Mike Jordan
|
|
|
Mike Phone #: ###-####. ok to occupy service bay expansion.
|
FIRE-Final Inspection | 9/19/2013 | 9/20/2013 | 9/20/2013 | A | CANC |
Troy Cobbley
|
|
|
A partial already given for these areas. Waiting for fire alarm to be finished.
|
FIRE-Final Inspection | 9/17/2013 | 9/17/2013 | 9/17/2013 | P | PART |
Troy Cobbley
|
|
|
Life safety in the Service Bay expansion is passed.
|
FIRE-Final Inspection | 8/29/2013 | 8/30/2013 | 8/30/2013 | A | PART |
Troy Cobbley
|
|
|
The fire doors in the Lube Bay and the new Service Shop passed inspection. Links are on both sides of the wall and at the deck.
|
BLD-Final | 8/27/2013 | 8/28/2013 | 8/28/2013 | A | PART |
Mike Jordan
|
|
|
Mike Phone #: ###-####. Temp. final on lube and wash only.
|
FIRE-Final Inspection | 8/27/2013 | 8/27/2013 | 8/27/2013 | P | PART |
Troy Cobbley
|
|
|
Lube Bay and Car Wash life safety complete. The fire door between the Lube Bay and the existing shop area shall remain locked until door has been tested and passed. As of now there are no "links" for activation installed on both sides of the wall at the roof deck as required in NFPA 80.
|
Zoning Approval | 8/26/2013 | 8/26/2013 | 8/26/2013 | | DONE |
Andrea Tuning
|
|
|
|
PubWorks Occupancy Approval | 8/26/2013 | 8/26/2013 | 8/26/2013 | | DONE |
Tiffany Lowery
|
|
|
|
FIRE-Final Inspection | 8/22/2013 | 8/23/2013 | 8/23/2013 | P | PART |
Troy Cobbley
|
|
|
todays inspection was for the Lube Bay and the Service Shop expansion. The life safety will be complete in the Lube Bay when an additional fire extinguisher is provided in the pit and the car wash and the fire door linkages have been installed and tested. The Service Shop life safety needs the fire doors addressed and exit signs, emergency lights and exit discharge lighting provided. This is based on the occupant load exceeding 29 people. See IFC table 1021.2, and 1006.1.
The Lexus drive through is complete as well and can be used.
|
BLD-Framing/Rough-in | 7/19/2013 | 7/19/2013 | 7/19/2013 | P | CANC |
Tom Arcoraci
|
|
|
|
BLD-Framing/Rough-in | 7/18/2013 | 7/19/2013 | 7/19/2013 | A | PASS |
Tom Arcoraci
|
|
|
mike Phone #: ###-####
|
BLD-Other | 6/13/2013 | 6/13/2013 | 6/13/2013 | P | PART |
Mike Jordan
|
|
|
grouting at 1:30 - masonary grouting - Mike Phone #: ###-####. top of wall west wall for west shop addition. Special inector on site. Work in progress.
|
BLD-Other | 6/7/2013 | 6/7/2013 | 6/7/2013 | P | NR |
Mike Jordan
|
|
|
No masonry today.
|
BLD-Other | 6/5/2013 | 6/5/2013 | 6/5/2013 | P | PART |
Mike Jordan
|
|
|
masonary grout//Mike Phone #: ###-####. Work in progress, 16ft. to 20ft. elevation for shop expansion. Special inspector on site.
|
BLD-Other | 6/4/2013 | 6/5/2013 | 6/5/2013 | A | CANC |
Mike Jordan
|
|
|
MOved to PM
|
BLD-Conference | 6/4/2013 | 6/4/2013 | 6/4/2013 | P | DONE |
Mike Jordan
|
|
|
On site to check on job progress. Noted that lube center is erected and shop expansion is nearly 3/4 erected. Also noted that no inspections were scheduled. Did note that all work has been inspected by special inspection. Noted to contractor that he is still required to schedule inspections with the building dept. While on site walk through lube expansion and observed grout placement on shop expansion from 12ft to 16ft. elevation. Also reviewed all special inspection reports to date.
|
BLD-Footing | 3/7/2013 | 3/8/2013 | 3/8/2013 | A | DEFR |
Mike Jordan
|
|
|
gary - pouring at 10:30 Phone #: ###-####. Mti on site.
