BLD-Final | 7/18/2013 | 7/18/2013 | 7/18/2013 | P | PASS |
Tom Arcoraci
|
|
|
Please call 1/2 hr prior. Thanks Jim Phone #: ###-#### >> Inspection requested via web by James Larkin
|
DOC - Permit Finaled | 7/18/2013 | 7/18/2013 | 7/18/2013 | P | PASS |
Tom Arcoraci
|
|
|
|
FIRE-Final Inspection | 7/18/2013 | 7/18/2013 | 7/18/2013 | P | CANC |
Troy Cobbley
|
|
|
please call 1/2 hr prior. Thanks jim Phone #: ###-#### >> Inspection requested via web by James Larkin Inspection cancelled from web by: James Larkin
|
BLD-Framing/Rough-in | 3/8/2013 | 3/8/2013 | 3/8/2013 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### >> Inspection requested via web by James Larkin
|
BLD-Wall Bracing | 3/8/2013 | 3/8/2013 | 3/8/2013 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### >> Inspection requested via web by James Larkin
|
BLD-Framing/Rough-in | 3/4/2013 | 3/4/2013 | 3/4/2013 | P | NR |
Mike Jordan
|
|
|
Phone #: ###-#### >> Inspection requested via web by James Larkin
|
BLD-Wall Bracing | 10/19/2012 | 10/19/2012 | 10/19/2012 | A | FAIL |
Mike Jordan
|
|
|
Exterior sheer Phone #: ###-#### >> Inspection requested via web by James Larkin
|
BLD-Conference | 10/19/2012 | 10/19/2012 | 10/19/2012 | A | CANC |
Mike Jordan
|
|
|
Exterior Sheer Phone #: ###-#### >> Inspection requested via web by James Larkin Inspection cancelled from web by: James Larkin
|
BLD-Wall cover | 10/11/2012 | 10/11/2012 | 10/11/2012 | A | PASS |
Jim Sly
|
|
|
Firewall construction Phone #: ###-#### >> Inspection requested via web by James Larkin
|
BLD-Energy code compliance | 9/13/2012 | 9/14/2012 | 9/14/2012 | A | PASS |
Mike Jordan
|
|
|
Steve Phone #: ###-####. Rigid foam insulation interior side of stemwall under slab on grade.
|
OVERRIDE | | | 8/27/2012 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 8/27/2012 | | DONE |
Christina Prado
|
|
|
|
Permit Ready to Issue | | | 8/27/2012 | | DONE |
|
|
|
|
Plan assigned to (CDM) | 6/20/2012 | 6/20/2012 | 8/24/2012 | | PASS |
Carl D Madsen
|
|
|
|
Routing - PLAN CHECK | 8/24/2012 | | 8/24/2012 | | PASS |
Carl D Madsen
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/24/2012 | | |
|
|
|
|
Case Summary (BLD) | | | 8/24/2012 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 8/24/2012 | | DONE |
|
|
|
|
Routing - MECHANICAL | 8/13/2012 | | 8/13/2012 | | PASS |
Troy James
|
|
|
|
1st review completed | | | 7/12/2012 | | FAIL |
|
|
|
|
Routing - PLAN CHECK | 6/26/2012 | | 7/12/2012 | | FAIL |
Carl D Madsen
|
|
|
|
Route to Impact Fee Review | 6/18/2012 | 6/21/2012 | 6/29/2012 | | PASS |
Cindy M. Gould
|
|
|
|
Routing - MECHANICAL | 6/22/2012 | | 6/26/2012 | | FAIL |
Troy James
|
|
|
emailed corrections to Canfield
|
Routing - PLANNING | 6/21/2012 | | 6/22/2012 | | PASS |
Sue Cummings
|
|
|
|
Routing - Addressing | 6/20/2012 | | 6/21/2012 | | PASS |
Terry Records
|
|
|
|
Routing - PUBLIC WORKS | 6/20/2012 | | 6/21/2012 | | PASS |
Beverly Mountain
|
|
|
|
Application received | | 6/18/2012 | 6/20/2012 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 6/20/2012 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 6/20/2012 | | DONE |
|
|
|
|
Intake Approval | | | 6/20/2012 | | PASS |
|
|
|
|
BLD-Wall cover | 11/1/2012 | 11/2/2012 | | P | |
Mike Jordan
|
|
|
Firewall construction Phone #: ###-#### >> Inspection requested via web by James Larkin
|