BLD-Final | 9/9/2013 | 9/9/2013 | 9/16/2013 | P | DONE |
Tony Young
|
|
|
Was never called in for a final........People moved in 2 weeks ago..........ds
|
DOC - Permit Finaled | 9/16/2013 | 9/16/2013 | 9/16/2013 | P | PASS |
Tony Young
|
|
|
|
BLD-Final | 8/30/2013 | 9/3/2013 | 9/9/2013 | A | PEND |
Tony Young
|
|
|
Was never called in for a final........People moved in 2 weeks ago..........ds,, ok to live in,, waiting on roof venting
|
PubWorks Occupancy Approval | 8/2/2013 | 8/2/2013 | 8/2/2013 | | DONE |
Jason C. Taylor
|
|
|
Recieved engineers approval for grading and drainage. Project is approved for occupancy. Jason Taylor ###-####
|
BLD-Energy code compliance | 10/22/2012 | 10/23/2012 | 10/23/2012 | A | PASS |
Tony Young
|
|
|
Phone #: ###-#### >> Inspection requested via web by SHANE JAYO
|
BLD-Framing/Rough-in | 10/22/2012 | 10/22/2012 | 10/22/2012 | P | PASS |
Tony Young
|
|
|
Phone #: ###-#### >> Inspection requested via web by SHANE JAYO
|
BLD-Framing/Rough-in | 10/18/2012 | 10/19/2012 | 10/19/2012 | A | FAIL |
Tony Young
|
|
|
Phone #: ###-#### >> Inspection requested via web by SHANE JAYO,,, still some corrections to be made
|
BLD-Framing/Rough-in | 10/15/2012 | 10/16/2012 | 10/16/2012 | P | FAIL |
Tony Young
|
|
|
Phone #: ###-#### >> Inspection requested via web by SHANE JAYO,, correction posted,, can insulate if you desire
|
BLD-Framing/Rough-in | 10/12/2012 | 10/15/2012 | 10/15/2012 | P | CANC |
Tony Young
|
|
|
Shane Phone #: ###-#### Inspection cancelled from web by: SHANE JAYO
|
BLD-Other | 10/4/2012 | 10/4/2012 | 10/4/2012 | P | PART |
Tony Young
|
|
|
shane - fire rating Phone #: ###-####,, fire caulk elec light boxes,, all other soffits covered
|
BLD-Foundation | 8/17/2012 | 8/17/2012 | 8/17/2012 | P | PART |
Tony Young
|
|
|
joe Phone #: ###-####,, work in progress
|
BLD-Foundation | 8/16/2012 | 8/16/2012 | 8/16/2012 | P | CANC |
Tony Young
|
|
|
Joe Phone #: ###-####
|
BLD-Footing | 8/14/2012 | 8/15/2012 | 8/15/2012 | A | PART |
Tony Young
|
|
|
Chris Phone #: ###-####
|
PubWorks Subgrade Approval | 8/14/2012 | 8/14/2012 | 8/14/2012 | | DONE |
Terry Records
|
|
|
Footing subgrade approved
|
Issue PAID IN FULL permit | | | 8/10/2012 | | DONE |
Tisha Gallop
|
|
|
|
Plan assigned to (CDM) | 6/20/2012 | 6/20/2012 | 7/13/2012 | | PASS |
Carl D Madsen
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/13/2012 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 7/13/2012 | | DONE |
|
|
|
|
Telephone call | | | 7/13/2012 | | DONE |
Christina Prado
|
|
|
Called shane to advise fees due and RP/GC is needed prior to issuance
|
Permit Ready to Issue | | | 7/13/2012 | | DONE |
Christina Prado
|
|
|
|
Routing - PUBLIC WORKS GRADING | 7/6/2012 | | 7/11/2012 | | PASS |
Terry Records
|
|
|
|
Routing - PLAN CHECK | 6/27/2012 | | 7/6/2012 | | PASS |
Carl D Madsen
|
|
|
|
1st review completed | | | 7/6/2012 | | DONE |
|
|
|
Fail pending Grading and drainage. 7-7-12 CDM
|
Case Summary (BLD) | | | 7/6/2012 | | DONE |
|
|
|
|
Route to Impact Fee Review | 6/20/2012 | 6/25/2012 | 6/28/2012 | | PASS |
Cindy M. Gould
|
|
|
|
Routing - FIRE | 6/26/2012 | | 6/27/2012 | | PASS |
Scott Arellano
|
|
|
No comments.
|
Routing - Erosion and Sediment | 6/25/2012 | | 6/26/2012 | | PASS |
Clint A Smith
|
|
|
ESC12-00644 plan approved with additional conditions attached to the permit.
|
Routing - MECHANICAL | 6/22/2012 | | 6/25/2012 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 6/22/2012 | | 6/22/2012 | | PASS |
David Moser
|
|
|
approved as redlined; driveway shall be max 33 feet in front setback
|
Routing - PUBLIC WORKS | 6/20/2012 | | 6/22/2012 | | PASS |
Connie Baumgartner
|
|
|
|
Routing PW Grading-Hillside | 6/20/2012 | | 6/21/2012 | | FAIL |
Terry Records
|
|
|
Grading plan needs revisions, foundation plan does not indicate steps or wall and footing elevations
|
Routing - Addressing | 6/20/2012 | | 6/21/2012 | | PASS |
Terry Records
|
|
|
|
Application received | | 6/18/2012 | 6/20/2012 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 6/20/2012 | | DONE |
Alexandra L. DeYoung
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 6/20/2012 | | DONE |
Alexandra L. DeYoung
|
|
|
|
Intake Approval | | | 6/20/2012 | | PASS |
Alexandra L. DeYoung
|
|
|
|
BLD-Final | 8/2/2013 | 8/2/2013 | | P | |
Tony Young
|
|
|
shane Phone #: ###-####
|