First Notice | | 5/3/2013 | 7/2/2015 | | DONE |
|
|
|
This permit finaled on the web by Jeremy Amar
|
Zoning Approval | 4/23/2013 | 4/23/2013 | 4/23/2013 | | PASS |
Josh Wilson
|
|
|
|
Permanent Occupancy | | | 4/23/2013 | | DONE |
Barbara Stitt
|
|
|
|
BLD-Final | 2/22/2013 | 2/25/2013 | 2/25/2013 | A | PART |
Jim Sly
|
|
|
Pat Phone #: ###-#### OK for Temp Occ. OK for Perm Occ. when Zoning Perms.
|
Temporary Occupancy | 2/25/2013 | 5/26/2013 | 2/25/2013 | | DONE |
Darla L Downs
|
|
|
|
Telephone call | | | 2/25/2013 | | DONE |
Tisha Gallop
|
|
|
Per phone call from Kristi Heller at ACHD inspection completed and ok for perm occupancy//2/25/13 leg
|
Print Occupancy Form | | | 2/25/2013 | | DONE |
|
|
|
|
FIRE-Final Inspection | 2/22/2013 | 2/22/2013 | 2/22/2013 | P | PASS |
Jim Sly
|
|
|
pat Phone #: ###-#### Fire life safety....OK
|
Override - Parcel Holds | 2/22/2013 | 1/1/1900 | 2/22/2013 | | |
|
|
|
schedule for temp occupancy
|
Override - Parcel Holds | 2/22/2013 | 1/1/1900 | 2/22/2013 | | |
|
|
|
schedule temp final
|
Zoning Approval Temp | 2/14/2013 | 2/14/2013 | 2/14/2013 | | PASS |
Josh Wilson
|
|
|
180 day temp occ for completion of landscaping and parking lot striping. Bond received 2-14-13.
|
BLD-Other | 1/9/2013 | 1/9/2013 | 1/9/2013 | P | PASS |
Jim Sly
|
|
|
Sheet rock inspection-Pat Phone #: ###-#### 1st layer and metal channel....ok.
|
BLD-Energy code compliance | 1/8/2013 | 1/9/2013 | 1/9/2013 | P | PASS |
Jim Sly
|
|
|
Pat phone
|
BLD-Energy code compliance | 1/8/2013 | 1/8/2013 | 1/8/2013 | P | PART |
Jim Sly
|
|
|
pat Phone #: ###-#### Need to come back to look at sheetrock boxes at HVAC exhaust fans.
|
FIRE-Conference | 1/7/2013 | 1/7/2013 | 1/7/2013 | P | PASS |
Troy Cobbley
|
|
|
Sprinkler piping is ok to cover.
|
BLD-Framing/Rough-in | 1/4/2013 | 1/7/2013 | 1/7/2013 | A | PART |
Jim Sly
|
|
|
pat Phone #: ###-#### Framing OK ...need Fire Sprinkler rough- in and install sheetrock boxes around ceiling exhaust fans.
|
BLD-Wall Bracing | 12/10/2012 | 12/11/2012 | 12/11/2012 | P | PASS |
Jim Sly
|
|
|
Pat Phone #: ###-####
|
CHANGE STATUS TO (ISS) | | | 11/21/2012 | | DONE |
Barbara Stitt
|
|
|
|
(F) Reprint permit | | | 11/21/2012 | | DONE |
Barbara Stitt
|
|
|
|
Plan assigned to (SRZ) | 11/14/2012 | 11/14/2012 | 11/19/2012 | | PASS |
Sam Zahorka
|
|
|
|
Routing - PLAN CHECK | 11/14/2012 | | 11/19/2012 | | PASS |
Sam Zahorka
|
|
|
|
Inspection Record Card- Bld | | | 11/19/2012 | | DONE |
Christina Prado
|
|
|
|
Telephone call | | | 11/19/2012 | | DONE |
Christina Prado
|
|
|
left message with Angie at Biltmore giving fees due
|
Plan Modification Accepted | | | 11/14/2012 | | DONE |
Christina Prado
|
|
|
Plan Modification for the removal of sheetrock from corridor along with the front door ratings and to change the downstairs patio door from a single door to a glass slider. Sheets affected are S-1.8 & A-106. For inspections related to these changes see Sam Z.
|
BLD-Foundation | 10/22/2012 | 10/23/2012 | 10/23/2012 | P | PASS |
Jim Sly
|
|
|
Jim Phone #: ###-####
|
BLD-Footing | 10/19/2012 | 10/22/2012 | 10/22/2012 | A | PART |
Jim Sly
|
|
|
Pat Phone #: ###-#### Partial...excavation, forms and rebar for footing....OK Placement 11' from East line in leiu of 10' as shown on plan. Talked to Contr. Need approval From Planners for change prior to pour.
