First Notice | | 12/29/2012 | 7/2/2015 | | DONE |
|
|
|
This permit finaled on the web by Jeremy Amar
|
Permanent Occupancy | | | 12/19/2012 | | DONE |
|
|
|
|
BLD-Final | 12/18/2012 | 12/18/2012 | 12/18/2012 | A | PASS |
Jim Storey
|
|
|
|
Zoning Approval Temp | 12/18/2012 | 12/18/2012 | 12/18/2012 | | PASS |
Josh Wilson
|
|
|
|
BLD-Final | 12/14/2012 | 12/17/2012 | 12/17/2012 | P | NR |
Jim Sly
|
|
|
KEVIN Phone #: ###-#### Need all fire finals and Zoning final.
|
FIRE-Final Inspection | 12/17/2012 | 12/17/2012 | 12/17/2012 | P | PASS |
Forrest France
|
|
|
Fire life safety inspection completed satisfactory. Door closures adjusted as discussed.
|
FIRE-Final Inspection | 12/14/2012 | 12/14/2012 | 12/14/2012 | P | PART |
Forrest France
|
|
|
Noted door closures in need of adjustment, project related fire sprinkler and alarm permits yet to be finaled.
|
BLD-Final | 12/14/2012 | 12/14/2012 | 12/14/2012 | P | NR |
Jim Storey
|
|
|
KEVIN Phone #: ###-####
|
FIRE-Final Inspection | 12/4/2012 | 12/4/2012 | 12/4/2012 | P | NR |
Forrest France
|
|
|
Pending project finishes
|
FIRE-Final Inspection | 12/4/2012 | 12/4/2012 | 12/4/2012 | A | DONE |
Forrest France
|
|
|
On site conference with contractor regarding conditions for fire life safety final approval.
|
FIRE-Sprinkler Rough-in | 11/20/2012 | 11/20/2012 | 11/20/2012 | A | PART |
Forrest France
|
|
|
Overhead fire sprinkler work okay to cover.
|
BLD-Other | 11/19/2012 | 11/19/2012 | 11/19/2012 | P | PASS |
Jim Storey
|
|
|
PAT- after 2 pm if possible Phone #: ###-####
|
BLD-Other | 11/8/2012 | 11/9/2012 | 11/9/2012 | A | PASS |
Jim Storey
|
|
|
RC1 channel insp//Pat Phone #: ###-####
|
BLD-Energy code compliance | 11/5/2012 | 11/6/2012 | 11/6/2012 | A | PASS |
Jim Storey
|
|
|
Pat Phone #: ###-####
|
BLD-Framing/Rough-in | 11/1/2012 | 11/2/2012 | 11/2/2012 | A | PART |
Jim Storey
|
|
|
Please call ahead - Pat Phone #: ###-#### fire stop spk line/ blk joist at closet/ fire stop at common wall tv and romex
|
BLD-Framing/Rough-in | 10/15/2012 | 10/16/2012 | 10/16/2012 | A | PART |
Jim Storey
|
|
|
entry sheet rock fire wall inspection please-Pat Phone #: ###-#### exterior ok
|
BLD-Wall Bracing | 10/4/2012 | 10/4/2012 | 10/4/2012 | A | PASS |
Jim Storey
|
|
|
|
BLD-Footing | 8/31/2012 | 8/31/2012 | 8/31/2012 | P | PASS |
Jim Storey
|
|
|
dane Phone #: ###-####
|
Issue PAID IN FULL permit | | | 8/24/2012 | | DONE |
Barbara Stitt
|
|
|
|
Route to Impact Fee Review | 8/22/2012 | 8/27/2012 | 8/23/2012 | | PASS |
Cindy M. Gould
|
|
|
|
Telephone call | | | 8/23/2012 | | DONE |
Christina Prado
|
|
|
called Greg to advise permit is ready and RP is required
|
Permit Ready to Issue | | | 8/23/2012 | | DONE |
Christina Prado
|
|
|
|
Print Occupancy Form | | | 8/21/2012 | | DONE |
Barbara Stitt
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/17/2012 | | DONE |
Sam Zahorka
|
|
|
|
Plan assigned to (SRZ) | 7/3/2012 | | 8/17/2012 | | PASS |
Sam Zahorka
|
|
|
1st review completed. Waiting for corrections.
|
Routing - MECHANICAL | 8/15/2012 | | 8/16/2012 | | PASS |
Troy James
|
|
|
|
Routing - PLAN CHECK | 8/7/2012 | | 8/15/2012 | | PASS |
Sam Zahorka
|
|
|
|
Plan resubmittals received | | | 8/7/2012 | | |
|
|
|
Received 1 response transmittal (3 pages), 3 copies of sheets A-001, A-101, A-103, A-107, A-108, S-101, S-102, S-103, S-104, S-105, S-106, S-107, S-109, S-110 and taken to Sam Zahorka
|
Routing - FIRE | 7/31/2012 | | 8/7/2012 | | PASS |
Scott Arellano
|
|
|
Attached comments to plans.
|
1st review completed | | | 8/7/2012 | | FAIL |
|
|
|
Failed Mechanical and IBC Plan Check
|
Routing - PLAN CHECK | 7/19/2012 | | 7/30/2012 | | FAIL |
Sam Zahorka
|
|
|
|
Routing - MECHANICAL | 7/11/2012 | | 7/19/2012 | | FAIL |
Troy James
|
|
|
emailed corrections to Alley
|
Routing - PLUMBING | 7/9/2012 | | 7/11/2012 | | PASS |
Daryl Spivey
|
|
|
Install a dcva backflow and per plans and 2003 UPC
|
Routing - Erosion and Sediment | 7/6/2012 | | 7/9/2012 | | PASS |
Clint A Smith
|
|
|
ESC12-00678 plan approved with additional conditions attached to the permit.
|
Routing - PUBLIC WORKS | 7/5/2012 | | 7/6/2012 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - PLANNING | 7/6/2012 | | 7/6/2012 | | PASS |
Josh Wilson
|
|
|
|
Routing - Addressing | 7/5/2012 | | 7/5/2012 | | PASS |
April Wing
|
|
|
For Ste Numbers see PW Documents
|
Routing - PLANNING Land Div | 7/2/2012 | | 7/3/2012 | | PASS |
Todd Tucker
|
|
|
|
Pending Assignment by JCM | 7/2/2012 | | 7/3/2012 | | DONE |
John Menard
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 7/2/2012 | | DONE |
Christina Prado
|
|
|
|
Intake Approval | | | 7/2/2012 | | PASS |
Sam Zahorka
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 7/2/2012 | | DONE |
Christina Prado
|
|
|
|
Application received | | 7/2/2012 | | | |
|
|
|
|