DOC - Permit Finaled | | | 10/1/2018 | | DONE |
|
|
|
see building final passed by Dave Hannah
|
Temporary Occupancy | 7/20/2018 | 10/18/2018 | 7/20/2018 | | DONE |
Candy A. Nichols
|
|
|
as per Jason B. temp c of o good thru 12/26/18
|
Telephone call | | | 7/20/2018 | | DONE |
|
|
|
emailed Angie that someone expired the permits but they're in temp c of o status so not sure why-also let her know that the temp c of o's do expire on 7/22
|
CHANGE STATUS TO (ISS) | | | 7/20/2018 | | DONE |
|
|
|
as per Angie B-permit was expired by mistake by the inspector
|
DOC - Permit Expired | 7/18/2018 | 7/18/2018 | 7/18/2018 | P | PASS |
Dave Hannah
|
|
|
|
BLD-Aging Inspection | 7/13/2018 | 7/13/2018 | 7/18/2018 | | PEND |
Dave Hannah
|
|
|
|
Temporary Occupancy | 6/22/2018 | 9/20/2018 | 6/22/2018 | | DONE |
Candy A. Nichols
|
|
|
Jason Blais ok'd 30 day extension on temp c of o
|
Telephone call | | | 6/12/2018 | | DONE |
|
|
|
emailed Angie B that the temp c of o was about to expire
|
BLD-Aging Inspection | 4/23/2018 | 4/23/2018 | 4/24/2018 | | PEND |
Dave Hannah
|
|
|
|
Temporary Occupancy | 3/21/2018 | 6/19/2018 | 3/21/2018 | | DONE |
Candy A. Nichols
|
|
|
as per Jason B ok to change status from EXP to TMP c of o
|
DOC - Permit Expired | 2/20/2018 | 2/20/2018 | 2/20/2018 | P | CANC |
Dave Hannah
|
|
|
|
DOC - Permit Expired | 2/20/2018 | 2/20/2018 | 2/20/2018 | P | PASS |
Dave Hannah
|
|
|
|
BLD-Final | 2/20/2018 | 2/20/2018 | 2/20/2018 | A | PASS |
Dave Hannah
|
|
|
space not in use
|
BLD-Aging Inspection | 2/19/2018 | 2/19/2018 | 2/20/2018 | | PEND |
Dave Hannah
|
|
|
|
Temporary Occupancy | 1/19/2018 | 4/19/2018 | 1/19/2018 | | DONE |
Candy A. Nichols
|
|
|
Jason Blais ok'd extension for 90 days from 1/15/18
|
Telephone call | | | 1/3/2018 | | DONE |
|
|
|
called Mark to let know that the temp c of o is going to expire on the 1/18/18-left message on his cell
|
BLD-Aging Inspection | 12/18/2017 | 12/18/2017 | 12/19/2017 | | PEND |
Dave Hannah
|
|
|
|
BLD-Aging Inspection | 10/16/2017 | 10/16/2017 | 10/16/2017 | | PEND |
Dave Hannah
|
|
|
|
BLD-Aging Inspection | 8/16/2017 | 8/16/2017 | 8/22/2017 | | PEND |
Dave Hannah
|
|
|
|
Temporary Occupancy | 7/17/2017 | 10/15/2017 | 7/17/2017 | | DONE |
Candy A. Nichols
|
|
|
Jason Blais ok'd ext good for 180 days starting on 7/19/17
|
BLD-Aging Inspection | 6/5/2017 | 6/5/2017 | 6/5/2017 | | PEND |
Dave Hannah
|
|
|
|
BLD-Aging Inspection | 4/3/2017 | 4/3/2017 | 4/3/2017 | | PEND |
Dave Hannah
|
|
|
|
BLD-Aging Inspection | 1/30/2017 | 1/30/2017 | 2/1/2017 | | PEND |
Dave Hannah
|
|
|
|
Temporary Occupancy | 1/12/2017 | 4/12/2017 | 1/12/2017 | | DONE |
Candy A. Nichols
|
|
|
Jason B ok'd extension good threw 6-29-17
|
BLD-Aging Inspection | 11/28/2016 | 11/28/2016 | 11/28/2016 | | PEND |
Dave Hannah
