Information based on query as of Friday, August 16, 2024.
Permit Information
Permit NumberBLD12-01911
StatusFinaled
Name BILTMORE COMPANY
Site Address 11904 W FAIRVIEW AVE
Project NameCLOVERLEAF PLAZA 4PLEX UNITS
Customer Number 
ePlanReviewNo
Description
Cloverleaf Plaza - Four-Plex (Lot 28) - *** 11-19-12 PLAN MODIFICATION TO INCLUDE: REMOVE THE 1-HOUR FIRE BARRIER WALL ASSEMBLIES, 1-HOUR HORIZONTAL ROOF CEILING ASSEMBLY AND OPENING PROTECTION AT THE EXIT PASSAGEWAY; CHANGE THE 1ST STORY PATIO DOOR TO GLASS SLIDER. SRZ*** To construct a new 3,812 sq. ft., two story, Four unit, apartment building. Each unit has a total of 953 square feet, two bedrooms, and two bathrooms. The 1st story units are required to be Type 'B' units. All four units share a common path of egress into and through a 1-hour exit corridor with 60 minute fire-resistive, listed, labeled, self-closing door assemblies from the dwelling units into the corridor. All construction per the approved plans, attached plan review report, and all other reviewing agencies approvals. One hour fire-partitions and one hour horizontal assemblies are required between dwelling units. This building is required to be fire sprinklered. The fire sprinkler system shall be per NFPA 13R as regulated by the fire department. DRH12-00142 Per Planning and Zoning. **SRZ**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
First Notice 5/4/20137/2/2015 DONE
This permit finaled on the web by Jeremy Amar
Permanent Occupancy  4/24/2013 DONE
DetailsBarbara Stitt
Zoning Approval4/23/20134/23/20134/23/2013 PASS
DetailsJosh Wilson
BLD-Final3/4/20133/4/20133/4/2013PPART
DetailsJim Sly
pat Phone #: ###-####
OK for Temp Occ. OK for Perm Occ when Zoning perms. Bond for Landscaping.
FIRE-Final Inspection3/1/20133/4/20133/4/2013APASS
DetailsTroy Cobbley
Life safety passed
Temporary Occupancy3/4/20136/2/20133/4/2013 DONE
DetailsDarla L Downs
Telephone call  2/25/2013 DONE
DetailsTisha Gallop
Per phone call from Kristi Heller at ACHD inspection completed and ok for perm occupancy//2/25/13 leg
Zoning Approval Temp2/14/20132/14/20132/14/2013 PASS
DetailsJosh Wilson
180 day temp occ for completion of landscaping and parking lot striping. Bond received 2-14-13.
BLD-Other1/29/20131/29/20131/29/2013PPASS
DetailsJim Sly
late as possible//sheetrock insp//Pat Phone #: ###-#### 1st layer and metal channel installed.
BLD-Energy code compliance1/28/20131/28/20131/28/2013PPART
DetailsJim Sly
pat Phone #: ###-####
Insulation OK........Need to see layers of gyp on lid.
BLD-Framing/Rough-in1/24/20131/24/20131/24/2013PPASS
DetailsJim Sly
pat Phone #: ###-####
BLD-Wall Bracing12/26/201212/27/201212/27/2012APASS
DetailsJim Sly
pat Phone #: ###-####
CHANGE STATUS TO (ISS)  11/21/2012 DONE
DetailsBarbara Stitt
(F) Reprint permit  11/21/2012 DONE
DetailsBarbara Stitt
Plan assigned to (SRZ)11/14/201211/14/201211/19/2012 PASS
DetailsSam Zahorka
Routing - PLAN CHECK11/14/2012 11/19/2012 PASS
DetailsSam Zahorka
Inspection Record Card- Bld  11/19/2012 DONE
DetailsChristina Prado
Telephone call  11/19/2012 DONE
DetailsChristina Prado
left message with Angie at Biltmore giving fees due
Plan Modification Accepted  11/14/2012 DONE
DetailsChristina Prado
Plan Modification for the removal of sheetrock from corridor along with the front door ratings and to change the downstairs patio door from a single door to a glass slider. Sheets affected are S-1.8 & A-106. For inspections related to these changes see Sam Z.
BLD-Foundation10/18/201210/19/201210/20/2012PPASS
DetailsJim Sly
found wall//Pat Phone #: ###-####
BLD-Footing10/17/201210/18/201210/18/2012APART
DetailsJim Sly
Pat Phone #: ###-####
Appears OK.......Not able to determine exact setback....No string line pulled.