|
Permit Ready to Issue | | | 12/10/2012 | | DONE |
Tisha Gallop
|
|
|
|
Issue PAID IN FULL permit | | | 12/10/2012 | | DONE |
Tisha Gallop
|
|
|
|
Print Occupancy Form | | | 12/10/2012 | | DONE |
Tisha Gallop
|
|
|
|
Plan assigned to (JCM) | 12/6/2012 | | 12/7/2012 | | PASS |
John Menard
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/7/2012 | | DONE |
John Menard
|
|
|
|
Telephone call | | | 12/7/2012 | | DONE |
|
|
|
contractor bringing in revised value
|
Routing - PLUMBING | 12/6/2012 | | 12/6/2012 | | PASS |
Daryl Spivey
|
|
|
Per plans and 2003 UPC.
|
Routing - PUBLIC WORKS | 12/6/2012 | | 12/6/2012 | | PASS |
Connie Baumgartner
|
|
|
|
Routing PW Environmental | 12/6/2012 | | 12/6/2012 | | PASS |
Walt Baumgartner
|
|
|
|
Extend Review Timeline | | | 12/4/2012 | | DONE |
Christina Prado
|
|
|
|
Telephone call | | | 11/26/2012 | | DONE |
Christina Prado
|
|
|
Spoke with Dave regarding the upcoming expiration date, was advised the message was sent to the GC and permit pick up should be soon. Will check back in 4 business days (11/30/12)
|
Expiration Notice | 11/13/2012 | 12/5/2012 | 11/13/2012 | | DONE |
Christina Prado
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/24/2012 | | DONE |
John Menard
|
|
|
|
Plan assigned to (JCM) | 6/12/2012 | | 7/24/2012 | | PASS |
John Menard
|
|
|
|
Plan Reviewer's activity | | | 7/20/2012 | | PASS |
John Menard
|
|
|
Reviewed and approved structural and nonstructural revisions. JCM
|
Plan resubmittals received | | | 7/18/2012 | | DONE |
John Menard
|
|
|
|
Route to Impact Fee Review | 6/12/2012 | 6/15/2012 | 7/17/2012 | | PASS |
Cindy M. Gould
|
|
|
|
1st review completed | | | 7/17/2012 | | FAIL |
John Menard
|
|
|
|
Routing - FIRE | 7/9/2012 | | 7/9/2012 | | PASS |
Scott Arellano
|
|
|
Attached Plan Review report to plans.
|
Routing - PUBLIC WORKS | 6/12/2012 | | 7/3/2012 | | PASS |
Beverly Mountain
|
|
|
|
Routing - PLAN CHECK | 6/12/2012 | | 7/2/2012 | | FAIL |
John Menard
|
|
|
|
Routing Off Site - STRUCTURAL | 6/12/2012 | | 6/20/2012 | | FAIL |
John Menard
|
|
|
|
Routing PW Drainage | 6/19/2012 | | 6/19/2012 | | PASS |
Brian Murphy
|
|
|
|
Routing - PLUMBING | 6/12/2012 | | 6/18/2012 | | PASS |
Daryl Spivey
|
|
|
Change venting on flammable interceptor tanks. Delete upstream vent and vent both flammable interceptors tanks separerately from sanitary waste vent lines.
|
Routing PW Environmental | 6/14/2012 | | 6/14/2012 | | PASS |
Walt Baumgartner
|
|
|
|
Routing - PLANNING Land Div | 6/12/2012 | | 6/13/2012 | | PASS |
Dave Abo
|
|
|
Parcel over 5 acres in size.
|
Routing PW Sewer Rating | 6/13/2012 | | 6/13/2012 | | PASS |
Connie Baumgartner
|
|
|
|
Payment Received | | | 6/12/2012 | | DONE |
|
|
|
Payment received via Govolutions
|
Routing - Design Review | 6/12/2012 | | 6/12/2012 | | PASS |
Andrea Tuning
|
|
|
|
Telephone call | | | 6/12/2012 | | DONE |
Christina Prado
|
|
|
Sent email for intake fees to be paid
|
Pending Assignment by JCM | 6/12/2012 | | 6/12/2012 | | DONE |
John Menard
|
|
|
|
Routing - Addressing | 6/12/2012 | | 6/12/2012 | | PASS |
Terry Records
|
|
|
|
Routing - Erosion and Sediment | 6/12/2012 | | 6/12/2012 | | PASS |
Clint A Smith
|
|
|
ESC12-00579 plan approved with additional conditions attached to the permit.
|
Intake Approval | | | 6/11/2012 | | PASS |
John Menard
|
|
|
|
Intake Approval | | | 6/11/2012 | | FAIL |
John Menard
|
|
|
|
Application received | | | 6/8/2012 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 8 2012 8:01AM
|