|
|
|
|
BLD-Aging Inspection | 9/26/2016 | 9/26/2016 | 9/26/2016 | | PEND |
Dave Hannah
|
|
|
|
BLD-Aging Inspection | 7/27/2016 | 7/27/2016 | 7/29/2016 | | PEND |
Dave Hannah
|
|
|
|
BLD-Aging Inspection | 5/18/2016 | 5/18/2016 | 5/26/2016 | | PEND |
Dave Hannah
|
|
|
|
BLD-Aging Inspection | 3/7/2016 | 3/7/2016 | 3/11/2016 | | PEND |
Dave Hannah
|
|
|
|
BLD-Aging Inspection | 1/4/2016 | 1/4/2016 | 1/5/2016 | | PEND |
Dave Hannah
|
|
|
|
Temporary Occupancy | 1/4/2016 | 12/31/2016 | 1/4/2016 | | DONE |
Candy A. Nichols
|
|
|
|
BLD-Aging Inspection | 11/2/2015 | 11/2/2015 | 11/9/2015 | | PEND |
Dave Hannah
|
|
|
|
BLD-Aging Inspection | 8/3/2015 | 8/3/2015 | 8/3/2015 | | PEND |
Dave Hannah
|
|
|
|
BLD-Aging Inspection | 5/4/2015 | 5/4/2015 | 5/5/2015 | | PEND |
Dave Hannah
|
|
|
|
BLD-Aging Inspection | 3/2/2015 | 3/2/2015 | 3/2/2015 | | PEND |
Dave Hannah
|
|
|
|
BLD-Aging Inspection | 12/29/2014 | 12/29/2014 | 1/5/2015 | | PEND |
Dave Hannah
|
|
|
|
Telephone call | | | 12/23/2014 | | DONE |
Candy A. Nichols
|
|
|
Mark will send an email requesting an extension. He said it would be a temp CO until the JUMP project is complete.
|
BLD-Aging Inspection | 10/27/2014 | 10/27/2014 | 11/3/2014 | | PEND |
Dave Hannah
|
|
|
|
Temporary Occupancy | 10/13/2014 | 12/31/2015 | 10/13/2014 | | DONE |
Candy A. Nichols
|
|
|
As per Angie and Jason B, Temp CO good thru 12-31-15
|
Telephone call | | | 10/10/2014 | | DONE |
Candy A. Nichols
|
|
|
called about temp occ being expired-left message asking them to either call in a final or request and extension with Jason Blais
|
BLD-Aging Inspection | 8/25/2014 | 8/25/2014 | 8/26/2014 | | PEND |
Dave Hannah
|
|
|
|
BLD-Aging Inspection | 6/23/2014 | 6/23/2014 | 6/30/2014 | | PEND |
Dave Hannah
|
|
|
|
BLD-Aging Inspection | 4/23/2014 | 4/23/2014 | 4/24/2014 | | PASS |
Dave Hannah
|
|
|
|
BLD-Aging Inspection | 2/21/2014 | 2/21/2014 | 2/24/2014 | | PEND |
Dave Hannah
|
|
|
|
Change Expiration Date Only | | | 12/31/2013 | | DONE |
|
|
|
Per Jason Blais, signed document on BLD12-01894 giving temp occupancy until 12-31-15
|
BLD-Aging Inspection | 12/2/2013 | 12/2/2013 | 12/4/2013 | | PASS |
Dave Hannah
|
|
|
|
Second Notice | | 11/17/2013 | 11/27/2013 | | DONE |
|
|
|
|
First Notice | | 10/11/2013 | 11/7/2013 | | DONE |
|
|
|
faxed to GC
|
BLD-Final | 9/30/2013 | 10/1/2013 | 10/1/2013 | P | PASS |
Dave Hannah
|
|
|
Noelle Phone #: ###-####
|
BLD-Final | 9/27/2013 | 9/30/2013 | 10/1/2013 | P | PASS |
Dave Hannah
|
|
|
noelle Phone #: ###-####
|
Temporary Occupancy | 10/1/2013 | 12/30/2013 | 10/1/2013 | | DONE |
Tisha Gallop
|
|
|
This permit is to establish only temporary occupancy during the construction of the JUMP project. Per Jason Blais exp 1 yr. If need longer can request extension at that time.
