Permit Information
Permit NumberBLD12-01818
StatusFinaled
Name CHAD BABCOCK (TEN REP)
Site Address 1030 W RIVER ST
Project NameJUMP TIME BOISE
Customer Number 
ePlanReviewNo
Description
(JUMP TIME BOISE) (10-9-12 PLAN MODIFICATION TO CHANGE THE DESIGN OF THE EXTERIOR RAMP AND TO DELETE THE EXTERIOR STAIRWAY FROM THE DESIGN.) The fire sprinkler system is used for building area increase. To convert an existing 11,555 square foot warehouse to a trampoline gym, play area, and party facility. Work is to include a restroom accessible to the disabled, upgrading 2 existing restrooms to be accessible to the disabled, interior nonbearing walls, millwork, an exterior double leaf door, a new exterior concrete stairway and ramp, and finishes. A 1,200 square foot mezzanine will be constructed. Mezzanine work includes concrete footings, steel columns, wood bearing walls, wood beams, wood floor joists, wood floor sheathing, an open stairway, and guards. Special inspection is required for concrete, anchors in concrete, welding, and epoxy anchors. Elevated walkways and stairways will be provided to access the trampolines. Elevated walkway work includes steel columns, steel joists, wood decking, and guards. The design for the elevated walkway is a deferred submittal item. Storage is not allowed below the elevated walkways. Skirting is required at the perimeter of the walkways to prevent access to the area below the walkways by the public. At least one transfer system accessible to the disabled is required for each elevated walkway to provide access to the trampolines for the disabled. The work is required to comply with the approved drawings, with the structural design, with the plan review report, and with all applicable codes and ordinances. The fire sprinkler system is required to comply with NFPA 13 as regulated by the Fire Department. **CJW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Print Statement  1/23/2013 DONE
First Notice 11/29/201212/3/2012 DONE
DetailsChristina Prado
mailed 12-4-12
BLD-Final11/19/201211/19/201211/19/2012PPASS
DetailsJim Storey
301 ok for final 425 signed card
Change Expiration Date Only  11/19/2012 DONE
DetailsBarbara Stitt
Permanent Occupancy  11/19/2012 DONE
DetailsBarbara Stitt
Temporary Occupancy10/26/20121/24/201310/26/2012 DONE
DetailsBarbara Stitt
BLD-Final10/25/201210/25/201210/25/2012PPART
DetailsDave Hannah
joe Phone #: ###-#### ok for temp occ needs a perm noslipe surface final spec report and passage door hardware on office door
BLD-Final10/23/201210/24/201210/24/2012ANR
DetailsJim Storey
Joe Phone #: ###-####
Zoning Approval10/24/201210/24/201210/24/2012 PASS
DetailsJosh Wilson
BLD-Final10/22/201210/23/201210/23/2012PFAIL
DetailsJim Storey
Joe Phone #: ###-#### si close out letter/ door hardware 2nd floor// sign on main exit/zoning sign off.
FIRE-Final Inspection10/22/201210/23/201210/23/2012APASS
DetailsForrest France
Fire life safety approved pending correct door hardware is installed at both mezzanine rooms and the fire sprinkler riser room- to be finished prior to structural final as discussed.
BLD-Footing10/11/201210/11/201210/12/2012PPASS
DetailsDave Hannah
joe Phone #: ###-####
CHANGE STATUS TO (ISS)  10/10/2012 DONE
DetailsTisha Gallop
picked up and paid for plan mod
OVERRIDE  10/9/2012  
Plan assigned to (CJW)9/25/20129/25/201210/9/2012 PASS
DetailsCarl Westfall
JUMP TIME BOISE - Plan modification for ext. ramp
Routing - Design Review10/5/2012 10/9/2012 PASS
DetailsJosh Wilson
OK- adequate parking lot dimensions remian with enlarged access ramp JGW 10-9-12
Routing - PLAN CHECK10/9/2012 10/9/2012 DONE
DetailsCarl Westfall
Routing completed.
