First Notice | | 12/23/2012 | 1/3/2013 | | DONE |
|
|
|
faxed
|
BLD-Final | 12/12/2012 | 12/13/2012 | 12/13/2012 | A | PASS |
Dave Hannah
|
|
|
ron Phone #: ###-####
|
Permanent Occupancy | | | 12/13/2012 | | DONE |
Christina Prado
|
|
|
|
FIRE-Final Inspection | 12/12/2012 | 12/12/2012 | 12/12/2012 | P | PASS |
Forrest France
|
|
|
Fire life safety final approved.
|
Change Expiration Date Only | | | 11/19/2012 | | DONE |
Barbara Stitt
|
|
|
|
BLD-Final | 11/8/2012 | 11/9/2012 | 11/9/2012 | A | PART |
Dave Hannah
|
|
|
call for access - Ron Phone #: ###-#### ok for temp occ ok for perm occ after other trades go perm
|
Temporary Occupancy | 11/9/2012 | 2/7/2013 | 11/9/2012 | | DONE |
Christina Prado
|
|
|
Per Romeo Gervais ok until 12-15-12
|
FIRE-Final Inspection | 11/8/2012 | 11/8/2012 | 11/8/2012 | A | PART |
Forrest France
|
|
|
Temp. occupancy granted with R. Gervais approval until 12/15/12. Final pending modifications to the existing building fire alarm system to accomodate adequate visual coverage at two locations.
|
FIRE-Final Inspection | 11/2/2012 | 11/5/2012 | 11/5/2012 | A | PART |
Forrest France
|
|
|
Fire life safety final pending modifications to the existing fire alarm system. Adjustments to maintatin notification coverage will be necessary due to the new floorplan. Remainder of fire life safety conditions are satisfactory.
|
FIRE-Final Inspection | 10/29/2012 | 10/29/2012 | 10/29/2012 | P | FAIL |
Forrest France
|
|
|
Type one hood failed to report to the FACP, modifications to the fire alarm system will be necessary to maintain coverage where new walls and partitions have been built, project related fire sprinkler permit needs called for inspection, noted one EM light to be repaired, relocate the K class PFE as discussed.
|
BLD-Framing/Rough-in | 9/5/2012 | 9/6/2012 | 9/6/2012 | A | PASS |
Dave Hannah
|
|
|
ron - call for access Phone #: ###-####
|
Issue PAID IN FULL permit | | | 8/24/2012 | | DONE |
Christina Prado
|
|
|
|
Routing - PLAN CHECK | 8/16/2012 | | 8/16/2012 | | PASS |
Tim L. Woodard
|
|
|
Approved with redines. TLW
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/16/2012 | | DONE |
Tim L. Woodard
|
|
|
|
Case Summary (BLD) | | | 8/16/2012 | | DONE |
Tim L. Woodard
|
|
|
|
Print Occupancy Form | | | 8/16/2012 | | DONE |
Christina Prado
|
|
|
|
Telephone call | | | 8/16/2012 | | DONE |
|
|
|
Spoke with Marvin permit ready fees given
|
Permit Ready to Issue | | | 8/16/2012 | | DONE |
|
|
|
|
Plan assigned to (TLW) | 7/24/2012 | | 8/16/2012 | | PASS |
Tim L. Woodard
|
|
|
|
Routing - PUBLIC WORKS | 8/14/2012 | | 8/15/2012 | | PASS |
Connie Baumgartner
|
|
|
|
Routing PW Environmental | 8/15/2012 | | 8/15/2012 | | PASS |
Walt Baumgartner
|
|
|
Mop sink should route to grease line if possible. Plans approved.
|
Routing PW Sewer Rating | 8/14/2012 | | 8/15/2012 | | PASS |
Connie Baumgartner
|
|
|
|
Plan resubmittals received | | | 8/13/2012 | | DONE |
Christina Prado
|
|
|
Received two sets of plans marked A2.11. Gave to Tim for further review
|
Routing - PUBLIC WORKS | 7/27/2012 | | 8/7/2012 | | FAIL |
Beverly Mountain
|
|
|
Failed by Environmental for grease abatement.
|
Routing - PLAN CHECK | | | 8/7/2012 | | PASS |
Tim L. Woodard
|
|
|
Approved with reduction in occupant load. TLW
|
Routing PW Sewer Rating | 7/30/2012 | | 8/7/2012 | | FAIL |
Beverly Mountain
|
|
|
Failed by environmental
|
Routing PW Environmental | 7/30/2012 | | 8/7/2012 | | FAIL |
Walt Baumgartner
|
|
|
No plumbing or grease abatement shown. Contact Terry Alber at ###-####
|
1st review completed | | | 8/7/2012 | | DONE |
Tim L. Woodard
|
|
|
|
Routing - Addressing | 7/24/2012 | | 7/26/2012 | | PASS |
Terry Records
|
|
|
|
Application received | | 7/23/2012 | 7/24/2012 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 7/24/2012 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 7/24/2012 | | DONE |
|
|
|
|