Zoning Approval | 1/10/2013 | 1/10/2013 | 1/10/2013 | | DONE |
Cody Riddle
|
|
|
|
Permanent Occupancy | | | 1/10/2013 | | DONE |
Christina Prado
|
|
|
|
BLD-Final | 1/8/2013 | 1/9/2013 | 1/9/2013 | P | PASS |
Jim Storey
|
|
|
bobby Phone #: ###-#### final ok no card on site.
|
FIRE-Final Inspection | 1/8/2013 | 1/9/2013 | 1/9/2013 | A | PASS |
Forrest France
|
|
|
Correction items verified for completion. Fire life safety passed.
|
FIRE-Final Inspection | 1/7/2013 | 1/8/2013 | 1/8/2013 | A | FAIL |
Forrest France
|
|
|
Refer to items number 4, 7 and 10 on the fire code review notes for details regarding corrections.
|
BLD-Final | 1/4/2013 | 1/8/2013 | 1/8/2013 | P | NR |
Jim Storey
|
|
|
the plans will be in 2284 // Bobby Phone #: ###-####
|
FIRE-Sprinkler Rough-in | 12/10/2012 | 12/10/2012 | 12/10/2012 | A | PART |
Forrest France
|
|
|
Fire sprinkler rough-in approved for ceiling cover.
|
BLD-Energy code compliance | 11/5/2012 | 11/5/2012 | 11/5/2012 | P | PASS |
Jim Storey
|
|
|
|
BLD-Framing/Rough-in | 11/5/2012 | 11/5/2012 | 11/5/2012 | P | PASS |
Jim Storey
|
|
|
bobby Phone #: ###-####
|
BLD-Energy code compliance | 11/1/2012 | 11/2/2012 | 11/2/2012 | A | FAIL |
Jim Storey
|
|
|
Bobby Phone #: ###-#### complet firewalls
|
BLD-Framing/Rough-in | 10/29/2012 | 10/30/2012 | 10/30/2012 | P | PART |
Mike Jordan
|
|
|
Bobby Phone #: ###-####. Finish fire stopping, install lateral bracing bper truss engineering and fire blocking. ok to insulate.
|
BLD-Conference | 10/18/2012 | 10/19/2012 | 10/19/2012 | P | PASS |
Jim Storey
|
|
|
fire wall exterior of north fire wall ok to cover.
|
BLD-Other | 10/17/2012 | 10/18/2012 | 10/18/2012 | A | NR |
Jim Storey
|
|
|
late am please//fire wall insp//Bobby Phone #: ###-####
|
BLD-Framing/Rough-in | 10/16/2012 | 10/16/2012 | 10/16/2012 | P | NR |
Jim Storey
|
|
|
Fire wall - Bobby Phone #: ###-####
|
BLD-Wall Bracing | 10/15/2012 | 10/15/2012 | 10/15/2012 | P | PASS |
Jim Storey
|
|
|
bobby Phone #: ###-####
|
BLD-Footing | 8/30/2012 | 8/31/2012 | 8/31/2012 | A | PASS |
Jim Storey
|
|
|
Chris Phone #: ###-####
|
OVERRIDE | | | 8/27/2012 | | |
|
|
|
|
Plan assigned to (SRZ) | 6/18/2012 | 6/18/2012 | 8/27/2012 | | PASS |
Sam Zahorka
|
|
|
1st review completed. Corrections needed.
2nd plan review completed. Corrections needed.
|
Issue PAID IN FULL permit | | | 8/27/2012 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 8/24/2012 | | 8/27/2012 | | PASS |
Sam Zahorka
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/27/2012 | | DONE |
Sam Zahorka
|
|
|
|
Print Occupancy Form | | | 8/27/2012 | | DONE |
|
|
|
|
Telephone call | | | 8/27/2012 | | DONE |
Christina Prado
|
|
|
Called Todd to advise permits are ready
|
Permit Ready to Issue | | | 8/27/2012 | | DONE |
Christina Prado
|
|
|
|
Routing - PLAN CHECK | 8/9/2012 | | 8/24/2012 | | PASS |
Sam Zahorka
|
|
|
|
Routing - PLUMBING | 8/24/2012 | | 8/24/2012 | | PASS |
Bill VanDegrift
|
|
|
general sizing and routing approved install per 2003 upc
|
Routing - FIRE | 8/24/2012 | | 8/24/2012 | | PASS |
Scott Arellano
|
|
|
Attached review comments to plans.
