Print Statement | | | 4/8/2014 | | DONE |
Barbara Stitt
|
|
|
|
First Notice | | 3/7/2014 | 4/1/2014 | | DONE |
|
|
|
Faxed 4-1-14
|
Agreement of Future work | 8/1/2012 | 8/1/2013 | 3/6/2014 | | |
Jason Blais
|
|
|
Upgrade Agreement attached to this case. Permit BLD12-01772.
3/6/14 - Work under the Upgrade Agreement has been completed. A copy of the recoreded Notice of Compliance is attached to this case.
|
Case Summary (BLD) | | | 2/25/2014 | | |
|
|
|
|
Permanent Occupancy | | | 2/25/2014 | | DONE |
Christina Prado
|
|
|
|
BLD-Final | 2/11/2014 | 2/12/2014 | 2/12/2014 | A | PASS |
Tom Arcoraci
|
|
|
Terry or Dorian Phone #: ###-#### ok after zoning signs off
|
Zoning Approval | 2/12/2014 | 2/12/2014 | 2/12/2014 | | DONE |
Sarah Schafer
|
|
|
|
FIRE-Final Inspection | 2/10/2014 | 2/11/2014 | 2/11/2014 | A | PASS |
Troy Cobbley
|
|
|
life safety passed
|
Plan Reviewer's activity | | | 1/2/2014 | | |
|
|
|
Must re-review this project as it was originalyy reviewed as a sprinkled and alarmed build which it is not. CDH
|
(F) Reprint permit | | | 12/31/2013 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 12/31/2013 | | DONE |
|
|
|
|
Plan assigned to (TLW) | 12/16/2013 | | 12/24/2013 | | PASS |
Tim L. Woodard
|
|
|
|
Routing - PLAN CHECK | 12/23/2013 | | 12/24/2013 | | PASS |
Tim L. Woodard
|
|
|
|
Print Occupancy Form | | | 12/24/2013 | | DONE |
|
|
|
|
Telephone call | | | 12/24/2013 | | DONE |
Christina Prado
|
|
|
called Dorian to advise permit is ready for pick up and gave fees due
|
Routing - FIRE | 12/20/2013 | | 12/23/2013 | | PASS |
Craig D. Hanson
|
|
|
See Fire Plan Review for Hazmat requirements
|
Case Summary (BLD) | | | 12/20/2013 | | DONE |
Tim L. Woodard
|
|
|
|
Routing - PLAN CHECK | 12/16/2013 | | 12/20/2013 | | PASS |
Tim L. Woodard
|
|
|
|
Plan Modification Accepted | | | 12/16/2013 | | DONE |
Christina Prado
|
|
|
Received plan modification application for changes made to "Warehouse 11". Received two sets of revised plan sheets marked A2.0, A2.2, A2.3 & A2.4; Taken to Tim for review
|
FIRE-Final Inspection | 10/18/2013 | 10/21/2013 | 10/21/2013 | P | FAIL |
Troy Cobbley
|
|
|
Repaair the two exit sign/emergency lights as noted and discuss with plan review if there is a need to resubmit plans showing the two small rooms, one of which cntains two 50 gallon drums of flammable liquids.
|
BLD-Final | 10/16/2013 | 10/17/2013 | 10/17/2013 | A | PASS |
Tom Arcoraci
|
|
|
Terry Phone #: ###-####
|
Plan Reviewer's activity | | | 7/29/2013 | | DONE |
Jason Blais
|
|
|
Dorian called indicating work is still occurring and will be completed fairly soon but not quite by the date of the Upgrade Agreement. Maybe a month longer or so. This is acceptable as work has progressed nicely and is almost completed. No need to modify the agreement at this point.
|
FIRE-Final Inspection | 5/16/2013 | 5/20/2013 | 5/20/2013 | A | PART |
Troy Cobbley
|
|
|
A temporary for the life safety is approved for the east half of the building per letter from Jason.
|
Plan Reviewer's activity | | | 5/16/2013 | | DONE |
Jason Blais
|
|
|
East side of building upgraded. Temporary occupancy can be granted on this side. If leased to another tenant, that tenant shall apply for a permit to obtain their own Certificate of Occupancy.
