Second Notice | | 9/7/2013 | 10/4/2013 | | DONE |
|
|
|
|
First Notice | | 8/11/2013 | 8/28/2013 | | DONE |
Christina Prado
|
|
|
mailed 8-29-13
|
Permanent Occupancy | | | 8/1/2013 | | DONE |
Tisha Gallop
|
|
|
|
BLD-Final | 7/30/2013 | 7/31/2013 | 7/31/2013 | A | PASS |
Dave Hannah
|
|
|
burton Phone #: ###-####
|
BLD-Aging Inspection | 7/2/2013 | 7/2/2013 | 7/2/2013 | | PEND |
Dave Hannah
|
|
|
|
Temporary Occupancy | 5/6/2013 | 8/4/2013 | 5/6/2013 | | DONE |
Barbara Stitt
|
|
|
|
BLD-Final | 5/2/2013 | 5/3/2013 | 5/3/2013 | P | PART |
Dave Hannah
|
|
|
###-#### Mark Kline ok for temp occ but sink in break room needs tobe lowered to 34 inchs
|
FIRE-Final Inspection | 4/30/2013 | 5/2/2013 | 5/2/2013 | P | PASS |
Forrest France
|
|
|
Fire life safety okay to final- door hardware to be installed prior to structural final as discussed.
|
Print Occupancy Form | | | 4/23/2013 | | DONE |
Christina Prado
|
|
|
|
BLD-Framing/Rough-in | 4/16/2013 | 4/16/2013 | 4/17/2013 | P | PART |
Dave Hannah
|
|
|
cover insection-Adrian Phone #: ###-#### ok to cover ceiling grid
|
FIRE-Sprinkler Rough-in | 2/8/2013 | 2/8/2013 | 2/8/2013 | P | PART |
Forrest France
|
|
|
Overhead fire sprinkler work at the sheetrock ceilings is approved for cover. HVAC registers to stay a min. of 1' from pendent heads as discussed.
|
BLD-Framing/Rough-in | 2/5/2013 | 2/5/2013 | 2/6/2013 | P | PASS |
Dave Hannah
|
|
|
Burton Phone #: ###-####
|
Issue PAID IN FULL permit | | | 9/20/2012 | | DONE |
|
|
|
|
Plan assigned to (TLW) | 9/4/2012 | | 9/17/2012 | | PASS |
Tim L. Woodard
|
|
|
|
Routing - PLAN CHECK | 9/4/2012 | | 9/17/2012 | | PASS |
Tim L. Woodard
|
|
|
A modification to the plan was submitted to add 600 sq. ft. to the newly created space. Review did not change. The square footage was added to the permit. TLW
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/17/2012 | | DONE |
Tim L. Woodard
|
|
|
|
Print Occupancy Form | | | 9/17/2012 | | DONE |
Christina Prado
|
|
|
|
Telephone call | | | 9/17/2012 | | DONE |
|
|
|
spoke with burton permit ready fees given
|
Permit Ready to Issue | | | 9/17/2012 | | DONE |
|
|
|
|
Plan resubmittals received | | | 9/4/2012 | | DONE |
Tisha Gallop
|
|
|
received transmittal and two copies of revised cert of value and plan sheets a0.01, a2.11, a2.31, a5.10, a5.11; taken to Tim Woodard
|
Routing - Addressing | 7/16/2012 | | 7/30/2012 | | PASS |
Tim L. Woodard
|
|
|
Approved on routing sheet. TLW
|
Plan assigned to (TLW) | | | 7/30/2012 | | PASS |
Tim L. Woodard
|
|
|
|
Routing - PLAN CHECK | 7/17/2012 | | 7/30/2012 | | PASS |
Tim L. Woodard
|
|
|
Approved with plan review report and redlines. TLW
|
1st review completed | | | 7/30/2012 | | DONE |
Tim L. Woodard
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/30/2012 | | DONE |
Tim L. Woodard
|
|
|
|
Case Summary (BLD) | | | 7/30/2012 | | DONE |
Tim L. Woodard
|
|
|
|
Print Occupancy Form | | | 7/30/2012 | | DONE |
Barbara Stitt
|
|
|
|
Permit Ready to Issue | | | 7/30/2012 | | DONE |
Barbara Stitt
|
|
|
|
Telephone call | | | 7/30/2012 | | DONE |
Barbara Stitt
|
|
|
Left a message for Cheryl that permit is ready & fees due on 7-30-12 @ 4:00pm//BAS
|
Routing - PUBLIC WORKS | 7/16/2012 | | 7/17/2012 | | PASS |
Connie Baumgartner
|
|
|
|
Routing PW Sewer Rating | 7/16/2012 | | 7/17/2012 | | PASS |
Connie Baumgartner
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 7/16/2012 | | DONE |
Christina Prado
|
|
|
|
Intake Approval | | | 7/16/2012 | | PASS |
Tim L. Woodard
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 7/16/2012 | | DONE |
Christina Prado
|
|
|
|
Application received | | 7/16/2012 | | | |
|
|
|
|