|
FIRE-Final Inspection | 9/27/2013 | 9/30/2013 | 9/30/2013 | A | PASS |
Forrest France
|
|
|
C/N items finished. Life safety passed.
|
BLD-Final | 9/26/2013 | 9/27/2013 | 9/30/2013 | P | CANC |
Dave Hannah
|
|
|
noelle Phone #: ###-####
|
FIRE-Final Inspection | 9/26/2013 | 9/27/2013 | 9/27/2013 | A | FAIL |
Forrest France
|
|
|
Post fire extinguishers- one in the special use area, one in the storage area, provide "door to remain unlocked..." signage at the main entry/exit, install approved door hardware or remove non-required exit signs at three locations in the storage areas, remove extension cord powering appliances run through the wall and ceilings from the adjacent office space to the storage room.
|
BLD-Framing/Rough-in | 7/19/2013 | 7/22/2013 | 7/22/2013 | A | PASS |
Dave Hannah
|
|
|
Tim Phone #: ###-####
|
Issue PAID IN FULL permit | | | 1/16/2013 | | DONE |
Tisha Gallop
|
|
|
|
Plan assigned to (CJW) | 7/20/2012 | 7/20/2012 | 12/6/2012 | | PASS |
Carl Westfall
|
|
|
JUMP PROMOTIONAL AND STORAGE (20 days - Aug. 14)
|
Routing - PLAN CHECK | 12/5/2012 | | 12/6/2012 | | DONE |
Carl Westfall
|
|
|
Routing completed.
|
Routing - PUBLIC WORKS | 12/6/2012 | | 12/6/2012 | | PASS |
Connie Baumgartner
|
|
|
|
Routing PW Sewer Rating | 12/6/2012 | | 12/6/2012 | | PASS |
Connie Baumgartner
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/6/2012 | | DONE |
|
|
|
|
Print Occupancy Form | | | 12/6/2012 | | DONE |
Tisha Gallop
|
|
|
|
Telephone call | | | 12/6/2012 | | DONE |
|
|
|
LM permit ready fees given
|
Permit Ready to Issue | | | 12/6/2012 | | DONE |
|
|
|
|
Routing - FIRE | 12/4/2012 | | 12/5/2012 | | PASS |
Scott Arellano
|
|
|
Attached updated comments to plans.
|
Routing - PLAN CHECK | 12/3/2012 | | 12/4/2012 | | DONE |
Carl Westfall
|
|
|
Route to Fire.
|
Routing - Design Review | 12/3/2012 | | 12/3/2012 | | PASS |
Josh Wilson
|
|
|
|
Routing PW Drainage | 12/3/2012 | | 12/3/2012 | | PASS |
Brian Murphy
|
|
|
TI ONLY
|
Routing - PUBLIC WORKS | 12/3/2012 | | 12/3/2012 | | PASS |
Connie Baumgartner
|
|
|
|
Routing PW Solid Waste | 12/3/2012 | | 12/3/2012 | | PASS |
Peter J. McCullough
|
|
|
No changes to trash
|
Routing - PLAN CHECK | 10/26/2012 | | 12/3/2012 | | PASS |
Carl Westfall
|
|
|
The scope of work was significantly reduced. Drawings approved after the resubmittal review.
|
Plan resubmittals received | | | 11/27/2012 | | DONE |
|
|
|
rec'd two copies of sheets a0.01; a0.02; a0.03; a0.04; a0.05; a0.06; a0.07; a0.08; a0.09; a0.10; a1.11; a2.01; a2.11; a2.31; a3.21; a5.11; a6.11; s1.1; s2.1; s3.1- taken to carl w
|
Routing - PUBLIC WORKS | 10/9/2012 | | 10/26/2012 | | FAIL |
Connie Baumgartner
|
|
|
Failed by Brian Murphy
|
Routing PW Drainage | 10/9/2012 | | 10/22/2012 | | FAIL |
|
|
|
STILL WAITING FOR REVISIONS AND STRUC LETTER
|
Routing - PLAN CHECK | 10/3/2012 | | 10/9/2012 | | PASS |
Carl Westfall
|
|
|
Drawings approved after 3rd review.