|
Issue PAID IN FULL permit | | | 9/17/2012 | | DONE |
Barbara Stitt
|
|
|
|
Route to Impact Fee Review | 9/14/2012 | 9/19/2012 | 9/14/2012 | | PASS |
Shauna Surgeon
|
|
|
|
Inspection Record Card- Bld | | | 9/14/2012 | | DONE |
Christina Prado
|
|
|
|
Permit Ready to Issue | | | 9/14/2012 | | |
|
|
|
|
Telephone call | | | 9/14/2012 | | |
|
|
|
9-14-12 called Kevin permit ready and fee given ///dld
|
Routing - PLAN CHECK | 8/28/2012 | | 9/13/2012 | | PASS |
Sam Zahorka
|
|
|
|
Routing PW Sewer Design | 9/13/2012 | | 9/13/2012 | | PASS |
Mike Sheppard
|
|
|
Revised sewer per request
|
Routing - PUBLIC WORKS | 9/13/2012 | | 9/13/2012 | | PASS |
Connie Baumgartner
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/13/2012 | | DONE |
Sam Zahorka
|
|
|
|
Plan assigned to (SRZ) | 7/19/2012 | | 9/13/2012 | | PASS |
Sam Zahorka
|
|
|
Pending Public Works to PASS.
|
Routing - Erosion and Sediment | 7/25/2012 | | 9/13/2012 | | PASS |
Clint A Smith
|
|
|
see BLD12-01909
|
Plan resubmittals received | | | 8/28/2012 | | DONE |
Tisha Gallop
|
|
|
received two copies of plan sheet A102; inserted by GC and taken back to Sam Z.
|
Routing - PUBLIC WORKS | 8/24/2012 | | 8/28/2012 | | FAIL |
Connie Baumgartner
|
|
|
Failed by Mike Sheppard for sewer design issues.
|
Routing PW Sewer Design | 8/24/2012 | | 8/27/2012 | | FAIL |
Mike Sheppard
|
|
|
|
Routing PW Solid Waste | 8/24/2012 | | 8/24/2012 | | PASS |
Peter J. McCullough
|
|
|
|
Routing - PLAN CHECK | 8/22/2012 | | 8/24/2012 | | PASS |
Sam Zahorka
|
|
|
|
1st review completed | | | 8/22/2012 | | FAIL |
|
|
|
Failed Public Works.
|
Routing - FIRE | 8/20/2012 | | 8/22/2012 | | PASS |
Scott Arellano
|
|
|
Attached review comments to plans.
|
Routing - PLAN CHECK | 8/1/2012 | | 8/20/2012 | | PASS |
Sam Zahorka
|
|
|
Sam Zahorka
|
Routing - MECHANICAL | 8/6/2012 | | 8/6/2012 | | PASS |
Troy James
|
|
|
|
Routing - MECHANICAL | 7/31/2012 | | 8/1/2012 | | FAIL |
Troy James
|
|
|
talked to alley air about corrections
|
Routing - PLANNING | 7/27/2012 | | 7/30/2012 | | PASS |
Josh Wilson
|
|
|
Ok with redlines sheets A104, A104., A104.2, A201, A202
|
Routing - PLUMBING | 7/26/2012 | | 7/27/2012 | | PASS |
Daryl Spivey
|
|
|
Each building is required to have a DCVA backflow installed on water service line.
Per 2003 UPC.
|
Routing - PUBLIC WORKS | 7/24/2012 | | 7/25/2012 | | FAIL |
Connie Baumgartner
|
|
|
Failed by Pamella Williams for trash enclosure issues
|
Routing PW Solid Waste | 7/24/2012 | | 7/25/2012 | | FAIL |
Pam Baldwin
|
|
|
Trash enclosure detail required, including orientation,dimensions, wind stops, gate opening.
|
Routing PW Sewer Rating | 7/23/2012 | | 7/24/2012 | | PASS |
Connie Baumgartner
|
|
|
|
Routing PW Drainage | 7/24/2012 | | 7/24/2012 | | PASS |
Brian Murphy
|
|
|
|
Routing - Addressing | 7/23/2012 | | 7/23/2012 | | PASS |
April Wing
|
|
|
Ste number see PW doc
|
Routing - PLANNING Land Div | 7/19/2012 | | 7/20/2012 | | PASS |
Dave Abo
|
|
|
Lot 27 of Clover Leaf Subdivision.
|
Application received | | 7/19/2012 | 7/19/2012 | | DONE |
Barbara Stitt
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 7/19/2012 | | DONE |
Barbara Stitt
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 7/19/2012 | | DONE |
Barbara Stitt
|
|
|
|
Intake Approval | | | 7/19/2012 | | PASS |
Sam Zahorka
|
|
|
|
Pending Assignment by JCM | 7/19/2012 | | 7/19/2012 | | DONE |
John Menard
|
|
|
|