BLD-Final | 4/13/2016 | 4/13/2016 | 4/13/2016 | P | PASS |
Mike Jordan
|
|
|
|
DOC - Permit Finaled | 4/13/2016 | 4/13/2016 | 4/13/2016 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Foundation | 7/9/2012 | 7/10/2012 | 7/10/2012 | A | PASS |
Mike Jordan
|
|
|
DANE Phone #: ###-####. Bldg 11, perimeter stem walls and column pedestals ok. Also received RFI from engineer noting only 2 #4 horizontals in stemwalls.
|
BLD-Footing | 7/5/2012 | 7/6/2012 | 7/6/2012 | P | PART |
Jim Sly
|
|
|
dane Phone #: ###-#### All re-inforcement in place and OK....Appears no special insp req...but unable to reach Eng of record to verify design of concrete 2500 or less PSI
|
Inspection Record Card- Bld | | | 6/13/2012 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 6/13/2012 | | DONE |
Christina Prado
|
|
|
|
Issue PAID IN FULL permit | | | 6/13/2012 | | DONE |
Christina Prado
|
|
|
|
(F) Reprint permit | | | 6/13/2012 | | DONE |
Christina Prado
|
|
|
|
Plan assigned to (DRS) | 6/12/2012 | 6/12/2012 | 6/12/2012 | | PASS |
Dan Stuart
|
|
|
|
Routing - PLAN CHECK | 6/12/2012 | | 6/12/2012 | | PASS |
Dan Stuart
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/12/2012 | | PASS |
|
|
|
|
1st review completed | | | 6/12/2012 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 6/12/2012 | | DONE |
Christina Prado
|
|
|
|
First Notice | 4/13/2016 | 4/13/2016 | | | |
Mike Jordan
|
|
|
|
Application received | | 6/11/2012 | | | |
|
|
|
|