|
Plan resubmittals received | | | 8/22/2012 | | |
|
|
|
Received 1 copy of response letter from Greg Denmark, 1 copy of of structural calcs for Shear wall, 3 copies of compliance certificate for unit 9, for unit 10, and for unit 11, 2 copies of sheets 6, 10, P1 and taken to Sam Zahorka//BAS
|
Routing - PLAN CHECK | 7/13/2012 | | 8/9/2012 | | FAIL |
Sam Zahorka
|
|
|
2nd plan review completed. Corrections needed.
|
Plan resubmittals received | | | 7/30/2012 | | |
|
|
|
Received 1 cover transmittal, 2 copies of sheets CS, 1,2,3,4,5,6,7,8,9,10,11,12 and taken to Sam Zahorka
|
Meeting | | | 7/23/2012 | | DONE |
Sam Zahorka
|
|
|
Meeting with the designers, and contractor to discuss Building plan review corrections. Explained comments/corrections and offered solutions. Waiting for resubmittals to be resubmitted for 2nd plan review.
|
Telephone call | | | 7/19/2012 | | DONE |
Sam Zahorka
|
|
|
Spoke with the residential designer Todd Henry. He never received corrections. Emailed corrections to him again. Answered some of his questions concerning needed coorections. Asked him to schedule a meeting to discuss corrections in detail. Waiting for him to call back and schedule the meeting.
|
Meeting | | | 7/19/2012 | | PEND |
Sam Zahorka
|
|
|
Meeting scheduled for Monday July, 23rd to discuss needed building plan review corrections.
|
Route to Impact Fee Review | 6/18/2012 | 6/21/2012 | 7/17/2012 | | PASS |
Cindy M. Gould
|
|
|
|
Routing - FIRE | 7/10/2012 | | 7/13/2012 | | FAIL |
Scott Arellano
|
|
|
Emailed resubmittal items to Architect.
|
1st review completed | | | 7/13/2012 | | FAIL |
|
|
|
Failed Fire, Plumbing, and Plan Check
|
Routing - PLAN CHECK | 6/26/2012 | | 7/10/2012 | | FAIL |
Sam Zahorka
|
|
|
Corrections needed.
|
Routing - PLANNING | 6/25/2012 | | 6/26/2012 | | PASS |
Cody Riddle
|
|
|
cup05-00006
|
Routing - PLUMBING | 6/22/2012 | | 6/25/2012 | | FAIL |
Daryl Spivey
|
|
|
|
Routing - MECHANICAL | | | 6/25/2012 | | PASS |
Troy James
|
|
|
|
Routing - PUBLIC WORKS | 6/20/2012 | | 6/22/2012 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - Erosion and Sediment | 6/22/2012 | | 6/22/2012 | | PASS |
Clint A Smith
|
|
|
ESC12-00598 plan waiver approved with additional conditions attached to the permit.
|
Routing - Addressing | 6/20/2012 | | 6/20/2012 | | PASS |
Terry Records
|
|
|
|
Routing - PLANNING Land Div | 6/18/2012 | | 6/19/2012 | | PASS |
Todd Tucker
|
|
|
|
Application received | | 6/18/2012 | 6/18/2012 | | DONE |
|
|
|
|
Intake Approval | | | 6/18/2012 | | FAIL |
Sam Zahorka
|
|
|
See circled items on the submittal checklist.
|
Intake Approval | | | 6/18/2012 | | PASS |
Sam Zahorka
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 6/18/2012 | | DONE |
Alexandra L. DeYoung
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 6/18/2012 | | DONE |
Alexandra L. DeYoung
|
|
|
|
First Notice | | 1/20/2013 | | | |
|
|
|
|