|
Plan resubmittals received | | | 10/8/2012 | | DONE |
|
|
|
Rec'd five copies of civil sheets C1.01; C2.01; C3.01; C4.01; C5.01 and two copies of O&M and drainage report - taken to Carl W
|
Routing - PUBLIC WORKS | 10/1/2012 | | 10/3/2012 | | FAIL |
Connie Baumgartner
|
|
|
|
Routing PW Drainage | 10/2/2012 | | 10/3/2012 | | FAIL |
Brian Murphy
|
|
|
NO NEW DRAINAGE REVISIONS
|
Routing - PLANNING Land Div | 9/24/2012 | | 10/1/2012 | | PASS |
Todd Tucker
|
|
|
|
Route to Impact Fee Review | 8/22/2012 | 8/27/2012 | 9/25/2012 | | PASS |
Cindy M. Gould
|
|
|
remodile in existing building
|
Routing - PLAN CHECK | 9/10/2012 | | 9/24/2012 | | |
|
|
|
Directed to start routing again.
|
Routing - Design Review | 9/24/2012 | | 9/24/2012 | | PASS |
Josh Wilson
|
|
|
OK per CZC12-00196
|
Routing - PLAN CHECK | 8/27/2012 | | 9/10/2012 | | FAIL |
Carl Westfall
|
|
|
Completed the 2nd review. Waiting for more information.
|
Plan resubmittals received | | | 9/6/2012 | | |
|
|
|
9-6-12 received 2 response letters 2 calcs & 2 copies of sheets A0.01,A0.06,A0.10,A1.11,A2.41,A4.11,S2.1,MG2.10,M2.10,M3.10,E3.10,E4.10 sent to Carl W.
|
Routing - FIRE | 8/22/2012 | 8/22/2012 | 8/27/2012 | | PASS |
Scott Arellano
|
|
|
Attached review comments to plans.
|
1st review completed | | | 8/27/2012 | | FAIL |
|
|
|
Failed Public Works and Plan Check
|
Routing - PLAN CHECK | 7/31/2012 | | 8/22/2012 | | FAIL |
Carl Westfall
|
|
|
This plan review was actually completed on Aug. 16. Routing was delayed while the plan review for the adjacent tenant space was completed. Both permit are attached to the same set of drawings.
|
Routing - PLUMBING | 7/27/2012 | | 7/31/2012 | | PASS |
Bill VanDegrift
|
|
|
|
Routing - Design Review | 7/31/2012 | | 7/31/2012 | | PASS |
Josh Wilson
|
|
|
Josh Wilson - DRH12-00002
|
Routing - Erosion and Sediment | 7/26/2012 | | 7/27/2012 | | PASS |
Kimberly M. Johnson
|
|
|
ESC Permit 12-00403 approved for all phases of project. See conditions
|
Routing - PUBLIC WORKS | | | 7/26/2012 | | FAIL |
Beverly Mountain
|
|
|
Failed by Brian Murphy
|
Routing PW Drainage | 7/25/2012 | | 7/26/2012 | | FAIL |
Brian Murphy
|
|
|
NEEDS REVISIONS.
|
Routing PW Sewer Rating | 7/25/2012 | | 7/25/2012 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - Addressing | 7/20/2012 | | 7/24/2012 | | PASS |
April Wing
|
|
|
|
Pending Assignment by JCB | 7/18/2012 | | 7/20/2012 | | DONE |
Jason Blais
|
|
|
|
Plan Reviewer's activity | | | 7/20/2012 | | DONE |
Jason Blais
|
|
|
Emailed architect representative to contact ACHD for evaluation of any impact fees dues with the change in use. Also an ACHD license agreement needs to be completed for the existing building that encroaches into the right of way. All need to be provided prior to the building permit being issued.
|
Application received | | 7/18/2012 | 7/18/2012 | | DONE |
Christina Prado
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 7/18/2012 | | DONE |
Christina Prado
|
|
|
|
Intake Approval | | | 7/18/2012 | | PASS |
Tim L. Woodard
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 7/18/2012 | | DONE |
Christina Prado
|
|
|
|