|
BLD-Final | 5/14/2013 | 5/15/2013 | 5/15/2013 | A | CANC |
Tom Arcoraci
|
|
|
|
BLD-Final | 5/13/2013 | 5/14/2013 | 5/14/2013 | P | PART |
Tom Arcoraci
|
|
|
east side ok for occupancy
|
BLD-Final | 5/10/2013 | 5/13/2013 | 5/13/2013 | P | DEFR |
Tom Arcoraci
|
|
|
terry Phone #: ###-####
|
FIRE-Final Inspection | 5/10/2013 | 5/13/2013 | 5/13/2013 | A | PART |
Troy Cobbley
|
|
|
Life safety for the east half of the building is passed. The work for the west half is not yet complete.
|
FIRE-Conference | 3/25/2013 | 3/26/2013 | 3/26/2013 | A | DONE |
Forrest France
|
|
|
On site conference with contractors regarding plan review red-line comments, fire extinguisher placement, premise identification, entrance gate, etc. A plan modification shoud be done to include the removal of one door between the east side offices and affected exiting.
|
FIRE-Conference | 3/19/2013 | 3/25/2013 | 3/25/2013 | A | DONE |
Forrest France
|
|
|
Regarding conditions for fire life safety approvals, scope of work, schedule, etc.
|
Zoning Approval | 3/21/2013 | 3/21/2013 | 3/21/2013 | | DONE |
Sarah Schafer
|
|
|
|
BLD-Framing/Rough-in | 3/11/2013 | 3/12/2013 | 3/12/2013 | A | PASS |
Tom Arcoraci
|
|
|
terry Phone #: ###-####
|
BLD-Framing/Rough-in | 11/26/2012 | 11/28/2012 | 11/28/2012 | A | PASS |
Tom Arcoraci
|
|
|
Terry Phone #: ###-#### ok to cover
|
BLD-Conference | 10/30/2012 | 10/30/2012 | 10/30/2012 | P | PASS |
Tom Arcoraci
|
|
|
|
Issue PAID IN FULL permit | | | 10/16/2012 | | DONE |
|
|
|
|
Plan assigned to (TLW) | 8/27/2012 | | 10/15/2012 | | PASS |
Tim L. Woodard
|
|
|
Sun Valley Marble - Reassigned to Tim Woodard
|
Routing - PLAN CHECK | 8/31/2012 | | 10/15/2012 | | PASS |
Tim L. Woodard
|
|
|
Approved with Redlines and a Plan Review Report. TLW
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/15/2012 | | DONE |
Tim L. Woodard
|
|
|
|
Case Summary (BLD) | | | 10/15/2012 | | DONE |
Tim L. Woodard
|
|
|
|
Print Occupancy Form | | | 10/15/2012 | | DONE |
Christina Prado
|
|
|
|
Permit Ready to Issue | | | 10/15/2012 | | DONE |
Tisha Gallop
|
|
|
|
Telephone call | | | 10/15/2012 | | DONE |
Tisha Gallop
|
|
|
called Dorian and told him permit is ready and fee.
|
Plan resubmittals received | | | 9/25/2012 | | |
|
|
|
9-25-12 received response and 2 copies of sheets A0.0,A0.1,A2.0,A2.1,A4.0 sent to Tim W
|
1st review completed | | | 8/31/2012 | | DONE |
Tim L. Woodard
|
|
|
|
Routing - FIRE | 8/30/2012 | | 8/31/2012 | | PASS |
Scott Arellano
|
|
|
No comments attached.
|
Routing - PLAN CHECK | 8/27/2012 | | 8/30/2012 | | FAIL |
Tim L. Woodard
|
|
|
Refer to plan review report. TLW
|
Plan assigned to (DRS) | 8/1/2012 | 8/1/2012 | 8/27/2012 | | DEFR |
Dan Stuart
|
|
|
Plans reassigned to Tim Woodard.
|
Routing - PLAN CHECK | 8/3/2012 | | 8/27/2012 | | DEFR |
Dan Stuart
|
|
|
Reassigned to Tim Woodard.
|
Routing - Design Review | 8/1/2012 | | 8/3/2012 | | PASS |
Sarah Schafer
|
|
|
Sarah Schafer
|
Pending Assignment by JCB | 7/31/2012 | | 8/1/2012 | | DONE |
Jason Blais
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 7/31/2012 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 7/31/2012 | | DONE |
|
|
|
|
Intake Approval | | | 7/31/2012 | | PASS |
Tim L. Woodard
|
|
|
|
Application received | | 7/5/2012 | | | |
|
|
|
|