Information based on query as of Tuesday, July 16, 2024.
Permit Information
Permit NumberBLD12-01771
StatusFinaled
Name THE BOISE HOTEL & CONFERENCE CENTER
Site Address 3300 S VISTA AVE
Project NameBOISE HOTEL & CONFERENCE CENTE
Customer Number 
ePlanReviewNo
Description
**(BOISE HOTEL & CONFERENCE CENTER)** Application for inspection to determine requirements for issuance of a Certificate of Occupancy for a 76,632 sq ft existing hotel. This space was previously occupied by "Holiday Inn". NO NEW WORK IS AUTHORIZED UNDER THIS PERMIT. There will be no change to the occupancy. **TLW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Case Summary (BLD)  8/26/2014 DONE
BLD-Final8/15/20128/16/20128/16/2012PPASS
DetailsJim Storey
Allen=Please call prior to inspection Phone #: ###-####
Permanent Occupancy  8/16/2012 DONE
BLD-Final7/27/20127/30/20127/30/2012PPART
DetailsJim Storey
Allen Phone #: ###-#### need smoke seals on doors/ replace door out bldg with out glazing to meet 20 min.
FIRE-Final Inspection7/25/20127/26/20127/27/2012APASS
DetailsForrest France
Correction items verified for completion. Fire life safety passed.
FIRE-Final Inspection7/24/20127/24/20127/25/2012PNR
DetailsForrest France
Pending corrections.
FIRE-Final Inspection7/20/20127/23/20127/23/2012AFAIL
DetailsForrest France
Noted correction items include; post door to remain unlocked signage at the west main entry/exit doors and remove keyed locking hardware at the first set of vestibule doors, provide approved lever set at the kitchen exit door, relocate fire extinguisher at the second level executive offices to a normal path of travel, post signage at the pool gates, remove keyed lock at the excersise room, post building address numbers as discussed, repair EM lights at four locations. See also list of general requirements attatched to the permit documents for plan review conditions.
BLD-Final7/20/20127/23/20127/23/2012PDEFR
DetailsJim Storey
Lily Phone #: ###-#### fire c/n listforest call andsaid that they would recall upon completition
Plan assigned to (TLW)7/5/2012 7/20/2012 PASS
DetailsTim L. Woodard
Routing - PLAN CHECK7/20/2012 7/20/2012 PASS
DetailsTim L. Woodard
PLANS/APPL TAKEN TO FRONT DESK  7/20/2012 DONE
DetailsTim L. Woodard
Case Summary (BLD)  7/20/2012 DONE
DetailsTim L. Woodard
Permit Ready to Issue  7/20/2012 DONE
DetailsTisha Gallop
Print Occupancy Form  7/20/2012 DONE
DetailsTisha Gallop
Issue PAID IN FULL permit  7/20/2012 DONE
DetailsChristina Prado
Routing - PLAN CHECK7/5/2012 7/17/2012 FAIL
DetailsTim L. Woodard
Need more information on conference rooms. TLW
1st review completed  7/17/2012 DONE
DetailsTim L. Woodard
Plans ACCEPTED BY PLAN TECH  7/5/2012 DONE
DetailsChristina Prado
Recd Pcfee & Taken To Pln CK  7/5/2012 DONE
DetailsChristina Prado
Application received 7/5/2012