Print Occupancy Form  10/9/2012 DONE
DetailsTisha Gallop
Telephone call  10/9/2012 DONE
DetailsChristina Prado
called Eric to advise permit is ready and gave fees due
BLD-Framing/Rough-in10/5/201210/5/201210/8/2012PPASS
DetailsDave Hannah
late pm//Joe Kennedy ###-#### (plan mod in for ADA ramp, not approved yet)
Override - Parcel Holds  10/5/2012  
Routing - PLAN CHECK10/2/2012 10/5/2012 PASS
DetailsCarl Westfall
2nd version of modified drawings approved
Plan resubmittals received  10/4/2012 DONE
DetailsChristina Prado
Received one set of engineering calcs for a ramp deck as well as two sets of plans marked A7.1; gave to Carl Westfall for further review
Routing - PLAN CHECK9/25/2012 10/2/2012 FAIL
DetailsCarl Westfall
Revisions required.
Plan Modification Accepted  9/25/2012  
Plan modification accepted to revise ADA ramp layout and construction materials. Sheet A7.1 and structural calcs were submitted with plan mod app and no change in value.
OVERRIDE  9/11/2012  
Route to Impact Fee Review8/31/20129/6/20129/11/2012 PASS
DetailsShauna Surgeon
Interior changes only, no external new square footage.
Plan assigned to (CJW)8/3/20128/3/20129/11/2012 PASS
DetailsCarl Westfall
JUMP TIME BOISE (20 days - Aug. 28)
Telephone call  9/11/2012 DONE
DetailsTisha Gallop
called David Glancy and told him permit is ready, fee, need GC/rce/form and RP.
Issue PAID IN FULL permit  9/11/2012 DONE
DetailsBarbara Stitt
Routing - PLAN CHECK9/8/2012 9/11/2012 PASS
DetailsCarl Westfall
Drawings approved after 3rd review.
PLANS/APPL TAKEN TO FRONT DESK  9/11/2012 DONE
Print Occupancy Form  9/11/2012 DONE
DetailsChristina Prado
Permit Ready to Issue  9/11/2012 DONE
DetailsTisha Gallop
Routing - PLAN CHECK9/5/2012 9/8/2012 FAIL
DetailsCarl Westfall
Completed the 2nd review. One item not resolved.
Plan resubmittals received  9/6/2012 DONE
DetailsChristina Prado
Received two sets of plans marked S1.1. Routed to Carl Westfall for further review
Routing - FIRE8/31/20128/31/20129/5/2012 PASS
DetailsScott Arellano
Attached comments to plans.
1st review completed  9/5/2012 FAIL
Failed plan check.
Plan resubmittals received  9/4/2012  
9-4-12 received 1 comment,1 response letter and 2 copies of sheets A0.1,A0.4,A1.1,A1.2,A3.1,S1.1 sent to Carl W.
Routing - PLAN CHECK8/9/2012 8/31/2012 FAIL
DetailsCarl Westfall
The IBC plan review was started on Aug 28 and was finished on Aug 31. Revised drawings and more information was required. See the plan review report.
Routing - Design Review8/8/2012 8/9/2012 PASS
DetailsJosh Wilson
Josh Wilson - CZC12-00152
Routing - PLUMBING8/7/2012 8/8/2012 PASS
DetailsBill VanDegrift
Per plans and 2003 UPC.
Routing - Erosion and Sediment8/6/2012 8/7/2012 PASS
DetailsKimberly M. Johnson
Waiver Request approved per conditions
Routing - PUBLIC WORKS  8/6/2012 PASS
Plan Reviewer's activity  8/3/2012 DONE
DetailsJason Blais
Emailed architect representative to contact ACHD for evaluation of any impact fees due. Written verification from ACHD needs to be provided to our Permit Counter prior to the building permit being issued.
Routing - Addressing8/3/2012 8/3/2012 PASS
DetailsApril Wing
Pending Assignment by JCB8/2/2012 8/3/2012 DONE
DetailsJason Blais
Application received 7/12/20128/2/2012 DONE
Intake Approval  8/2/2012 PASS
Plans ACCEPTED BY PLAN CHECK  8/2/2012 PASS
Recd Pcfee & Taken To Pln CK  8/2/2012 DONE
Plans ACCEPTED BY PLAN TECH  8/2/2012 DONE
Intake Approval  7/16/2012 FAIL