BLD-Footing10/17/201210/17/201210/17/2012PNR
DetailsJim Sly
pat Phone #: ###-####
Needs to do more excavating.
Issue PAID IN FULL permit  9/17/2012 DONE
DetailsBarbara Stitt
Route to Impact Fee Review9/14/20129/19/20129/14/2012 PASS
DetailsShauna Surgeon
Inspection Record Card- Bld  9/14/2012 DONE
DetailsChristina Prado
Permit Ready to Issue  9/14/2012  
Telephone call  9/14/2012  
9-14-12 called Kevin permit ready and fee given ///dld
Routing - PLAN CHECK8/28/2012 9/13/2012 PASS
DetailsSam Zahorka
Routing PW Sewer Design9/13/2012 9/13/2012 PASS
DetailsMike Sheppard
Revised plans per comments
Routing - PUBLIC WORKS9/13/2012 9/13/2012 PASS
DetailsConnie Baumgartner
Routing - PLAN CHECK9/13/2012 9/13/2012 PASS
DetailsSam Zahorka
PLANS/APPL TAKEN TO FRONT DESK  9/13/2012 DONE
DetailsSam Zahorka
Plan assigned to (SRZ)7/19/2012 9/13/2012 PASS
DetailsSam Zahorka
Pending Public Works to PASS.
Routing - Erosion and Sediment7/25/2012 9/13/2012 PASS
DetailsClint A Smith
see BLD12-01909
Routing - PUBLIC WORKS8/24/2012 8/28/2012 FAIL
DetailsConnie Baumgartner
Failed by Mike Sheppard for sewer design issues.
Plan resubmittals received  8/28/2012 DONE
DetailsTisha Gallop
received two copies of plan sheet A102; inserted by GC and taken back to Sam Z.
Routing PW Sewer Design8/24/2012 8/27/2012 FAIL
DetailsMike Sheppard
Routing PW Solid Waste8/24/2012 8/24/2012 PASS
DetailsPeter J. McCullough
Routing - PLAN CHECK8/22/2012 8/24/2012 PASS
DetailsSam Zahorka
1st review completed  8/22/2012 FAIL
Failed Public Works
Routing - FIRE8/20/2012 8/22/2012 PASS
DetailsScott Arellano
Attached review comments to plans.
Routing - PLAN CHECK8/1/2012 8/20/2012 PASS
DetailsSam Zahorka
Sam Zahorka
Routing - MECHANICAL8/6/2012 8/6/2012 PASS
DetailsTroy James
Routing - MECHANICAL7/31/2012 8/1/2012 FAIL
DetailsTroy James
talked to alley air about corrections
Routing - PLANNING7/27/2012 7/30/2012 PASS
DetailsJosh Wilson
Ok with redlines sheets A104, A104., A104.2, A201, A202
Routing - PLUMBING7/26/2012 7/27/2012 PASS
DetailsDaryl Spivey
Each building required to have a DCVA backflow installed on water service line.
Per 2003 UPC.
Routing - PUBLIC WORKS7/24/2012 7/25/2012 FAIL
DetailsConnie Baumgartner
Failed by Pamella Williams for trash enclosure issues
Routing PW Solid Waste7/24/2012 7/25/2012 FAIL
DetailsPam Baldwin
Trash enclosure detail needed, including orientation, dimensions, wind stops, gate opening.
Routing PW Sewer Rating7/24/2012 7/24/2012 PASS
DetailsConnie Baumgartner
Routing PW Drainage7/24/2012 7/24/2012 PASS
DetailsBrian Murphy
Routing - Addressing7/23/2012 7/23/2012 PASS
DetailsApril Wing
Ste Numbers see PW doc
Routing - PLANNING Land Div7/19/2012 7/20/2012 PASS
DetailsDave Abo
Lot 28 of Clover Leaf Subdivision.
Application received 7/19/20127/19/2012 DONE
DetailsBarbara Stitt
Plans ACCEPTED BY PLAN TECH  7/19/2012 DONE
DetailsBarbara Stitt
Intake Approval  7/19/2012 PASS
DetailsSam Zahorka
Recd Pcfee & Taken To Pln CK  7/19/2012 DONE
DetailsBarbara Stitt
Pending Assignment by JCM7/19/2012 7/19/2012 DONE
DetailsJohn Menard